Installation and Start-up LEX 1500 Connect Single Water Softener 3
Installation LEX 1500 Connect Single Water Softener
Mount the rotating flange (DN 20 - DN 32) in the installation. Observe the enclosed
additional mounting instructions for the flange!
Mount the bypass valve to the rotating flange (DN 20 to DN 32). Make sure that
the flange seal is seated properly.
Remove the John-Guest connection angle from the brine pipeline. Seal the
John-Guest connection angle into the control head and connect the brine pipe
previously directed out of the salt tank with the angle. Note: use only Teflon
tape as a sealant for the control head‘s male thread (synthetic thread!).
Fit the angle socket to the control head‘s flushing water connection piece (use
only Teflon tape as a sealant).When dividing the enclosed transparent hose,
make sure to have adequate lengths for the flushing and overflow connections.
Connect the corresponding transparent hose to the mounted angle socket (as
the flushing water connection piece is submitted to pipe pressure, use the
enclosed hose clamp). Direct the hose end to the on-site drain connection.
Fit both threaded unions hand-tight to the control head‘s connections + .
Ensure that the socket (marked with a label) is fitted with the check valve to the
inlet . Note:make sure that the strap of the Hall sensor at the control head‘s
outlet remains in place. Connect the flexible connection hoses ( to and
to — observe the correct direction of flow!) to the bypass valve‘s connections
and the control head‘s threaded unions without applying stresses.
Use the clamp to fit the second transparent hose to the safety overflow. Direct
the hose end to the on-site drain connection
Use the enclosed water hardness testing equipment to determine the raw water
hardness.
Observe the air gap according to EN 1717 and DIN 1988, part 100.
Advice: we recommend our tundish 0214.00.908 (accessory). Prior to star-
ting the device, fill the salt tank with regeneration salt and add 5 liters of water
up to the maximum filling quantity.
Slowly open the shut-off valves of the bypass valve. Vent the system at a draw-
off point.
Plug the four connectors in the control head on the backside of the control unit.
Observe the correct pin assignment
Fit the control unit to the control head‘s base.
The installation is completed.
Brine pipe
Angle socket
Shut-off
valve
Power supply
12VAC/500 mA
Chlorine generation
Motor Turbine
1.
2.
3.
4.
5.
6.
7.
8.
9.
Shut-off valve