Baxi Slinky User manual

© Baxi Heating UK Ltd 2006
Installation of Ground Array (Slinky®)
Horizontal Ground Coupling for Heat Pumps
Please keep these instructions safe in a safe place.
If you move house, please hand them over to the next occupier.
Operation, Installation & Maintenance
Instructions

2© Baxi Heating UK Ltd 2006
CONTENTS
Cross section of typical slinky®installation 3
Elevation of typical single slinky®installation 4
Introduction 5
General arrangement of heat pump & slinkies®6
Sizing, Installation orientation 7
Placing the slinky®8
Testing & Backfilling 9
Construction of 30m,40m & 50m slinkies®10
Manifolds & Pipe Connections 11
Typical manifold arrangement 12
Orientation, Lakes & Ponds 13
Slinkies®being installed in a lake, add antifreeze14
Section Page
© Baxi Heating UK Ltd 2006 All rights reserved. No part of this publication may
be reproduced or transmitted in any form or by any means, or stored in any
retrieval system of any nature (including in any database), in each case whether
electronic, mechanical, recording or otherwise, without the prior written
permission of the copyright owner, except for permitted fair dealing under
Copyrights, Designs and Patents Act 1988.
Applications for the copyright owner’s permission to reproduce or make other
use of any part of this publication should be made, giving details of the proposed
use, to the following address:
The Company Secretary, Baxi Heating UK Ltd, Pentagon House,
Sir Frank Whittle Road, Derby, DE21 4XA.
Full acknowledgement of author and source must be given.
WARNING: Any person who does any unauthorised act in relation to a
copyright work may be liable to criminal prosecution and civil claims for damages.

3
© Baxi Heating UK Ltd 2006
Typical Slinky®Installation

4© Baxi Heating UK Ltd 2006
Typical Single Slinky®Installation

5
© Baxi Heating UK Ltd 2006
Introduction
Introduction
The invention of the slinky®in 1985 is credited to Oklahoma University in the USA, which could be considered the heart of ground source heat pump
technology. Slinkies®are considered by many ground array design experts to be the best method of “horizontal ground coupling” for heat pumps. They are
particularly well suited to the UK, and require less digging per kW of heat delivered than any other method - and therefore offer the most economic installation
costs.
Why slinkies®?
Ground source heat pumps do not generally use deep geothermal heat energy from the core of the earth to heat buildings. From several metres down to 100
metres or so, the ground temperature is more or less uniform in the UK, often between 8°C and 11°C; there are obvious local exceptions, including Bath and
Southampton. Even “drilled” closed loop vertical ground arrays placed in a borehole only absorb perhaps 5% of their output from “deep geothermal” energy.
Instead, ground source heat pumps absorb low-grade solar energy during the winter, which must be gradually re-charged by the sun, and also every time it rains.
The ground acts as a battery, which means that incorrectly designed or sized closed loop ground arrays can over-cool the ground surrounding the pipe, leading
to much lower outputs and efficiencies from the heat pump. The slinkies®should be a clear 1 metre below ground level; there is little or no temperature
advantage achieved by digging much deeper. There is no evidence that vertical ground arrays are any warmer than slinkies®, mostly because the high cost of
drilling means that usually only the “bare minimum” of vertical arrays are fitted, whereas slinkies®have a much larger margin of duty. slinkies®have a distinct
thermodynamic advantage over drilled systems because the two pipes in a vertical borehole are right next to each other and connected by a porous grout,
which ensures that there can never be much temperature difference between the feed and return pipes. In slinky®installations there is no such limitation and the
pipes are widely spaced to prevent the very cold water leaving the heat pump from cooling down the warmer water returning from the ground.
How do slinkies®work ?
The heat pump pumps a cold (typically between 0 and 10°C) mixture of water and “glycol” antifreeze out into the slinkies®. As this mixture passes around the
slinkies®, it absorbs low-grade heat energy from the ground before returning warmer to the heat pump. The heat pump uses this low-grade heat to warm a
refrigerant, which then transfers it to the water in the building’s heating distribution system (usually underfloor heating), in the process “upgrading” the heat into
usable energy to heat buildings. A useful analogy is with a domestic fridge, where the inside of the fridge (5°C) is the ground, and the back of the fridge (35°C) is
the underfloor system in the building.
What’s the difference between “closed” and “open” loop
Closed loop ground arrays circulate the same fluid around them all the time, usually a mixture of antifreeze and water. Open loop system pump water from a
source (river/borehole/sea etc) through the heat pump and then dispose of the water. If a closed loop ground array such as a slinky®is placed in a large lake,
river or the sea, it behaves like and open loop system, in that the “battery” effect does not apply.

6© Baxi Heating UK Ltd 2006
General arrangement of heat pump

7
© Baxi Heating UK Ltd 2006
Sizing, Installation Orientation
Sizing
The amount of solar energy that lands per square metre is more or less the same anywhere in the UK. It follows that the amount of energy available for heat
energy absorption by ground arrays is therefore not affected greatly by different soil types. As a rule, “wetter” soil is slightly better than well-drained soil. The
sizing of slinkies®takes little account of soil types - although the type of soil does slightly affect heat transfer rates, other factors such the moisture content (which
is not always easy to determine until digging has started) will make much more of a difference. However, the formulae of 10 metres of trench to provide 1 kW
of delivered heat from the heat pump can be more or less uniformly applied across most of the UK.
There is a difference between using the “peak” heating requirement of a building to size a ground array, and using the “total annual heat demand”. However,
providing that the building is insulated at least to the requirements of Part L (J in Scotland) of the building regulations (and, preferably, far exceed this) then the
“peak” heating requirement alone can usually be used to size the slinkies®. Provided that the recommended number and lengths of slinkies®are installed
correctly, and the slinkies®are sized to meet the full peak heating requirement of the building (ie. as the sole source of heat - without supplementary electrical
backup, for example), then they will absorb sufficient energy from the ground to heat the building year-around. If too little pipe is buried then the temperature of
the slinky®will fall too much over the course of the winter, to below 0°C, and the heat pump will no longer give its rated output, and exceed its operating
envelope. This will cause the heat pump to operate continuously, eventually potentially freezing the slinkies®. If too much pipe is buried then it will take a
disproportionate amount of water circulating pump energy to move the fluid around the slinky®at a high enough speed to absorb the energy.
Installation Orientation
slinky®coils should be installed vertically in a narrow (300 mm) trench, dug with the narrowest digger bucket. A minimum distance of 5 metres between adjacent
trenches should be maintained. Keep the edge of any trench at least 1.5 metres inside any property line and away from any buildings. The trenches do not have
to be straight. If rock or large boulders are found before the trench gets to 2 metres deep, it is possible to turn the slinkies®on their side, for some or all of this
part of the trench, and dig the trench 1.2 metres deep by 1.2 metres wide.
The pipe
Only MDPE or HDPE (Medium or High Density Polyethylene) pipe should be used, with at least the PE80 pressure rating. Beware of using blue pipe, which
denotes that it contains only fresh water under Water Resources Council guidelines, which would be incorrect as ground arrays contain antifreeze.
Unrolling the coil
The slinkies®are formed and held together using black plastic "zip" ties. When formed into a coil for transport, the slinkies®are held together with white cable
ties. When the slinkies®arrive on site, the white cable ties should be cut, which will allow the coil to be unwound. The slinky®can then be laid out and placed in
the trench.

8© Baxi Heating UK Ltd 2006
Placing the slinky®
Headers
The slinkies®are supplied with a “header”, which is usually about 10 metres or more. This allows the 2 m deep slinky®trench to be terminated a little way from
the building, and for these header pipes from all the slinkies®to join together into a single “header trench”, which is often only 1.2 m deep, and allows the header
pipes to exit the soil vertically, directly under the “Slinky®Manifold”, which is always fixed to the outside of the building.
Cutting the pipe
The pipe can be cut with a hacksaw, but it is recommended that a proper plastic pipe cutter is used. These are available from plumbers merchants. Do not
reduce the total length of one slinky®without reducing the length of all of them by the same amount. This is because the lengths of the slinky®must be equal to
ensure that there is equal flow through all the slinkies®.
Digging The Trenches
Any size of digger can usually be used, although a full-sized machine may be required to dig through shale, and to move large boulders or other obstructions. The
best way is usually to lay out the slinkies®alongside the proposed route for the trench, and to start digging at the point furthest from the building.
Placing the slinky®in the trench
There are two ways of placing the coils in the trench:-
i) Dig the entire trench, unroll the slinky®from its coil and place it in the trench complete.
ii) Unroll the slinky®from its coil, dig part of the trench and place the slinky®in the trench as you progress.
The first method is preferable where only one or two people are working and where there are no health and safety implications for leaving a long trench open,
and the soil is compacted sufficiently for there to be no risk of collapse.
The Return
The return pipe should go in the same trench as the slinky®, and run up the side of the building and into the slinky®manifold.
Unused or excess pipe
Allowing enough pipe above ground (usually 1.5 metres) to cut down and connect into the slinky®manifold, any excess “header” pipe can be coiled back into
the trench. Alternatively, it can be cut off, as long as the same amount is cut off all the slinkies®
Tips on manipulating the pipe
There is a tremendous difference between the flexibility of the pipe at 5 deg C (an average winters day) and 20 deg C (an average summers day). However,
even on the coldest days, the pipe can still be formed into a 1 metre diameter circle, but this is will be much more difficult.

9
© Baxi Heating UK Ltd 2006
Testing & Backfilling
Testing
The slinky®coils are supplied pre-tested and certified by Baxi. It is recommended that the slinkies®are re-tested with either air or water before the trenches are
backfilled. It is possible to pressure test using an air compressor, but great care must be taken in case of a sudden release of air. Using water is a safest method,
but it is necessary to "purge" the air from each slinky®using a plastic container full of clean water and a powerful pump. The connection of a garden hose will not
produce sufficient volume of water to move the air from the tops of the loops. There are further instructions on the purging of slinkies®®in our heat pump
Operation, Installation & Maintenance Instructions.
Repairing Leaks - Cutting & Joining Pipe
The recommended method of joining buried plastic pipe is to use an “electrofusion” machine, which will produce a suitably robust joint. Alternatively, “Plasson”
type “O” seal connectors or brass compression fittings can be used but this is not recommended.
Kinked Pipes
If the plastic pipe is formed in too tight a radius it can possibly kink which must be avoided. If this does happen, it is may be possible to simply straighten out the
pipe. If the kink has permanently deformed the pipe, then the damaged section will have to be removed and the pipe rejoined.
Backfilling
Care must be taken during the backfilling procedure as damage to the slinkies® can easily occur. Heat transfer depends on good contact between the pipe loop
and the ground. Clay soils must be carefully prepared before returning the material to the trench, since much larger ‘clods’ can be present that could leave large
air pockets around the slinky®. If the clay is unmanageable and cannot be broken down, a well-graded sand or pea gravel should be used as the backfill. Soils
containing sharp flints and rocks should not be used as backfill. A digger bucket dropping stones from a height of 3 metres onto plastic pipe will easily damage the
pipe. Since slinkies®are a "closed loop" system any leaks will allow the water pressure to fall below that at which the circulating pump can operate. The earth pile
should be shoveled sideways so that it falls gradually into the trench. Break up or discard any ‘clods’ or lumps of earth. Shoring is required under health & safety
legislation if a trench is more than 1.2 metres deep.

10 © Baxi Heating UK Ltd 2006
Construction of 30,40,50m slinkies®

11
© Baxi Heating UK Ltd 2006
Manifolds & Pipe Connections
Manifolds
The manifold for the slinkies®should be placed on the outside wall of the building, with the heat pump on the other side of the wall. It is strongly recommended
that the manifolds are NOT situated inside a building, as this would require insulation. On the slinky®manifold, each end of each slinky®is terminated in a 32 mm
to 28 mm reducer which is connected to a 28 mm compression valve. Each of these valves is connected to either a "feed header" or "return header". It is
important that the effective length of each slinky®is the same, to ensure even flow across them all; plumbers call this principle "reverse return".
Connecting pipe to the manifold
The pipe must be cut squarely, and neatly, and any burrs inside or outside removed. A proper plastic pipe cutter should be used. Each slinky®manifold is supplied
with copper ferules, one of which must be inserted into the end of each pipe. These ferules act as support sleeves so that the plastic pipe is not crushed by the
olive in the 32 to 28 mm reducers. It is essential that the slinkies®must be the same length to ensure even water flow. The slinkies®are all supplied in identical
lengths - they must not be cut to different lengths.
The pipe must be pushed all the way into the reducers, before the nut is tightened. Two spanners must be used to tighten the reducers - one to hold the body
of the reducer, and one to turn the nut. As the nut is tightened, the copper or brass olive is compressed onto the plastic pipe, sealing the joint. A jointing
compound such as Stag®may be used on the joints. For it to be effective it must be applied to the pipe before it is inserted into the reducer to achieve
maximum coverage.
Connecting the manifold to the heat pump
All standard twin slinky®manifolds are supplied with 28 mm Speedfit®push-fit connectors for connection via 28 mm Hep2O®or similar plastic pipe systems to
the heat pump. This pipe can be purchased from any plumbers merchants. The pipes should be insulated using "vapour barrier" (such as Armaflex®) insulation
once inside the building to prevent dripping. Any pipe outside the building need not be insulated since the circulating fluid contains anti-freeze.

12 © Baxi Heating UK Ltd 2006
Typical Manifold Arrangement
Typical manifold arrangement for a pair of slinkies®.
Ensure that the slinkies®are connected “reverse return”
to ensure even flow through both slinkies®.

13
© Baxi Heating UK Ltd 2006
Orientation, Lakes & Ponds
Orientation of connections
It is immaterial which direction the fluid is pumped around the ground arrays - the connections to the heat pump are generic. It is essential that the slinkies®are
connected so that one end of each slinky®is connected to the "feed" manifold, and the other end is connected to the "return" manifold"; the effective length of
each of the slinkies®must be the same.
Using ground arrays in lakes, ponds, rivers etc
Since plastic pipe is buoyant even when filled, the arrays and their headers must be kept in place using weights. The arrays should be assembled on a stainless
steel mesh and held down using plastic zip ties. The arrays should be filled with air, not water, and floated into place with any weights attached. When in the
proper location, the arrays can be filled with water using a hose (providing that there is sufficient main water pressure) and sunk into position. Additional weights
may then also need to be carefully placed on the arrays.
After commissioning
The “disturbed” ground surrounding the newly installed slinky®will not make perfect contact with the pipe initially. After several years of constant rain, and the
compression effect of the ground, conduction with the soil will improve. Essentially, if the building is heated successfully over the first winter, performance in later
winters will generally improve.
What will the water temperature coming from the ground into the heat pump ?
This will be anywhere between 2 and 5°C below “static” ground temperature—in simple terms, between 3 and 7°C

14 © Baxi Heating UK Ltd 2006
slinkies®, installed in a lake
Slinkies®being installed in a lake. Note the headers from
the other slinkies®on the left hand side that are already
floated out.
Adding antifreeze to an 8 slinky®system.

15
© Baxi Heating UK Ltd 2006
Notes
Notes

© Baxi Heating UK Ltd 2006 Comp NoTP0202 - Iss 1 - 6/06
All descriptions and illustrations provided in this leaflet have been carefully
prepared but we reserve the right to make changes and improvements in
our products which may affect the accuracy of the information contained in
this leaflet. All goods are sold subject to our standard Conditions of Sale
which are available on request.
Baxi Heating UK Ltd
Brooks House, Coventry Road, Warwick. CV34 4LL
After Sales Service and Technical Enquiries 08700 603 261
Website www.baxi.co.uk
e&oe
company
Table of contents
Other Baxi Accessories manuals

Baxi
Baxi 7703233 Guide

Baxi
Baxi MULTIFIT User instructions

Baxi
Baxi MULTIFIT Solar Collectors User manual

Baxi
Baxi EXTERNAL SENSOR KIT User manual

Baxi
Baxi VALOR FIRES 845 Instructions for use

Baxi
Baxi MULTIFIT Evacuated Tube Collector User manual

Baxi
Baxi MULTIFIT Evacuated Tube Collector Manual

Baxi
Baxi MULTIFIT SOL 200 L User manual

Baxi
Baxi MULTIFIT Flue Systems Assembly instructions