
6
© Copyright 2016 Zoeller®Co. All rights reserved.
Operation
GENERAL
Zoeller pumps are lubricated and tested at the factory prior to shipment and
require minimum pre-start-up maintenance.
Maximum continuous operating temperature of pump liquid for standard model
pumps must not exceed 130° F (54° C). WD models pump liquid should not
exceed 120° F (49° C). Nonautomatic pumps and pumps with adjustable
level controls must be totally submerged on long pumping cycles. A maximum
of ½ hour run time per hour.
These units are not designed to handle liquids other than water or sewage. If
pump is used in water contaminated with heavy, viscous, or abrasive materials,
the warranty will be voided.
NAMEPLATE DATA
The nameplate, located on the top of pump, indicates specic information about
the construction of the pump. The model number and date code information
should be recorded on the front page in the “Owner’s Information” section of
this manual.
SHORT TERM STORAGE
If pump is to be stored for more than six months, the following is advised:
• Store pump inside whenever possible or cover with some type of protective
covering.
• Tape or seal in plastic bag the terminal ends of wire leads.
• Spray coat unpainted surfaces with rust inhibiting oil.
• The impeller should be rotated every six months in order to keep the seals
lubricated and not develop a permanent set.
If panel is to be stored for more than six months, the following is advised:
• Store the panel inside whenever possible and leave in the shipping box.
• All openings shall be sealed.
• Store in an upright position.
• Do not stack anything on top of panel.
STARTUP PROCEDURE
Before placing the equipment into operation the following checked:
• Correct pump rotation (3 Phase units only).
• Clean pit.
• Panel dry and securely installed.
• Floats positioned properly.
• Discharge valves open.
• 3/16” vent hole drilled in pipe between check valve and pump.
Once the above has been veried proceed with the following checks:
• Pump power cables properly connected to panel.
• Float cables properly connected to panel.
• Conduit connections to panel are properly sealed.
• Thermal overload adjustments made in the panel.
• After installing the pump into the containment area, with adequate sub-
mergence, open the discharge valve fully. Start the unit using manual
controls. If ow is appreciably less than rated performance, pump may
be air locked. To expel trapped air, jog the unit several times, using the
manual controls.
• Have a qualied electrician take voltage and current measurements on
the black wire of single phase or all three power wires of three phase with
the pump running. Record these readings in the space provided in the
“Owner’s Information” section of this manual for future reference.
After the preoperational functional test has been completed, system is ready
for operation. Zoeller recommends completing a Start-up Report (FM0990)
whenever a system is started for the rst time or after a system has had a
signicant change take place (i.e. pump replacement, overhaul, ect.). A copy
of the Start-up Report should remain with the system for future reference.
ADJUSTMENT PROCEDURE
Pumps: No adjustments are required other than assuring correct rotation.
Panels: The thermal overloads in the panel (3 Ph systems) must be set
to the F.L.A. rating on the pump nameplate (or refer to pump data
sheet).
Floats: Refer to the system drawing for desired location of each oat
function.
Valves: Discharge valves should be placed in the fully open position. Sys-
tems should not be operated for extended periods of time with the
discharge valves partially closed due to damaging the valve.
SHUTDOWN PROCEDURES
If a system is shutdown for more than six months, the following is
recommended:
Pumps: If pit is to remain dry, then the pump can remain in the pit. With the
pump in the pit, it should be operated for ve minutes once every
three months. If the pit is to remain wet, the pump should be removed
and stored as noted below.
Panels: The panel should have all openings sealed to prevent moisture and
dust from entering the enclosure. Prior to restarting system, the
panel should be inspected for presence of moisture and any loose
connections.
Valves: Consult the valve/actuator supplier for information concerning these
systems components (used on dewatering pump stations only).
Maintenance
Repair and service should be performed by a Zoeller Pump
Company Authorized Service Station only.
SAFETY PROCEDURES
For your protection, always disconnect pump and panel from
its power source before handling.
Never enter the basin until it has been properly vented and
tested. Any person entering a basin should be wearing a harness with safety
rope extending to the surface so that they can be pulled out in case of asphyxi-
ation. Sewage water gives off methane and hydrogen sulde gases, both of
which can be highly poisonous.
Installation and checking of electrical circuits and hardware should be performed
by a qualied electrician.
Pump is never to be lifted by power cord.
Unit must be ushed and disinfected, inside and out, prior
to servicing.
GENERAL SYSTEM INSPECTION
Before the system is placed into operation, a system Start-up Report should
be conducted by a qualied technician.
Wiring and grounding mustbe in accordance withthe national
electrical code and all applicable local codes and ordinances.
LUBRICATION PROCEDURES
No lubrication is required.
If pumps are to be stored for more than six months, refer to short term storage
procedure in the Operation section.
PREVENTIVE MAINTENANCE
Preventive maintenance is recommended to ensure a long service life from
the product. Provided is a suggested maintenance schedule.
Every month:
• Check for proper and unobstructed oat operation.
• Listen for proper check valve operation.
• Activate pumps and take voltage and amperage readings.