CONNECTING THE BRINE SIDE
• Insulate all indoor brine pipes against condensation.
•The level vessel must be installed as the highest point
in the brine system on the incoming pipe before the
brine pump (Alt. 1).
If the level vessel cannot be placed at the highest
point, an expansion vessel must be used (Alt. 2).
NOTE
Note that condensation may drip from the level
vessel. Position the vessel so that this does
not harm other equipment.
• Details of the antifreeze used must be shown on the
level vessel.
•Install the enclosed safety valve below the level vessel
as illustrated.
• Install a shut off valve for outgoing brine as close to
the heat pump as possible.
• Fit the enclosed filterball on the incoming brine.
TIP
If filling connection KB25/KB32 is used, the
enclosed filterball does not need to be fitted.
In the case of connection to an open groundwater sys-
tem, an intermediate frost-protected circuit must be
provided, because of the risk of dirt and freezing in the
evaporator. This requires an extra heat exchanger.
Heating medium side
CONNECTING THE CLIMATE SYSTEM
A climate system is a system that regulates indoor
comfort with the help of the control system in F1155PC
and for example radiators, underfloor heating/cooling,
fan convectors etc.
•Install all necessary safety devices, shut-off valves (as
close to the heat pump as possible) and the enclosed
filterball.
• Fit safety valve on heating medium return as illus-
trated. Recommended opening pressure is 0.25 MPa
(2.5 bar). For information about max opening pressure,
see technical specifications.
• When connecting to a system with thermostats on all
radiators (or underfloor heating coils), either a bypass
valve must be fitted or some of the thermostats must
be removed to ensure there is sufficient flow.
Cold and hot water
CONNECTING THE HOT WATER HEATER
NOTE
If F1155PC is not docked to a water heater or
if it is to work with fixed condensing, the con-
nection for the water heater (XL9) must be
plugged.
• Fit shut-off valve, non-return valve and safety valve as
illustrated.
• The safety valve must have max. 1.0 MPa (10.0 bar)
opening pressure, and be installed on the incoming
domestic water line as shown.
• A mixer valve must also be installed, if the factory
setting for hot water is changed. National regulations
must be observed.
• Hot water production is activated in the start guide or
in menu 5.2.
15Chapter 4 | Pipe connectionsNIBE F1155PC