
5
2.4.2 Charge-Discharge Commissioning
step 1 Control the PCS startup through the background monitoring interface, close the ring network
cabinet, issue the PCS startup command, the PCS should be able to start normally, and
issue the PCS shutdown command, the PCS should be able to stop normally.
step 2 Through the background monitoring interface, take 100kW as the step, increase the PCS
power to the actual maximum dischargeable power, run for 10min, the intelligent unit board
should be able to distribute the power to the PCS normally. Observe that the voltage, current,
temperature and other parameters of the battery RACK in the battery container should be
normal. Observe all DC/DC voltage, current, and device temperature rise parameters. There
should be no abnormality. Observe PCS voltage, current, and device temperature rise
parameters. Set the PCS power to 0kW.
step 3 Through the background monitoring interface, take 200kW as the step, increase the PCS
power to the actual maximum rechargeable power, run for 10min, the intelligent unit board
should be able to distribute the power to the PCS normally. Observe that the voltage, current,
temperature and other parameters of the battery RACK in the battery container should be
normal. Observe all DC/DC voltage, current, and device temperature rise parameters. There
should be no abnormality. Observe PCS voltage, current, and device temperature rise
parameters.
step 4 Set a battery SOC upper limit value, charge with the actual maximum power that can be
charged, and observe that when the set SOC upper limit value is reached, the DC/DC
corresponding to RACK should be in a hot standby state.
step 5 Set a battery SOC lower limit value, discharge with the power that can actually discharge
the maximum power, observe that when the set SOC lower limit value is reached, the DC/
DC corresponding to RACK should be in a hot standby state.
step 6 The background monitoring interface issues the PCS startup command, the PCS should be
able to start normally, and the communication between the background and the PCS should
be cut off, and the PCS should be able to stop.
- - End
The upper/lower limit values set in steps 4 and 5 refer to the actual state of charge
of the battery RACK, select a value that can be reached in a short time, and
change the parameter back to the original setting value after the test is completed.
2.4.3 Charge-Discharge Cycle Commissioning
step 1 The background monitoring performs a full charge and full discharge cycle to calibrate the
battery SOC according to the actual charge/discharge situation of the battery RACK in the
battery container.
step 2 Observe that the voltage, current, temperature and other parameters of the battery RACK
during the charging and discharging process should be normal.
step 3 Observe that the PCS voltage, current, and device temperature rise parameters should be
normal.
- - End
Operation & Maintenance Instruction 2 Commissioning