WHEELTRONIC SPACESAVER 9000 Series User manual

READ THIS INSTRUCTION MANUAL THOROUGHLY BEFORE
INSTALLING, OPERATING, SERVICING OR MAINTAINING
THE LIFT. SAVE THIS MANUAL.
NOV 2007 REV.B
INSTALLATION
and OPERATION
MANUAL
6-0606
SPACESAVER
9000 SERIES
SPACESAVER
9000 SERIES
6500 MILLCREEK DRIVE,
MISSISSAUGA, ONTARIO L5N 2W6
TEL: 905-826-8600 * FAX: 905-826-7800

2 of 31
TABLE OF CONTENTS PAGE
1IMPORTANT SAFETY INSTRUCTIONS........................................................................3
2SAFETY WARNING DECALS...........................................................................................5
3SPECIFICATIONS...............................................................................................................6
4CONTENTS...........................................................................................................................7
5TOOLS REQUIRED FOR INSTALLATION:..................................................................8
6INSTALLATION INSTRUCTIONS...................................................................................8
6.1 BAY LAYOUT................................................................................................................9
6.2 UNPACKING PROCEDURE.....................................................................................10
6.3 HYDRAULIC INSTALLATION................................................................................10
6.4 ELECTRICAL INSTALLATION..............................................................................11
6.5 MECHANICAL SAFETY INSTALLATION............................................................12
6.6 REAR TIE BAR INSTALLATION............................................................................14
6.7 LEVELLING PROCEDURE......................................................................................14
6.8 ANCHORING PROCEDURE:...................................................................................15
6.9 INSTALLATION FOR ALIGNMENT MODELS 9004, AND 9005.......................16
6.10 INSTALLATION FOR ALL MODELS.................................................................17
7OPERATING INSTRUCTIONS:......................................................................................17
7.1 RAISING THE LIFT:..................................................................................................17
7.2 LOWERING THE LIFT:............................................................................................18
8FINAL CHECK OF ASSEMBLED LIFT........................................................................19
9OPERATION TEST WITH VEHICLE............................................................................19
10 RECOMMENDED MAINTENANCE:..........................................................................20
11 PARTS MANUAL ...........................................................................................................21
11.1 SPACE SAVER ALIGNMENT...............................................................................21
11.2 SPACE SAVER ALIGNMENT MAIN FRAME ASSEMBLY - PART LIST....22
11.3 SPACE SAVER SERVICE & RUST PROOFER..................................................24
11.4 SPACE SAVER MAIN FRAME ASSEMBLY, SERVICE & RUST PROOFER25
11.5 SPACE SAVER OPTIONS......................................................................................26
11.6 SPACE SAVER - OPTIONS PART LIST..............................................................27
11.7 SPACE SAVER HYDRAULICS .............................................................................28
11.8 SPACE SAVER - HYDRAULICS PART LIST.....................................................29
11.9 9,000 LB SPACE SAVER POWER PACK.............................................................30
11.10 9,000 LB SPACE SAVER POWER PACK - PARTS LIST..................................31

3 of 31
1 IMPORTANT SAFETY INSTRUCTIONS
When using this lift, basic safety precautions should always be followed, including the following:
1. Read all instructions in this manual and on the lift thoroughly before installing, operating,
servicing or maintaining the lift.
2. Inspect lift daily. Do not operate if it malfunctions or problems have been encountered.
3. Never attempt to overload the lift. The manufacturer’s rated capacity is shown on the
identification label on the power side column. Do not override the operating controls or
the safety devices.
4. Only trained and authorized personnel should operate the lift. Do not allow customers or
bystanders to operate the lift or be in the lift area.
5. Caution! Never work under the lift unless the mechanical safety locks are engaged.
6. Always keep the lift area free of obstruction and debris. Grease and oil spills should
always be cleaned up immediately.
7. Never raise vehicle with passengers inside.
8. Before lowering check area for any obstructions.
9. To protect against the risk of fire, do not operate lift in the vicinity of opencontainers of
flammable liquids.
10. Adequate ventilation should be provided when working on internal combustion engines.
11. Never open hydraulic lines under pressure.
SAVE THESE INSTRUCTIONS

4 of 31
Installation shall be performed in accordance with ANSO/ALI ALIS, Safety Requirements for
Installation and Service of Automotive Lifts.
For additional safety instructions regarding lifting, lift types, warning labels, preparing to lift,
vehicle spotting, vehicle lifting, maintaining load stability, emergency procedures, vehicle
lowering, lift limitations, lift maintenance, good shop practices, installation, operator training
and owner/employer responsibilities, please refer to “Lifting It Right” (ALI/SM) and “Safety
Tips” (ALI/ST).
For additional instruction on general requirements for lift operation, please refer to “Automotive
Lift-Safety Requirements For Operation, Inspection and Maintenance” (ANSI/ALI ALOIM).
ATTENTION! This lift is intended for indoor installation only. It is
prohibited to install this product outdoors. Operating environment
temperature range should be 41 – 104 °F (5 – 40 °C). Failure to adhere will
result in decertification, loss of warranty, and possible damage to the
equipment.

5 of 31
2 SAFETY WARNING DECALS
Be sure the operator is aware and underastands all safety warning lables and follows them
accordingly.

6 of 31
SPACE SAVER 9000 SERIES
3 SPECIFICATIONS
Maximum Capacity: 9000 lbs. 4100kg
Overall Width: 84” 2134mm
Width Between Runways: 36” 914mm
Overall Length ”A” (9004 - 144”W/B): 221” 5613mm
Overall Length “A” (9005 - 172”W/B): 264” 6706mm
Overall Length “A” (9000 - 144”W/B): 213” 5410mm
Overall Length “A” (9006 - 172”W/B): 256” 6502mm
Max. Raised Height: 72” 1829mm
Min. Lowered Height: 8 3/4” 222mm
Lifting Time: 60 Sec.
Power Requirements (Standard): 230 Volts, 1Ph., 60Hz.
Shipping Weight (144”W/B): 3450 lbs. 1804 kg
Shipping Weight (172”W/B): 4180 lbs. 1900 kg
Figure 1. Lift dimensions

7 of 31
4 CONTENTS
CHECK CONTENTS OF ACCESSORY BOX WITH PACKING LIST ENCLOSED IN BOX.
The complete lift is contained in two (2) packages:
1. The main structural components are pre-assembled and packaged one on top of the other.
2. The remaining parts are packed in an accessory box.
Main Structural Components:
1pc. - Left Side Main Frame Assembly; Runway, Scissors and Base Frame
1pc. - Right Side Main Frame Assembly; Runway, Scissors and Base Frame
Note: Hydraulic lines in base frames have been factory installed
Accessory Box Contents:
1pc. - Power Pack (with flow control)
2pcs. - Approach Ramps
2pcs. - Front Wheel Stops
1pc. - Standard Rear Tie Bar
1pc. - Front Tie Bar (9000, 9005, 9006)
2pcs. - Ramp Pins
2pcs. - Safety Toe Guard
2pcs. - Safety Release Pedal
2pcs. - Mechanical Safety Release Rod
1pc. - Mechanical Safety Release Connecting Rod
2pcs. - Safety Release Tab
5pcs. - Hydraulic Line Covers
1pc. - Center Cover
1pc. - Center Hydraulic Line
3pc. - Recoil Hose
2pcs. - 3/8” Hydraulic Tubing (20’ LG.)
2pcs. - Front Levelling Leg Bracket - Inside (9004, 9005)
4pcs. - Levelling Leg Bracket - Outside (9004, 9005)
4pcs. - Locking Plunger (9004, 9005)
4pcs. - Levelling Leg (9004, 9005)
8pcs. - Shim Plate, 1/16”thk.
8pcs. - Shim Plate, 1/8”thk.
8pcs. - Shim Plate, 1/4”thk.
1pc. - Installation Hardware Kit (comes with separate packing list)
1pc. - Assembly Hardware Kit (comes with separate packing list)
1pc. - Owners Manual
1pc. - ALI manual “Lifting It Right”
1pc. - Automotive Lift Safety Tips
1pc. - Automotive Lift, Operation, Inspection, and Maintenance manual

8 of 31
5 TOOLS REQUIRED FOR INSTALLATION:
* Rotary Hammer Drill or Similar, ¼" and ½” Concrete Drill Bits
* 4' Level
* SAE Wrenches and Sockets
* Hammer (for anchor installation)
* Pry Bar (for shim installation)
* Chalk Line (for lift location)
* Tape Measure
* Side Cutters (to cut shipping straps)
* Screw Drivers
* Tube bender
* Tube cutter
* Flaring Tool (single flare) 37°JIC
* Hydraulic Fluid ISO 32 (10 weight hydraulic oil) - (20 liters / 5.3Gal.)
* 25’ hose ¼” hydraulic hose, 3/8” JIC female fitting each end
6 INSTALLATION INSTRUCTIONS
When the lift arrives on site, please read the owner’s manual completely. Check the
contents to make sure no parts are missing before starting installation. Gather all the tools listed
and make sure the installation instructions are fully understood before commencing with the
installation.
IMPORTANT: It is the user’s responsibility to provide a satisfactory installation area for
the lift. Lifts should only be installed on level concrete floors with a minimum thickness of
five (5) inches or 130 mm. Concrete must have a minimum strength of 4000 psi or 30 MPa
and should be aged thirty (30) days prior to installation. Please consult the architect,
contractor or engineer if doubt exists as to the strength and feasibility of the floor to enable
proper lift installation and operation.
It is the user’s responsibility to provide all wiring for electrical hook-up prior to installation
and to insure that the electrical installation conforms to local building codes. Where
required, it is the user’s responsibility to provide an electrical isolation switch located in
close proximity to the lift that will enable emergency stop capability and isolate electrical
power from the lift for any servicing requirements.

9 of 31
6.1 BAY LAYOUT
Figure 2. Typical bay layout
NOTE: Leave any additional room for any desired aisle or work area. Recommended clearance
around the lift is a minimum of three (3) feet. Ensure clearance conforms to local building and
fire codes.
Recommended overhead clearance is a minimum of twelve (12) foot ceiling providing 6 feet for
the maximum lift height and 6 feet for the supported vehicle. For vehicles taller than 6 feet it is
recommended that the user provides additional overhead clearance or a shut off mechanism to
stop the lift from raising the vehicle too high.
IMPORTANT: DO NOT UNBOLT SHIPPING CLAMPS HOLDING EACH MAIN
FRAME ASSEMBLY TOGETHER UNTIL INSTRUCTED TO DO SO.

10 of 31
1. After selecting the location best suited for your lift, draw a line parallel to the front of the
lift, approximately 72” (1829mm) back from the cabinet/work bench area. This will be
the approximate location of the front of the lift. Refer to Figure 2.
NOTE: Check the installation area for obstructions. (Overhead; light fixtures, heating ducts,
ceiling, and In-ground; floor drains, electrical, etc...)
2. Mark on the floor an outline matching the dimensions listed.
SPACE SAVER - Alignment Model 9004: 144"(3658mm) Wheel Base. 221"(5613mm) x
84"(2134mm).
9000 SERIES - Alignment Model 9005: 172"(4369mm) Wheel Base. 264"(6706mm) x
84"(2134mm).
- Service Model 9000: 144"(3658mm) Wheel Base. 213"(5410mm) x
84"(2134mm).
- Service Model 9006: 172"(4369mm) Wheel Base. 256"(6502mm) x
84"(2134mm).
3. Draw a center line down the middle of the outline starting at the front of the lift location
and ending at the rear approach ramps.
4. Draw two lines parallel to the center line 18” (457mm) on either side to locate the inside
of the baseframes.
5. Draw a line parallel to the front of the lift, 39” (991mm) back for 144”W/B models and
52” (1321mm) back for 172”W/B models. Align the front of each base frame assembly onto
this line.
6. Check the floor in the outline for the highest point using a four (4) foot level. Mark this
location, reference will be made to it later during the leveling procedure.
6.2 UNPACKING PROCEDURE
1. Cut and remove the metal banding straps that hold the accessory box (and sliding Jack
Beams if so equipped) and place in a convenient location near the installation area.
2. Cut and remove the metal banding straps surrounding the Two Main Frame Assemblies.
Position the Main Frame Assemblies in the location previously marked in the bay layout.
NOTE: To distinguish between the left and right Main Frame Assemblies the pull-out step
should be located at the front facing outward from the lift. All measurements are to be
taken from the front of the lift.
3. Check that the inside of the base frames are 18" (457mm) away from the center line at
both the front and rear of each mainframe assembly and that the front of each base frame
is on the line drawn in step 5 of the bay layout, section 4.1.
6.3 HYDRAULIC INSTALLATION

11 of 31
NOTE: When working with hydraulics it is important to keep all components clean. All
hydraulic connections are 37 ½° JIC flares.
1. Select a position best suited for the power pack.
2. Remove the breather filler cap and fill with 20liters/5.3Gal. of ISO 32 hydraulic fluid.
3. Using a hydraulic tube bender, run a hydraulic line from the power pack to the hydraulic
inlet fitting located on the left side of the left base frame. After all the lines are cut and
formed, install the nuts and sleeves, and then flare the ends of the tube.
4. If you have purchased the factory air kit option you should now cut and form the air supply
line, from the lift to the desired location for customer connection to their shop air supply.
The air supply line should have an operating pressure of 90-120psi (6-8 bar).
5. Tighten all the supply lines. You may now anchor the hydraulic power pack. (floor or
wall mount).
6. Connect one end of the center hydraulic line to the outlet side of the left main frame
assembly and the other end to the inlet side of the right main frame assembly. Tighten
the hydraulic line in place so that it runs along the floor giving it a low profile.
IMPORTANT: THE SHIPPING CLAMPS HOLDING EACH MAIN FRAME ASSEMBLY
TOGETHER MUST BE UNBOLTED BEFORE CONNECTING ELECTRICAL POWER.
THERE ARE TWO (2) CLAMPS ON EACH ASSEMBLY.
6.4 ELECTRICAL INSTALLATION
IMPORTANT: ALL FINAL ELECTRICAL CONNECTIONS SHOULD BE
MADE BY A QUALIFIED ELECTRICIAN.
Please refer to Figure 3, the electrical diagram. Select a position for the remote hand
control pendant to be hung from the ceiling. Hang in a position so the safety pedal may
be easily reached.
NOTE: THE CONTROL PENDANT SHALL BE INSTALLED IN SUCH A
MANNER THAT THE CONTROL PENDANT CANNOT ENTER THE 18” HIGH
LEVEL ABOVE THE FLOOR.
(CLASS 1, DIVISION 2, HAZARDOUS LOCATIONS)

12 of 31
Figure 3. electrical Schematic, 230 Volt, 1Ph. 60 Hz
NOTE: Optional voltage and phase type power units will come with their own wiring diagram.
IMPORTANT: WITH THE MAIN ELECTRICAL SUPPLY CONNECTED, PRESS THE
UP CONTROL BUTTON TO RAISE THE LIFT 10” (254mm). STOP,
THEN PRESS THE DOWN CONTROL BUTTON TO LOWER THE
LIFT. REPEAT THIS PROCEDURE THREE (3) TIMES TO RELIEVE
AIR FROM THE HYDRAULIC SYSTEM. CHECK FOR HYDRAULIC
LEAKS AT ALL CONNECTIONS.
6.5 MECHANICAL SAFETY INSTALLATION
1. Locate the two (2) mechanical safety release rods and one (1) mechanical safety release
connecting rod.
2. Raise the lift by pressing the up button on the hand control.
3. Turn off the power supply to the power pack.
4. Slide each mechanical safety release rod through the holes closest to the rear of each
baseframe.

13 of 31
5. Slot in end of the bar should be parallel to the ground when center cut-out points up
towards the front. Refer to Figure 4.
Figure 4. Safety release rod location
6. Install the rectangular safety release tab using 2; ¼" - 20UNC x ¾" long hex bolts and
lock washers. The safety release tab bolts to the flat surface of the safety release rod
located under the mechanical safety locking bar.
7. Install foot pedals one on the outside of each safety release rod, using for each pedal 2;
¼" - 20UNC x 1¼" long hex bolts, nuts, and lock washers.
8. Install pedal safety guards. One on each baseframe using the ¼" - 20UNC x ¾" long hex
bolts, nuts, and lock washers.
9. Install the safety release connecting rod between the safety release rods, using
¼" - 20 UNC x 1 ¼" long hex bolt, nut and lock washers one on each end of the rod.
10. Tighten all installation hardware.
11. Place the mechanical safety locking bars back in their engaging positions.
Turn power back on.
12. FOR THOSE UNITS EQUIPPED WITH SLIDING JACK BEAMS NOW IS THE
TIME TO INSTALL THE JACK. Lower lift and consult instructions supplied with each
Jacking Beam.
13. Turn on the shop air supply and check for leaks. The air supply line should have an
operating pressure of 90-120psi (6-8bar).

14 of 31
6.6 REAR TIE BAR INSTALLATION
1. Raise lift to working height and lower onto safety.
2. Have 2; ½”-13UNC x 1½” long hex head bolts, flatwashers, lockwashers and nuts ready
to support the tie bar when it is raised into place.
3. Raise the rear tie bar into place making sure the slotted holes are up and the nose-like
protrusions are pointing toward the front of the units. The vertical members on the tube
should be on the outside of the deck skirts. Line up each vertical section slot with the
respective slot on the deck and place the bolts with washers through, one on each side.
Put the flatwashers and lockwashers and nuts on the inside of the decks.
DO NOT TIGHTEN!
4. Install 2; ½”-13UNC x 1½” long hex bolts, flatwashers and lockwashers to each end of
the tie bar positioned under the deck. DO NOT TIGHTEN!
5. Now install the remaining 6; ½”-13UNC x 1½” long hex bolts, flatwashers, and
lockwashers to the tie bar. DO NOT TIGHTEN! Baseframes should be level before
tightening, Refer to leveling procedure (following section).
6.7 LEVELLING PROCEDURE
NOTE: This is a very important procedure and time must be taken to do it correctly.
1. The highest point on the floor, noted from Section 4.1 step 6 is the point from which the
base frame will be levelled from. A quick check using a four (4) foot level across the
base frame should again verify that this is the highest point.
2. Starting at the corner closest to the highest point, check along the length of the base
frame edge with the four foot level and shim as required. NOTE THE FIVE CRITICAL
POSITIONS THAT SHIMS MUST BE PLACED ON EACH BASE FRAME OF
EACH MAIN FRAME ASSEMBLY. Refer to Figure 5.
3. Continue shimming across that base frame from side to side, and front to rear.
4. Once one frame is completely leveled, level the inside rails of the base frames to one
another.
5. Now level the remaining outside half of the last base frame by placing the level across
that unit and shimming as required.
6. A quick check across, along and between each base frame will ensure the levelling
procedure was carried out successfully. Re-adjust the tie bars if necessary.
LEVELLING EXAMPLE: FIGURE 5
Assuming that the front right corner is the highest point level in the following order:
- Shim along side “A”
- Shim across from side “A” to side “B” (check along side “B” from front to back)

15 of 31
The Right Side base frame should now be levelled.
- Shim across from side “B” to side “C” (check along side “C” from front to back)
- Shim across from side “C” to side “D” (check along side “D” from front to back)
- Shim along side E & side F (locking Mechanism)
Both base frames should now be levelled from front to back and side to side.
NOTE: Base frame levelling should be performed as a reference before main levelling of the
decks.One last check before anchoring is to make sure that there is 36” between the
baseframes.
Figure 5. Leveling procedure example
6.8 ANCHORING PROCEDURE:
1. Raise the lift to full height and repeat the measurements, and ensure there are no
differences.
2. Using a rotary hammer drill and a 1/2” concrete bit, drill through the floor at each of the
six (6) anchor bolt locations on each of the base frames. Make sure that the 1/2” concrete
drill bit is in good condition. Refer to Figure 6.
3. Assemble the nut and washer onto the 1/2” x 4 1/2” long wedge anchor bolts supplied. A
minimum of six threads must be visible below the surface of the nut.
4. Clean out the drilling dust from the holes and hammer in the anchors until they make
contact with the baseplate. Hand tighten all anchor bolts.
5. Torque all anchor bolts to 55 ft-lbs.
6. Position the console in the final desired location. Using a rotary hammer drill and a 1/4”
concrete bit, drill and anchor the console to the floor using the Nail in Anchors located in
the hardware kit.
7. Use the line covers to protect all cables, hoses, and wiring running to the lift. Using a
rotary hammer drill and a ¼” concrete bit, drill and anchor the line covers using the nail
in anchors located in the hardware kit.

16 of 31
8. With all anchor bolts torqued as specified operate the lift checking its full operation.
If anchor bolts do not tighten to 55 ft-lbs. OR project more than 2 ¼” above the concrete
surface, the concrete should be replaced by an appropriate concrete pad. (Consult Product
Manufacturer / Supplier for further details
Figure 6. Anchoring
6.9 INSTALLATION FOR ALIGNMENT MODELS 9004, AND 9005
1. Locate and install two (2) front wheel stops; one (1) to the front of each of the runways
using six long hex head bolts, flat washers, lock washers, and nuts.
NOTE: The 9005 has a front tie bar which must be installed in between the front of the deck
and the front wheel stop.
2. Unpack the levelling legs as marked on the leg and mounting hardware and place in their
respective locations. NOTE: On the long alignment models (9005) the rear levelling
legs fold up toward the rear, whereas, on the shorter alignment model (9004) the legs fold
up toward the front of the lift.
3. Position but do not tighten all levelling leg brackets. The levelling legs should hang in
the brackets and swing freely. Thrust washers are provided to take up any side play in legs,
install if required. Install thrust washers if there is more than 1/8”(3mm) clearance.
4. Check that legs hang perpendicular to the ground BEFORE tightening leg bracket bolts.
5. Lower the Space Saver lift down onto the levelling legs.
6. Check and adjust the decks for level using the 4’ level. Adjusting screw and jam nuts
should be adjusted until each corner of lift is level. Make sure jam nuts are tightened after
levelling. Both the front turn plate cutouts and rear slip plates should be checked. Refer
to Figure 7.

17 of 31
Figure 7. Deck leveling
6.10 INSTALLATION FOR ALL MODELS
1. Locate and install the center cover over the mechanical safety release connecting rod and
hydraulic line. Install using four (4), ¼" - 20 UNC x ¾" long hex head bolts, flat washers
and lock washers.
2. Check to make sure that the safety release connecting rod does not rub or bind during
operation.
3. Locate and install protective line covers over all air and hydraulic supply lines on the left
side base frame of the left main frame assembly.
4. Using a rotary hammer drill and a ¼" concrete drill bit, drill all line cover locations.
Using the ¼" concrete nails supplied fasten the line covers to the floor.
5. Install the approach ramps using ramp pins, washers, and cotter pins.
6. Tighten all bolts on crossmember(s).
7 OPERATING INSTRUCTIONS:
7.1 RAISING THE LIFT:
1. If the lift is equipped with Sliding Jack Beam(s) be sure that the Beam(s) are positioned
at the front or mid travel of the lift, fully down, with the risers removed and stored.
Never store Jack Beam(s) at the rear of the lift.
2. Be sure that the lift is fully lowered before attempting to load or unload a vehicle.

18 of 31
3. Position the vehicle on the lift ensuring the resulting load on each runway is as equal as
possible. Under no circumstances should a vehicle be lifted if the weight distribution is
unbalanced by 10% on either side of the center line between the runway.
NOTE: The vehicle is positioned correctly when the distance from the center of the tires to the
inside edge of the runways is equal on both runways, for the front and rear tires.
4. Check that there are no obstructions above the lift that could damage the lift or vehicles.
5. Raise the lift by pressing the up button on the remote pendant control. Raise the lift up,
continue to raise, past the desired working height until the mechanical safety drops into
position. Stop raising, now press the down button to lower the lift down onto both of the
mechanical safeties.
NOTE: NEVER WORK UNDER A VEHICLE OR THE LIFT UNLESS IT IS POSITIONED
ON BOTH MECHANICAL SAFETIES!!!
7.2 LOWERING THE LIFT:
1. Check that there are no obstructions under the lift or vehicle. Be sure that the Sliding
Jack Beams are fully lowered and positioned at the front or mid section of the lift.
2. Raise the lift by pressing the up button until the mechanical safety bars are off of their
stops. Stop raising.
3. Depress the safety release pedal to disengage the mechanical safety locking bars.
Continue to hold the pedal depressing the down button on the remote pendant control.
4. Continue lowering until the lift is approximately 34" (864mm) above the floor. Then
release the mechanical safety release pedal, allowing the mechanical safety locking bars
to be readied for their next use. Continue to depress the down button until the lift is
completely lowered.
NOTE: The operator must always keep their attention on the operation of the lift while
raising or lowering.
5. Be sure that the lift is completely lowered before removing the vehicle from the lift.

19 of 31
8 FINAL CHECK OF ASSEMBLED LIFT
1. Final dimension check after anchoring. ____
2. Check for hydraulic leaks. ____
3. Re-check level of decks, front to rear, side to side. ____
4. Check torque of anchor bolts. ____
5. Check all fasteners, tighten if necessary. ____
6. Operate lift to full stroke then lower to ground while checking ____
for proper functionality.
7. Ensure Customer Care Kit is complete and given to operator. ____
a.Operation Manual ____
b.ANSI / ALI Lift It Right Manual ____
c.ANSI / ALI Safety Tip Card ____
d.ANSI / ALI ALIS Safety Requirements for Installation ____
and Service of Automotive Lifts
e.ANSI / ALI Quick Reference Guide ____
8. Train end user on operation of lift. ____
9 OPERATION TEST WITH VEHICLE
1. Lower lift to ground.
2. Drive vehicle on to lift.
3. Raise lift to and lower onto 3-4 lock positions during full rise to ensure all locks are
working correctly.
4. Check lowering speed and smooth decent rate.
5. Lower lift to ground and drive vehicle off lift.
If any problems occur during the final checkout or operation of the lift please contact customer
service at 1-800-268-7959

20 of 31
10 RECOMMENDED MAINTENANCE:
1. Adjust level of lift daily.
2. The lift should be greased at least once every two months. There are six (6) points on
each lift that will take grease: four (4) on the scissors hinges and one on each of the
two (2) hydraulic cylinder rod eyelet’s.
3. The fluid level in the reservoir should be checked periodically. Be sure that the lift is
fully lowered when checking. The hydraulic fluids should be changed once every five
years. Use only ISO 32 hydraulic fluid.
4. The roller tracks should always be kept clean and free of debris. This area should be
checked before any raising or lowering of the lift.
5. Inspect the operation of the lift daily. Raise and lower fully.
6. Inspect electrical and mechanical operations of all switches, electrical and mechanical.
7. Lifts equipped with full floating rear slip plates and front radius turning plates, require to
be disassembled and cleaned once every 3 months. More frequently with lifts that are in
areas with more exposure to sand and salt.
NOTE: Locking pins should always be installed on front and rear plates before attempting
to drive a vehicle on or off the lift.
8. If uneven lifting occurs as described in section 5.1.3 the crossmember(s) will need to be
re-adjusted.
Quarterly Slip Plate Maintenance
1. Remove top Slip Plate covers by first removing the four (4) shoulder bolts on each cover.
2. Remove polyethylene bearing cages insuring that all the delrin bearings remain in the
cages. Additional delrin bearings may be purchased if required.
3. Clean runway surface and touch up any paint wear with a rust resistant paint. Allow
paint to dry thoroughly.
4. To obtain optimum performance, the position of the slip plate bearing cage should be
rotated every quarter to change the wear pattern. With the first quarter maintenance, flip
the bearing cage over to the opposite side. With the second quarter maintenance, rotate
the bearing cage end-to-end. With the third quarter maintenance, flip bearing cage over
to the opposite side. Fourth quarter maintenance should see the bearing cage rotated
back to the position it started in.
5. Quarterly maintenance will optimize performance and contribute to longer slip plate life.
This manual suits for next models
6
Table of contents
Other WHEELTRONIC Lifting System manuals
Popular Lifting System manuals by other brands

Genie
Genie AWP Super Series 114002 Operator's manual

Stenhoj
Stenhoj MOLNAR BRADBURY SB40 Please read this manual before you get started. You must read and understand the precautions for saf

Genie
Genie Lift Guard GR-12 Service manual

TECNA
TECNA 9336L instruction manual

Vancare
Vancare P-600 Technical manual

Parkside
Parkside P-SA 1200 Operation and safety notes