WebDT Mobile Tablet Barcode Scanner Operation Guide
MobilesTablet
Barcode Scanner
Buon Management
The default scanner trigger buon is at right side. To
assign Scanner Trigger buon, follow the procedures
below.
1. Start Buon Manager by clicking on in the
system tray.
2. Select an available unused buon marked with the
icon .
3. Click on to go to the second screen of Buon Manager.
4. Click on the icon to assign the Scanner Trigger to the unused buon.
5. Click OK to apply conguraon sengs and close the window.
Installaon
The Barcode Scanner is preinstalled as an opon for DT 392.
DT 392 OPERATION GUIDE
Scanner 1/2
Barcode Scanner
Trigger Buon
Scanner Conguraon
To Add/Remove Symbologies, follow the procedures below.
1. Click Start | All Programs | DT Research | Buon
Manager | ScannerCong.
2. Select COM3 and click Connect buon.
3. Add Symbology with buon and Remove
Symbology with buon.
4. Select the Beep aer scanning barcode checkbox to
enable beep sound aer scanning bar code or deselect
it to disable the beep sound.
5. Click OK to apply the conguraon sengs and close
the window.
Note: Adding only the symbologies you need for tesng will give the best results. Adding too many
symbologies all at the same me will inuence performance.