3.4 PACKING ADJUSTMENT (Injectable)
3.4.1 The packing adjustments to the XS150-ULV can be made while the valve is under working
pressure. Read the entire warning below.
3.4.2 Occasionally, the XS150-ULV’s chest seal may require an adjustment. To adjust the
XS150-ULV’s chest seal, inject small amounts of the packing material through each of the
injection holes until the leak stops. Inject just enough packing to stop leakage. Over
packing the chest seal may cause undue pressure against the gate making the valve
difficult to operate and cause rapid chest seal wear. If possible, stroke the valve a few
times before injecting packing. IMPORTANT: Packing must be added evenly to all four
ports to evenly load the chest seal.
3.4.3 Determine the location of the leak and slowly tighten the nearest packing injection bolt. If
this bolt is already bottomed out, new packing will have to be injected into the seal cavity.
Slowly remove the packing injection bolt that is closest to the leak. Read the entire
warning below.
REMOVE THE PACKING SCREWS VERY SLOWLY AND WATCH FOR
ANY SIGNS INDICATING LEAKAGE PAST THE PACKING BOLT. IF
ANY LEAKAGE PAST THE PACKING BOLT IS OBSERVED WHEN THE
BOLT IS BEING REMOVED, QUICKLY SCREW THE BOLT BACK TO ITS
FULL DEPTH. THE PIPELINE WILL NEED TO BE DE-PRESSURIZED
BEFORE THE VALVE’S CHEST SEAL CAN BE REPACKED.
3.4.4 Inject small amounts of packing by placing it in the hole and slowly pushing it into the
valve.
NOTE: A simple re-packing tool will be required for packing the valve. This packing tool
can easily be fabricated on the job site. Use a piece of rod or a round shank screw driver
with the end cut off or a 3/16” Allen wrench to force the packing into the lateral seal. (The
tool diameter should be approximately 0.21”) The shank length of the tool should be at least
5” long. If you make the tool yourself, grind a small chamfer on the end of the tool to prevent
damaging the threads in the injection holes.
3.4.5 Replace the packing injection bolt and tighten until snug. Inspect for leaks. If leaks
continue, repeat step 3.4.4 until the leak stops. Care should be taken not to over fill the
lateral seal with packing as this could lead to premature failure due to wear against the
gate.
SPECIAL PRECAUTIONS MUST BE TAKEN BEFORE REMOVING THE
PACKING BOLTS. WEAR PROTECTIVE CLOTHING AND EQUIPMENT
NORMALLY REQUIRED TO AVOID INJURY FROM THE PARTICULAR
FLUID IN THE LINE. WEAR PROTECTIVE CLOTHING AND PROTECTIVE
EQUIPMENT THAT SAFEGUARDS EYES, FACE, HANDS, ALL SKIN AND
LUNGS. IF THERE IS ANY DOUBT, CONTACT THE PROPER
SUPERVISOR IMMEDIATELY.