17. Move the collar down to bring
the lower part (indicated by the tip
of the arrow) in correspondence to
the line below the diameter of the
pipe on which the operation is being
carried out (i.).
18. Loosen the knob on the
graduated scale, turn the graduated
scale 90° counter-clockwise and
then tighten the knob (J.).
19. Turn on hydraulic power and
begin drilling until the pipe coupon
detaches. The location of the collar
indicates the farthest travel the
machine can be operated safely
without drilling too far.
20. Return the hydraulic operator
lever to the neutral position (K.)
21. Turn off the hydraulic power and
the hydraulic control unit.
22. Turn the feed screw counter-
clockwise until the shell cutter is
inside of the drilling bell.
23. Close the slide gate valve.
24. Attach relief piping (L.).
25. Purge the residual pressure
above the closed gate a suitable
distance from possible sources of
ignition.
26. Remove hoses from the
hydraulic control unit and operator.
27. Remove the drilling machine.
28. Carry out the cleaning operation
using the cleaning inspection
machine equiped with nylon wire
brush (M.).
i.
Collar
K.
Lever in
Nuetral
L.
Flexible Pipe
M.
29. Proceed with stopping operation.
30. Check the operation of the
expanding stopper. If the sealing
ring does not expand evenly on
the entire perimeter, it is necessary
to lubricate the walls surrounding
the ring with PURITY-FG Spray or
equivalent (walls are compressed
by two steel langes). Expand and
retract the sealing ring a few times
until the expansion is uniform. In the
event that the stopper is not used
for a long time, it is recommended to
completely disassemble the stopper,
replace the sealing ring and lubricate
thoroughly. After reassembling the
stopper, wipe the outer side of the
ring that comes into contact with the
inner side of the pipe.
31. Clean and lubricate the stopper
bar and the sealing disk to provide
smooth operation and to allow
centering of the stopper during the
expansion phase.
32. Position the stopping machine
(N.) on the slide gate valve.
NOTE: There are 2 handles on
the stopping machine. The longer
one should always be on the
upstream side.
J.
Graduated
Scale
N.
Long Handle Short Handle
Cleaning /
Inspection
Machine
with
Viewer
Brush
Bleed Valve
Knob