1 Evaluation Module Overview
1.1 Introduction
The TPSF12C1EVM-FILTER evaluation module (EVM) is designed to conveniently evaluate the performance
of the TPSF12C1 active filter IC. The EVM helps to improve the CM EMI signature in single-phase AC power
systems.
The TPSF12C1 provides a low shunt impedance path for CM noise in the frequency range of interest for EMI
measurement and helps to meet prescribed limits for EMI standards, such as:
• CISPR 11, EN 55011 – Industrial, Scientific and Medical (ISM) applications
• CISPR 25, EN 55025 – Automotive applications
• CISPR 32, EN 55032 – Multimedia applications
Enabling up to 30 dB of CM noise reduction at the lower end of specified frequency ranges (for example, 100
kHz to 3 MHz) significantly reduces the footprint, volume, weight and cost of the CM filter implementation,
especially the CM choke components that are designed to attenuate lower-order harmonics – and hence are
large size. The TPSF12C1 senses the high-frequency noise on each power line using two Y-rated sense
capacitors and injects a noise-canceling current back into the power lines using a Y-rated inject capacitor. The
GND terminal of the EVM requires a direct, low-inductance connection to the chassis ground or Earth terminal of
the filter circuit.
1.2 Kit Contents
• A complete filter board (EVM) rated at 10 A, including the TPSF12C1 active EMI filter IC
• EVM Disclaimer Read Me
• High Voltage Read Me
1.3 Specifications
Table 1-1 lists the EVM specifications. The input accepts 120 VAC or 240 VAC standard single-phase mains
supply voltages. VVDD = 12 V, unless otherwise indicated.
Table 1-1. Electrical Performance Specifications
PARAMETER CONDITIONS MIN TYP MAX UNIT
INPUT CHARACTERISTICS – EMI FILTER BOARD
Filter input voltage, VAC 85 240 265 VRMS
Filter rated current, IAC 10 ARMS
INPUT CHARACTERISTICS – TPSF12C1 AEF IC
VDD supply voltage, VVDD (1) 8 12 16
VVDD UVLO turn-on threshold, VVDD(on) VVDD rising 7.7
VDD UVLO turn-off threshold, VVDD(off) VVDD falling 6.7
VDD supply current, enabled, IVDD(on) EN open or tied high 12.5 mA
VDD supply current, disabled, IVDD(off) EN tied to GND 50 µA
OUTPUT CHARACTERISTICS – TPSF12C1 AEF IC
Inject voltage, VINJ (2) 2.5 VVDD – 2 V
Inject current, IINJ VVDD = 8 V to 16 V –80 80 mA
SYSTEM CHARACTERISTICS
Common-mode EMI reduction(3) 150 kHz to 1 MHz 20 dB
Ambient temperature, TA–40 85 °C
IC junction temperature, TJ–40 150
(1) The nominal VDD supply voltage (relative to chassis GND) of the TPSF12C1 is 12 V.
(2) Verify that the INJ pin voltage swing is between the prescribed limits to avoid saturation and clipping.
(3) The expected EMI reduction with this EVM is up to 30 dB (with the TPSF12C1 enabled vs. disabled) when swept from 100 kHz
to 3 MHz. This performance metric can change based on the VDD supply voltage, passive filter component values, active circuit
compensation and damping component values, ambient temperature, and other parameters.
Evaluation Module Overview www.ti.com
2Active EMI Filter Evaluation Module for Single-Phase AC Power Systems SLVUCQ2A – JULY 2023 – REVISED JULY 2023
Submit Document Feedback
Copyright © 2023 Texas Instruments Incorporated