Outdoor Prepackaged System Installation Instructions
1. Review the drawing in Figure 8 on page 8 and the actual
system to become familiar with the components in the
packaged grinder pump system. Review where the unit will
be installed. Determine where the power feed, inlet pipe,
and discharge pipe will be located.
2. Remove the unit from packing. Prepackaged outdoor
systems are preassembled at the Zoeller Company and
require a minimum of eld assembly work. Float switches
are set and tethered for proper operation from the Factory.
The alarm switch should be located 76 mm (3") above the
pump “on” level. Three-oat systems used with a control
panel are placed at 686 mm (27"), 610 mm (24"), and 381mm
(15") from the bottom of the basin. Four oat systems used
with a control panel are placed at 762 mm (30"), 686 mm
(27"), 610 mm (24"), and 381mm (15") from the bottom of
the basin. If the invert location is at or below the level of the
oat switches, contact the factory.
3. Float switches are tied in place for shipping purposes on
all model prepackaged systems. Cut the cable tie around
each oat switch bulb or the unit will not operate properly.
Verify that where the oat switches are set will work for
your application. Verifying that the oat switches are
set properly and will not hang up inside the basin is the
responsibility of the installing contractor.
4. Dig a hole for the basin. The hole should be at least 610 mm
(24") largerindiameter than the basin diameter to provide 305
mm (12") of backll all around and deep enough to provide
either 305 mm (12") of compacted backll or 152 mm (6")
whena concrete padis required. Note: Care must betaken
when excavating in order to avoid underground utilities
and disturbance of existing structure foundations. The
hole should be located at least ten feet from adjacent
structures. Additional distance may be required to
sufciently locate the basin outside of the loading area
of the adjacent structures.
5. The location of the inlet hub is determined by the depth of
the inlet pipe. The inlet hub must be used with 102 mm (4")
pipe. It is best to install the inlet on the side of the basin
opposite the oat switches. To install, use a 102 mm (4")
hole saw to drill into the side of the basin at the correct
elevation. Center the hub inner diameter with the hole in
the basin. Attach the hub to the side of the basin using the
sealant and hardware provided.
6. The bottom of the excavation can now be properly backlled,
compacted and leveled. Set basin in hole. Ensure the
removable cover extends above the nished grade line and
the grade slopes away from the unit. Backll and subbase
should be 3.2 - 19 mm (1/8” –3/4”) pea gravel or 3.2 - 12.7 m
(1/8” –1/2”) crushed stone. (Reference basin installation
instructions included with unit.) Most systems are supplied
with a eld installed 102 mm (4") pipe seal inlet tting. This
inlet tting is installed in the basin's side-wall in a 127 mm (5")
hole drilled with a hole saw at a location lining up with the inlet
pipe. Other type ttings and sizes are occasionally provided.
7. Pouring a concrete anchor around system can now be
completed. Basin should be lled with water when pouring
concrete to minimize movement of the system. Backll
around basin with specied media. Care should be used
to avoid damaging components or leaving voids when back
lling. Refer to Basin installation reference guide on more
specic requirements.
8. PVC or HDPE discharge piping is connected to the 132 mm
(1¼”) threaded tting located in the basin sidewall. Support
discharge piping with sufcient backll.
9. On basin depths of 1.8 m (72") and greater, the system’s
disconnect assembly is shipped loose and must be screwed
into the discharge piping. Apply pipe dope to threaded
connection.
10. Connect pull rod to Pump assembly. Connect lift cable to top
of pump. Lower the pump into basin ensuring the discharge
pipe bracket slides into the disconnect tting.
11. Note: The grinder basin is a sewage holding tank. Vent
connection should be installed in accordance with all
national, state and local plumbing codes.
12.
Dig a trench for the electrical conduit. The conduit should be
located below the frost line. Follow all applicable electrical
codes.
13. Connect electrical conduit and wiring to junction box
according to wiring instructions included in this manual and
wiring diagram in box. Use the potting kit provided with the
junction box. Follow the instructions for sealing the conduit
connection at the junction box.
14. Mount the control panel within sight of the system. Connect
oat switches and pump cords according to the “Pump Wiring
Instructions” found in this manual and located inside the
panel enclosure.
15. Remove any debris from the basin. Using clean water, check
the system for proper operation.
16. Seal and secure the lid using the proper bolts and sealant
when using a lid without a formed gasket.
17. Test system for leaks and proper pump operation.
18. Record system start-up data for future reference.
This set of instructions is for factory prepackaged outdoor grinder systems with Square Guide Rail system. If
installing a Z-Rail® Package or a eld-assembled outdoor system you can use these instructions as a guideline. If this is an indoor
system then go back to pages 6 and 7 in this manual that covers indoor systems. The pump should not be installed in the basin
until permanent electrical power is available.