4TSM DS 50-001/REV.2/ 031-300-190-002/ 09-23-96
1.1. SYSTEM OUTLINE
The PAT Overload Warning System Model DS 50 is designed to disable all functions
which may cause tipping or structural damage when the crane attempt to lift over
its limits.These limits are specified in the load capacity chart provided by the crane
manufacturer.
When the DS 50 system detects an overload condition the following crane
functions are disabled immediately.
a. telescope out
b. boom up and boom down
c. hoist up
To remove the overload condition the operator must achieve a safe working
condition.This can be achieved by lowering the load and repositioning the crane
or decreasing the radius by telescoping in. Observe that the radius can not be
decreased by lifting the boom. The boom up function is also disabled while
attempting to overload the crane.
The system design allows you to operate the crane in an emergency situation or
system failure without the DS 50 system in operation . In this situation leave the
crane electric switch in the off position and operate the crane manually. The
DS 50 Overload Warning System is not operative and can not warn the operator.
Warning
By switching the crane power switch off the DS 50 Overload Warning system
is by-passed. Operating the crane without using the range diagram may
result in property damage, injury or death.
The DS 50 system contains of a Central unit. The length sensor is part of the
Central unit. The load cell is supporting the hoist drum and used to measure the
load on hook.
1. INTRODUCTION TO TROUBLESHOOTING THE
PAT OVERLOAD WARNING SYSTEM DS 50