Installation Instructions
1. Consult local codes for specific installation requirements and restrictions
applicable to your area. It is recommended that system supply pressure
be at least 20psi (133kPa).
2. These instructions apply to Series 850 (DC) and 856 (DCDA), sizes 21⁄2"
to 10" only (65 – 250mm). The valves may be installed only in the orienta-
tion/flow direction as shown. The gate valves may be rotated as permit-
ted by the flange bolt pattern on vertical installations only.
3. The valve assembly must be installed where it is accessible for periodic
testing and maintenance. Clearances shown in the installation views
apply to exterior, interior and pit/vault installations and are only recom-
mendations. These minimums do not apply to removable protective
enclosures. Refer to local codes for actual requirements in your area.
4. PRIOR TO INSTALLING THE VALVE INTO THE LINE, FLUSH THE SUPPLY
LINE OF ALL FOREIGN MATERIAL. Failure to flush the supply line may
cause the check valves to become fouled and require disassembly and
cleaning.
5. Lift the assembly by connecting lift hooks to the lift rings cast into the
valve body. DO NOT LIFT THE ASSEMBLY BY CONNECTING TO THE
GATE VALVE HANDWHEELS OR STEMS.
6. After installation SLOWLY fill the assembly with water and bleed air from
the body using the # 3 and # 4 test cocks. Test the valve assembly to
ensure correct operation.
NOTE: All assemblies are tested at the factory for proper operation and
leakage. If the valve does not pass the field test, it is most likely due to a
fouled check valve. This is not covered by the factory warranty. The valve
cover(s) must be removed and the check seats inspected and cleaned.
Any damage or improper operation caused by pipeline debris or improp-
er installation/start-up is not included in the factory warranty.
In case of a possible warranty claim, contact your local supplier or
FEBCO Representative. DO NOT REMOVE THE VALVE ASSEMBLY
FROM THE PIPELINE.
7. The assembly must be protected from freezing and excessive pressure
increases. Thermal expansion or water hammer can cause pressure
increases. These excessive pressure situations must be eliminated to
protect the valve and system from possible damage.
Typical Installation
Figure 1
Figure 2
Figure 3
IS-F-850/856-DC/DCDA
INSTALLATION INSTRUCTIONS
Series 850, 856
Double Check Valve Assemblies
Double Check Detector Assemblies
Sizes: 21⁄2" – 10" (65 – 250mm)
RWWP
FRT
4175
850
12" Min (300mm)
Refer to Local Codes
6" Min (150mm)
Refer to Local Codes
Flow
HORIZONTAL INSTALLATION OR THE DC SERIES 850
(Front View, Shown With Strainer)
6" Min (150mm)
Refer to Local Codes
18" Min (450mm)
HORIZONTAL INSTALLATION OR THE DC SERIES 850
(Top View, Shown With Strainer)
6" Min (150mm)
Refer to Local Codes
18" Min (450mm)
VERTICAL INSTALLATION OR THE DC SERIES 850
(Shown With Strainer)
Flow
MAINTENANCE MANUAL
Limited Warranty: FEBCO warrants each product to be free from defects in material and workmanship under normal usage for a period of one year from the date of original shipment. In the event of
such defects within the warranty period, the Company will, at its option, replace or recondition the product without charge. This shall constitute the sole and exclusive remedy for breach of warranty, and
the Company shall not be responsible for any incidental, special or consequential damages, including without limitation, lost profits or the cost of repairing or replacing other property which is damaged
if this product does not work properly, other costs resulting from labor charges, delays, vandalism, negligence, fouling caused by foreign material, damage from adverse water conditions, chemical, or
any other circumstances over which the Company has no control. This warranty shall be invalidated by any abuse, misuse, misapplication or improper installation of the product. THIS WARRANTY IS IN
LIEU OF ALL OTHER WARRANTIES, EXPRESS OR IMPLIED, INCLUDING ANY IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Any implied warranties that
are imposed by law are limited in duration to one year.
Some States do not allow limitations on how long an implied warranty lasts, and some States do not allow the exclusion or limitation of incidental or consequential damages. Therefore the above limitations
may not apply to you. This Limited Warranty gives you specific legal rights, and you may have other rights that vary from State to State. You should consult applicable state laws to determine your rights.
General
1. Detailed maintenance manuals are available from your local FEBCO
representitive.
2. Rinse all parts with clean water prior to reassembly.
3. DO NOT USE ANY PIPE DOPE, OIL, GREASE OR SOLVENT ON ANY
PARTS unless instructed to do so.
4. Do not force parts. Parts should fit together freely. Excess force may
cause damage and render the assembly inoperable.
5. Carefully inspect seals and seating surfaces for debris or damage.
6. After servicing, repressurize the assembly and test to ensure proper
operation.
Disassembling the Check Valve
1. Close the outlet shutoff valve, then close the inlet shutoff valve. Bleed
residual pressure from the assembly by opening the #4, #3, and # 2
test cocks in this sequence.
2. Remove the cover bolts/nuts and lift the cover from the body. The
springs are retained and the cover should be pushed away from the
body approximately 1⁄4inch.
3. Inspect/clean debris from the disc and seat ring. Replace worn or
damaged parts as required.
4. Replace the cover, ensure the spring assembly is positioned in the pivot
socket. If necessary, apply FDA approved grease to the O-ring groove in
the body to keep the O-ring in position while installing the cover.
5. Install the bolts and nuts and tighten.
Test Procedure
FEBCO recommends the use of the appropriate test method presented in
the ASSE Series 5000 manual that is consistent with your local codes.
Troubleshooting for Double Check Assemblies
PROBLEM CAUSE SOLUTION
1. Check valve leaking a. Debris on seating surface Disassemble and clean
b. Leaking shutoff valve. Disassemble and clean
2. Low flows a. Mainline check fouled Disassemble and clean
passing through b. Bypass line plugged Disassemble and clean
Servicing Check Valve Assemblies
A Division of Watts Water Technologies, Inc. USA: 4381 N. Brawley • Ste. 102 • Fresno, CA • 93722 • Tel. (559) 441-5300 • Fax: (559) 441-5301 • www.FEBCOonline.com
Canada: 5435 North Service Rd. • Burlington, ONT. • L7L 5H7 • Tel. (905) 332-4090 • Fax: (905) 332-7068 • www.FEBCOonline.ca
IS-F-850/856-DC/DCDA 0613 EDP# 980048 © FEBCO, 2007

This manual suits for next models

1

Other FEB Industrial Equipment manuals

FEB 765 Owner's manual

FEB

FEB 765 Owner's manual

FEB 860 Series User manual

FEB

FEB 860 Series User manual

FEB 825YD Series User manual

FEB

FEB 825YD Series User manual

Popular Industrial Equipment manuals by other brands

Amtrol THERM-X-TROL ST-20V-C Installation & operation instructions

Amtrol

Amtrol THERM-X-TROL ST-20V-C Installation & operation instructions

Siemens SIMOCODE pro 3UF710-1 A00-0 Series operating instructions

Siemens

Siemens SIMOCODE pro 3UF710-1 A00-0 Series operating instructions

Schulte FM-350 Operator's manual

Schulte

Schulte FM-350 Operator's manual

Enerpac MRS-1 instruction sheet

Enerpac

Enerpac MRS-1 instruction sheet

New Leader Raven OMNiPOWER NL5000 G5 Operator's manual

New Leader

New Leader Raven OMNiPOWER NL5000 G5 Operator's manual

SCHUNK ROTA-M flex 2+2 Series Assembly and operating manual

SCHUNK

SCHUNK ROTA-M flex 2+2 Series Assembly and operating manual

Scotchman PRESSPRO 176MT manual

Scotchman

Scotchman PRESSPRO 176MT manual

Index R200 Operating instructions and Maintenance instructions

Index

Index R200 Operating instructions and Maintenance instructions

ABB HT610734 Operation manual

ABB

ABB HT610734 Operation manual

Banner A-GAGE MINI-ARRAY MACNXDN-1 instruction manual

Banner

Banner A-GAGE MINI-ARRAY MACNXDN-1 instruction manual

Jäger F120-H830.02 S9W2V manual

Jäger

Jäger F120-H830.02 S9W2V manual

CKD INDEXMAN PPLX Series instruction manual

CKD

CKD INDEXMAN PPLX Series instruction manual

CashCode SNR Software Description

CashCode

CashCode SNR Software Description

ABB GE ReliaGear AMP1 installation instructions

ABB

ABB GE ReliaGear AMP1 installation instructions

Buhler GAS 222.10 Assembly, installation and operation instructions

Buhler

Buhler GAS 222.10 Assembly, installation and operation instructions

MachineryHouse Metalmaster PB-820A Operation manual

MachineryHouse

MachineryHouse Metalmaster PB-820A Operation manual

4tek RAIN1A User and installation manual

4tek

4tek RAIN1A User and installation manual

Zimmer MATCH LWR50F-01-03-A Installation and operating instructions

Zimmer

Zimmer MATCH LWR50F-01-03-A Installation and operating instructions

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.