Duarib Altitude 150 Installation instructions

Compliant with norm NF EN 1004
Compliant with Decree dating form 01/09/04
HEAD OFFICE
Route de la Limouzinière - BP 41
44310 St PHILBERT DE GRAND LIEU
Phone: 02 40 78 97 22
Fax: 02 40 78 78 71
www.duarib.fr
Mail: welco[email protected]
D040369B
C0400227B
ASSEMBLY,
DISASSEMBLY AND
USE INSTRUCTIONS
R O L L I N G S C A F F O L D I N G S

D040369B
Compliant with norm NF EN 1004
Compliant with Decree dating form 01/09/04
ALTITUDE 150
Code Floor
height
Work
height Load Weight
Parcel
Gencod
500001 500006 500003 500004 500005
500802 1.8 m 3.8 m Class 3 54 Kg 11376016602061 4
500803 2.8 m 4.8 m Class 3 59 Kg 111376016602062 1
500804 3.8 m 5.8 m Class 3 82 Kg 121376016602063 8
500805 4.8 m 6.8 m Class 3 86 Kg 121376016602064 5
376016602011 9 376016602058 4 376016602013 3 376016602014 0 376016602015 7Gencod
NF EN 1004
4.8 m floor height3.8 m floor height2.8 m floor height1.8 m floor height
LOADING CONDITIONS
Floor: Maximum allowed load spread over the floor = 150 kg
Whole scaffolding: Maximum allowed load spread over the
floors = 300 kg
(class 3 = 200 Kg/m² spread load)
500802
500803
500804
500805
Safe asembly
Assembly on a difference
in level
Fitting through doors
Page 2/20
ASSEMBLY, DISASSEMBLY AND USE INSTRUCTIONS

Min dim. A
Min dim. B
Center-to-center D Center-to-center E
Overall F
Dimensions
Florr
Height ABCDEF
Code
1.8 m 2180 1620 1570 1500 620 690500802
2.8 m 2800 2260 1570 1500 620 690500803
3.8 m 2960 2500 1570 1500 620 690500804
4.8 m 3480 3040 1570 1500 620 690500805
Unit of measurement: mm
C257005
C257003
C257008
11307
C257010
C257009
C257001
C257012
C257004
Head Office:
Route de la Limouzinière
44310 St Philbert de Grand Lieu
EN1004 - 3 – 4,8/4,8 - XXXD Rolling
Follow the assembly and use instructions
08067
Page 3/20
D040369B
Overall C
Reference to the norm
Load evenly spread class
(class 3, 200 Kg/m²)
Maximum outdoor height use
Maximum indoor height use
Access via stairs: no
Access via step stairs: no
Access via tilted ladder: no
Access via vertical ladder: yes

PARCEL CONTENT
Code Description Weight
Kg
Parcel
500001 500006 500003 500004 500005
C257001 Ø125 wheel adjustment on 15 cm 1.6 4
C257012 1.765m x 0.62m base ladder 3.4 2
C257003 2m x 0.62m ladder 3.5 123
C257004 1m x 0.62m ladder 1.8 2
C257005 1.5 m handrail 1.2 24
11307 1.5m wide alu-wood floor with integrated toeboards 13 1
C257008 Brace’s Lg: 2m 0.8 2244
C257009 Stabilizer 3.7 4
C257010 Pin (bundle w/ 2 pins) 0.05 4123
Parcel weight 36 Kg 17.8 Kg 5.2 Kg 10.4 Kg 14 Kg
C257012 C257003
Page 4/20
C257004 C257001
C257010
C257009
11307
C257005
C257008
D040369B

D040369B
Compliant with norm NF EN 1004
Compliant with Decree dating form 01/09/04
ALTITUDE 200
Code Floor
height
Work
height Load Weight
Parcel
Gencod
500011 500016 500013 500014 500015
500812 1.9 m 3.9 m Class 3 71 Kg 11376016602065 2
500813 2.9 m 4.9 m Class 3 78 Kg 111376016602066 9
500814 3.9 m 5.9 m Class 3 108 Kg 121376016602067 6
500815 4.9 m 6.9 m Class 3 113 Kg 121376016602068 3
500816 5.9 m 7.9 m Class 3 119 Kg 1211376016602069 0
500817 6.9 m 8.9 m Class 3 150 Kg 1311376016602070 6
500818 7.9 m 9.9 m Class 3 154 Kg 132376016602071 3
376016602016 4 376016602059 1 376016602018 8 376016602019 5 376016602020 1Gencod
NF EN 1004
LOADING CONDITIONS
Floor: Maximum allowed load spread over the floor = 205 kg
Whole scaffolding: Maximum allowed load spread over the
floors = 500 kg
(class 3 = 200 Kg/m² spread load)
500812
500813
500814
500818
Safe assembly
Assembly on a difference
in height
Fitting through doors
Page 5/20
ASSEMBLY, DISASSEMBLY AND USE INSTRUCTIONS
500815
500816
500817
1.9 m floor
height
7.9 m floor
height
6.9 m floor
height
5.9 m floor
height
4.9 m floor
height
3.9 m floor
height
2.9 m floor
height

C257010
C257009
C257101
C257112
C257109
C257104
C257108
C257103
11308
C257105
Min dim. A
Min dim. B
Overall C
Center-to-center D Center-to-center E
Overall F
Dimensions
Floor
height ABCDEF
Code
1.9 m 2240 1480 2100 2000 690 790500812
2.9 m 2740 2040 2100 2000 690 790500813
3.9 m 2800 2200 2100 2000 690 790500814
4.9 m 3220 2680 2100 2000 690 790500815
500816 5.9 m 3580 3260 2100 2000 690 790
500817 6.9 m 3560 3680 2100 2000 690 790
500818 7.9 m 4060 4220 2100 2000 690 790
Unit of measurement: mm
C257104
C257108
C257103
11308
C257105
Head Office:
Route de la Limouzinière
44310 St Philbert de Grand Lieu
EN1004 - 3 – 7,9/7,9 - XXXD Rolling
Follow the assembly and use instructions
08068
Page 6/20
D040369B
Reference to the norm
Load evenly spread class
(class 3, 200 Kg/m²)
Maximum outdoor height use
Maximum indoor height use
Access via stairs: no
Access via step stairs: no
Access via tilted ladder: no
Access via vertical ladder: yes

PARCEL CONTENT
Code Description Weight
Kg
Parcel
500011 500012 500013 500014 500015
C257101 Ø200 wheel adjustment on 15 cm. 3.3 4
C257112 1.765m x 0.69m base ladder 4.7 2
C257109 1st step with screw and bolts 0.9 1
C257103 2m x 0.69m ladder 4.7 123
C257104 1m x 0.69m ladder 2.4 2
C257105 2 m handrail 1.4 24
11308 2m wide alu-wood floor with integrated toeboards 17.4 1
C257108 Brace's Lg: 2.4m 12244
C257009 Stabilizer's Lg: 2.476m 3.7 4
C257010 Pin (bundle w/ 2 pins) 0.05 4123
Parcel weight 48.3 Kg 23 Kg 6.8 Kg 13.6 Kg 18.4 Kg
C257112 C257103
Page 7/20
C257104 C257101
C257010
C257009
11308
C257105
C257108
C257109
D040369B

D040369B
Compliant with norm NF EN 1004
Compliant with Decree dating form 01/09/04
LOADING CONDITIONS
Floor: Maximum allowed load spread over the floor = 260 kg
Whole scaffolding: Maximum allowed load spread over the
floors = 500 kg
Safe assembly
Assembly on a
difference in height
Fitting through doors
Page 8/20
ASSEMBLY, DISASSEMBLY AND USE INSTRUCTIONS
ALTITUDE 250
Code Floor
height
Work
height Load Weight
Parcel
Gencod
500021 500026 500023 500024 500025
500822 1.9 m 3.9 m Class 3 78 Kg 11376016602072 0
500823 2.9 m 4.9 m Class 3 86 Kg 111376016602073 7
500824 3.9 m 5.9 m Class 3 122 Kg 121376016602074 4
500825 4.9 m 6.9 m Class 3 127 Kg 121376016602075 1
500826 5.9 m 7.9 m Class 3 134 Kg 1211376016602076 8
500827 6.9 m 8.9 m Class 3 170 Kg 1311376016602077 5
500828 7.9 m 9.9 m Class 3 175 Kg 132376016602078 2
376016602021 8 376016602060 7 376016602023 2 376016602024 9 376016602025 6Gencod
NF EN 1004
(class 3 = 200 Kg/m² spread load)
500822
500823
500824
500828
500825
500826
500827
1.9 m floor
height
7.9 m floor
height
6.9 m floor
height
5.9 m floor
height
4.9 m floor
height
3.9 m floor
height
2.9 m floor
height

C257010
C257009
C257101
C257112
C257109
C257104
C257208
C257103
11309
C257205
Min dim. A
Min dim. B
Overall C
Center-to-center D Center-to-center E
Overall F
Head Office:
Route de la Limouzinière
44310 St Philbert de Grand Lieu
EN1004 - 3 – 7,9/7,9 - XXXD Rolling
Follow the assembly and use instructions
08068
Page 9/20
Dimensions
Floor
height ABCDEF
Code
1.9 m 2360 1400 2100 2000 690 790500822
2.9 m 2820 2020 2100 2000 690 790500823
3.9 m 2740 2240 2100 2000 690 790500824
4.9 m 3140 2800 2100 2000 690 790500825
500826 5.9 m 3460 3420 2100 2000 690 790
500827 6.9 m 3400 3840 2100 2000 690 790
500828 7.9 m 3860 4400 2100 2000 690 790
Unit of measurement: mm
D040369B
Reference to the norm
Load evenly spread class
(class 3, 200 Kg/m²)
Maximum outdoor height use
Maximum indoor height use
Access via stairs: no
Access via step stairs: no
Access via tilted ladder: no
Access via vertical ladder: yes

PARCEL CONTENT
Code Description Weight
Kg
Parcel
500021 500026 500023 500024 500025
C257101 Ø200 wheel adjustment on 15 cm 3.3 4
C257112 1.765m x 0.69m base ladder 4.7 2
C257109 1st step with screw and bolts 0.9 1
C257103 2m x 0.69m ladder 4.7 123
C257104 1m x 0.69m ladder 2.4 2
C257205 2.5 m handrail 1.9 24
11309 2.5m wide alu-wood floor with integrated toeboards 20.4 1
C257208 Brace’s Lg: 2.8m 1.5 2244
C257009 Stabilizer’s Lg: 2.476m 3.7 4
C257010 Pin (bundle w/ 2 pins) 0.05 4123
Parcel weight 50.3 Kg 28 Kg 7.8 Kg 15.6 Kg 20.4 Kg
C257112 C257103
Page 10/20
C257104 C257101
C257010
C257009
11309
C257205
C257208
C257109
D040369B

Set the handrail with the hook, as indicated on diagram 1,
by leaving the lock open.
Using the brace's end, joint it in the other end of the handrail, as indicated on
diagram 2
Set the handrail with the brace, first by moving the handrail back
then by moving up and joint in the other end.
Handrail safe assembly
Repeat this step to safely set the
upper level handrails.
1
2
3
4
With the brace, close the lock at
the end of the handrail on the
rung with a small movement
downwards.
You will close the second lock of
the handrail when access to the
upper level is possible.
Page 11/20
Diag. 1
Diag. 2
DUARIB
PATENT
D040369B

1 rung maximum
Floor safe assembly
The distance between each floor
cannot exceed 3m.
1
1
2
Setting the floor at a higher position is done by moving each end
of the floor one after the other until you have reached the desired
height.
2
3
4
Set a floor about six feet off the
ground, leaving the floor's locks
open.
Page 12/20
DUARIB
PATENT
D040369B
The floor's hooks allow for a difference of
one rung maximum.

1
Attach and pin the wheels on the base ladder.
Set two handrails on the first rung.
Set up the braces and lock them.
Activate the wheels' brake.
With a spirit level, check the handrails and the rungs are horizontal.
2
Set the stabilizers.
Fine-tune the stabilizers so they touch the
ground. Be careful, the wheels must stay in
contact with the ground.
3
Set two 2m ladders
Pin both ladders.
Set up 4 handrails from the ground by following the safe
handrail assembly instructions.
Brace's lock position:
closed.
Spirit level
Page 13/20
Mark Description Qty
1Ø25 bent pipe 1
2Plastic pipe cap 2
3Open stirrup 1
4M8 wing-nut connector 1
5"U" shaped stirrup 2
6H M8 brake nut 4
3
5
4
6
1
2
The first bent step must be set only on one of the two base ladders for the
Altitude 200 and 250 scaffoldings. This step must be set inside the scaffolding.
D040369B

4
5
Go up on the floor
Close the locks of all four handrails
Set and lock two braces
6
Set two 1m ladders
Pin both ladders
With the help of a brace, set four handrails for the upper level by following the
handrail's safe assembly instructions
Set the first floor up.
Close the two locks at each end of the floor's hooks.
Page 14/20
D040369B

7
Set the floor for the upper level
Lock the floor
8
Go up on the floor
Close the locks of all four handrails
Set both handrails
Page 15/20
D040369B

Assembly on a difference in height
1m max
Door width
The Altitude 150 scaffolding can fit through a 0.7m (width) x
1.93 (height) door.
The Altitude 200 and 250 scaffoldings can fit through a 0.8m
(width) x 1.93 (height) door.
In this setup, you can transport your hardware and small
tools.
Page 16/20
Assembly for transport and to fit through doors
D040369B

Special case: Anchors assembly
Top view
Use the scaffolding when the wind doesn't
exceed 45 kmph.
If the wind exceeds 45 kmph, anchor the
scaffolding at the top or disassemble it.
Anchor
If the wind exceeds 45 kmph, it is forbidden to use the
scaffolding, even if it is anchored.
Page 17/20
With a wind speed superior to 45 kmph, it is mandatory to
either disassemble or anchor it at the top.
If you chose to anchor it:
Set the stabilizers according to the below picture
Add 2 anchors at the top.
Anchors not included in the parcel (Anchoring kit code:
20865)
Superior to
45 kmph
D040369B

Special case: Supporting bar assembly
Supporting bar
Here are some ways to guarantee the scaffolding's stability when
mounted in front of a building:
Set the stabilizers according to the below picture
Add 2 support bars on the upper end (one on each vertical upright)
Supporting bars not included in the parcels
Supporting bars must always be set above the stabilizer's upper
attachment point.
When working on the front of the building,
use stabilizers and add 2 support bars.
Supporting bar set up zone
OK
Page 18/20
D040369B

Safety measures
It is forbidden to move a scaffolding that has a rolling bridge, a crane or handling equipment.
the moving area must be free of obstacles.
The scaffolding can only be manually moved on solid ground (for a loose ground, plan a roll
out walkway), free of personnel or tools, with the space between supporting bars and the
ground being very low.
Do not move the scaffolding if the wind speed exceeds 45 kmph.
It is forbidden to jump on floors.
It is forbidden to create a bridge between a
rolling scaffolding and a building or any
other fixed structure.
It is forbidden to use planks as a floor.
Only go up or down the scaffolding
through the trapdoors in the floors.
Use the scaffolding when the wind doesn't
exceed 45 kmph.
The scaffolding must be secured at the
end of the day, by anchoring it or
disassembling it.
Beware of turbulences when near the
angle of a building or under a porch.
All 4 wheels must always touch the ground in order to support the work load and the
structure's own weight. Maximum load on one wheel: 125 kg.
Make sure that support points can bear the load on the ground and that contact surface is
properly calculated according to the ground's type (on loose ground, use wedges under the
wheels and the supports, do not use hollow breeze blocks or any other non reliable wedges).
Assemble the scaffolding on a flat ground that is on a level.
It is forbidden to use a scaffolding that has not been vertically assembled (1% tolerance).
It is strictly forbidden to extend the height over the one mentioned in this user guide.
It is forbidden to set up a ladder or any other accessory on the floor to extend the scaffolding.
Make sure the work area is far from any working power line.
Page 19/20
Superior to
45 kmph
D040369B

Safety measures
Assembly and disassembly must be performed by operators who have been trained in
assembly and security instructions.
Only use parts in good condition we have manufactured and referenced in the nomenclature.
Make sure the assembly is compliant with the user guide.
For any use not compliant to the user guide, please contact the manufacturer.
Before going on the scaffolding, please check that stabilizers are tightened and wheels locked.
Check that all the parts are pinned and that security features are locked.
During assembly and disassembly, you must wear Personal Protective Equipment, such as:
hard hat, safety shoes, gloves…
Respect the assembly order described in this user guide to the letter.
Anchor the scaffolding to a building or any other surface that can bear the stress.
Anchor the scaffolding on the top part at the end of each operation.
Horizontal forces must not exceed 30 kg
on the last floor level.
According to the current regulation, the
space between two floors cannot exceed
3m.
Maximum force: 30kg
MAINTENANCE:
Before any assembly or use, you must check all the parts of the scaffolding to see if any could be
defective and replace it, if necessary.
You must make sure that:
Wheel treads and their brakes work properly.
All lock mechanisms (base body, handrails, diagonal braces) work properly.
The plywood of the floor and the trapdoor are in good condition.
DISASSEMBLY:
Before any disassembly, check that the wheels are locked and stabilizers are firmly tightened.
For the disassembly, respect the reverse assembly order described in this user guide to the
letter.
Disassemble them gradually to operate with maximum security.
When working on the front of the building,
use stabilizers and add 2 support bars.
OK
OK
OK
3m max 3m max
OK
OK
OK
Page 20/20
OK
D040369B
Table of contents
Popular Lifting System manuals by other brands

Lehner Lifttechnik
Lehner Lifttechnik LIFTboy user manual

Playcore
Playcore Spectrum Aquatics Summit WP 400 manual

Medline
Medline MDS400SA owner's manual

Manitou
Manitou MI-X 50L D C ST3A S2 Operator's manual

Snorkel
Snorkel SP20 Operator's manual

Tractel Group
Tractel Group jockey Operating and maintenance instructions

Sumner
Sumner Roust-a-Bout R Series Operator's manual

Oshkosh Corporation
Oshkosh Corporation JLG 830P Operation and safety manual

Safelift
Safelift PushAround PA35 Original instructions

rav
rav VARKPH 370.32/T Translation of the original instructions

stellar labs
stellar labs ECCR owner's manual

morse
morse 410M-124 Operator's manual