RAVOLT Generation 2 Instruction sheet

Rev. 1.0 (12/19/2022) 1
RaVolt Installation Guidelines
Generation 2
Version 1.0 Dated 12/19/2022
**Installation to be conducted by qualified personnel only**

Rev. 1.0 (12/19/2022) 2
Table of Contents
1. Recommended Tools & Materials
2. Installation Overview
3. Unloading Equipment
4. Placement of Enclosure & Generator Pads
5. Placement of Enclosure & Generator
6. Trenching & Conduit
7. Terminations
8. Enclosure Labeling
9. QA/QC Walkthrough
10. Commissioning & Photos

Rev. 1.0 (12/19/2022) 3
All information contained below shall be used as a guide and not intended as complete instructions.
All installation activities shall be carried out by a qualified and properly trained electrician
and all personnel must wear appropriate PPE.
All installation means and methods shall be per Scope of Work (SOW), stamped Design Documents
and manufacturer installation guides.
For further support please contact the RaVolt team.
Service Line: 1 (844) RAVSERV/ 1 (844) 728-7378
Email: service@ravolt.com

Rev. 1.0 (12/19/2022) 4
1.) Recommended Tools & Materials
The following list of tools and materials are recommended, but not required. Installations
may require additional materials based on design.
Tools:
1.) Hand Tools
•Phillips head screwdriver
•Flat head screwdriver
•Small precision screwdriver
•5/16” nut driver
•Wire strippers
•Cable cutters
•Linesman pliers
•Crimpers
•Shovel
•Tamper
•Level
•Hammer
•6 foot ladder
•Meter
•Ground rod attachment
2.) Power Tools
•Knockout set or hole-saw set
•Cordless hammer drill
•Bandsaw or Sawzall
•Impact gun
3.) Rigging
•6’ rigging straps
•Shackle

Rev. 1.0 (12/19/2022) 5
4.) Anchoring
•Refer to RaVolt Anchoring Diagram
Materials:
1.) Conduit
•PV Input to DC Disconnects (1 list per string)
o(1) 1” weatherhead
o(1) 1” sch. 40 cut to length (roughly 12-18”)
o(1) 1” TA/MA
o(1) 1” bushing
o(1) 1” locknut
•Generator Circuit
o(1) 2” non-metallic flexible conduit cut to length (roughly 6’)
o(1) 2” sch. 40 cut to length (roughly 4’)
o(1) 2” sch. 40 to be placed in trench
o(2) 2” 90° sch. 40 fittings
o(2) 2” flexible straight fittings
o(2) 2” flexible 90° fittings
o(2) 2” locknuts
o(2) 2” bushings
•AC Output Circuit
o(1) 2” MA/TA
o(1) 2” expansion joint
o(1) 2” locknut
o(1) 2” bushing
o(1) 2” 90° sch. 40 fitting
o2” sch. 40 to be placed in trench to AC disconnect according to design
2.) Miscellaneous Materials
•Unistrut hardware
•Unistrut straps
•Colored electrical tape
•All weather code-compliant conduit glue

Rev. 1.0 (12/19/2022) 6
2.) Installation Overview
The RaVolt installation follows a standard process consisting of the following steps:
1.) Unloading Equipment-Trucks will arrive with a palleted enclosure, palleted generator,
concrete pads, and batteries. It is recommended to level and set pads first, and then set the
enclosure and generators directly off the truck.
2.) Placing the Enclosure & Generator Pads-Choosing a desired location for both pads,
typically on the northern side of the array, about 6 feet apart. This step also consists of
leveling and compacting the designated pad locations.
3.) Placing the Enclosure & Generator- Using slings and shackles on a capable machine
(skid steer, mini excavator, or tractor), rig and place the equipment on their dedicated
concrete pads.
4.) Trenching & Conduit- There will be 2 main trenches, the AC Out trench and the
generator circuit. The AC Out trench will be from the load center on the side of the unit, to
the AC disconnect on the side of the home. The generator circuit will be from the generator
to the enclosure.
5.) Terminations- The RaVolt unit arrives with pre-installed and pre-configured equipment.
There are roughly 10 additional terminations to make on a standard project.
6.) QA/QC, Commissioning, Photos- Installers will inspect the work using the QA/QC
guidelines. There is a short commissioning process to ensure process functionality,
followed by some photos for product warranties.
These 6 steps are broken down in greater detail throughout this installation guide.

Rev. 1.0 (12/19/2022) 7
3.) Unloading Equipment
Recommended Tools & Materials: Weight rated slings, weight rated shackles, ratchet
strap.
1. Determine a safe, flat location for the truck to park for unloading.
2. The truck will arrive with the RaVolt enclosure banded to a pallet, a palleted
concrete pad, and any additional batteries in crates.
3. Operator must ensure sufficient lifting capacity of the machine to be used.
Estimated equipment weights are below:
a. Estimated weight without batteries-600 lbs
b. Estimated weight with batteries-1100 lbs
c. Unit will usually arrive to site with batteries installed (1100 lbs)
4. If using a mini excavator for unloading the equipment, utilize properly weight rated
slings and properly weight rated shackles. The unit will arrive with 4 lifting points present
on the top of the enclosure. Operator must use extreme caution to not bend or break these
lifting points, which may interfere with the enclosure’s NEMA 3R rating. If using a forklift

Rev. 1.0 (12/19/2022) 8
or skid steer for unloading the equipment, utilize properly rated 4 foot forks for lifting the
pallets.
5.) If using a forklift or skid steer for unloading the equipment, utilize a ratchet strap to
secure the equipment to the mast of the machine when transporting.
6.) Place equipment in a flat, safe location until the crew is ready to progress.
4.) Placement of Enclosure Pad
RaVolt Enclosure Pad Dimensions: 4’ L x 3’ W
Recommended Tools & Materials: Shovel, rake, hand tamper, crushed gravel, 4 foot level.
1. Determine the best location for the placement of the RaVolt enclosure. Refer to the
project specific design documents when determining the general location. The
precise location should be flat and protected from erosion and other weather
factors.
2. Level and compact the determined location for the concrete pad. It is recommended
to utilize gravel or crushed stone for compaction to create a firm base. (See below
photos.)
3. Using a two-man lift, place the concrete pad on the level and compacted location.
Notes:
Pads can be placed in any homeowner-desired orientation. Units are usually installed on
the north side of the solar array for ground mount applications, or near the meter for
rooftop applications.
Installer must ensure the enclosure placement is outside of the minimum distance required
by code from an existing gas line or propane tank.
Installer must ensure placement allows for a 4-foot serviceable radius in front and on the
sides of the RaVolt enclosure. If there will be a generator present, ensure that there is 4 feet
between the enclosure and the generator.

Rev. 1.0 (12/19/2022) 9
5.) Placement of Enclosure
Recommended Tools & Materials: Slings, shackles, straps, snips
1. After the pad has been placed in its determined location, operator will begin to
properly rig and lift the enclosure for placement. It is recommended to transport the
unit on its pallet to the determined location, before removing bands for lifting and
placing.
2. Using all 4 lifting eyes on the RaVolt unit and appropriate rigging, lift the RaVolt
enclosure off the shipping pallet and place the enclosure on top of the placed or
poured pad.
3. Installers must ensure the unit is centered on the concrete pad.
4. Utilize the provided anchoring hardware to secure the unit to the pad.
5. Install the supplied drip edge after the enclosure has been set to ensure the NEMA
3R rating is upheld. The drip edge will fit in the three holes on the top of the
enclosure, on both the front and back of the unit.
6. These T30 bolts are already installed on the enclosure. Simply remove these bolts,
place the drip edge so the holes line up on the enclosure, and replace these bolts.

Rev. 1.0 (12/19/2022) 10
6.) Trenching & Conduit
It is a requirement to contact diggers hotline prior to any excavations and confirm
location of any unmarked utility or private owned utilities.
1.) After placement of the enclosure and other project components, utilize a trencher or
mini excavator for trenching.
2.) Trenches will be in three main locations:
Generator/Grid Input: RaVolt Enclosure to Generator or Service Disconnect
AC Output: RaVolt Enclosure to the AC Disconnect at the home
PV Input: RaVolt Enclosure to the Solar Array (if necessary)
3.) Install 2” sch. 40 conduit within the trench, utilizing a 90° fitting to stub up to the above
locations prior to backfilling. Ensure that all-weather code-compliant conduit glue is being
used for connections.
4.) The following locations typically use these fittings to land into the RaVolt Enclosure:

Rev. 1.0 (12/19/2022) 11
Generator/Grid Input: Conduit stub->Female adapter->Straight flex fitting->Flexible
conduit->90° flex fitting->Bushing & locknut into disconnect on RaVolt Enclosure
AC Output: Conduit stub->Female adapter-> Straight flex fitting-> Flexible conduit->
Straight flex fitting->Bushing & locknut into loadcenter on RaVolt Enclosure
PV Input (Underground): Conduit stub->Coupler->Sch. 40 conduit cut to length->LB
fitting-> Sch. 40 conduit cut to length ->Male adapter->Bushing & locknut into the DC
disconnects on the RaVolt Enclosure
PV Input (Weatherhead): 1” Weatherhead->1” Conduit cut to length->1” Male adapter-
>Bushing & locknut into DC Disconnect
Notes:
Installers can use either flexible conduit or sch. 40 for all incoming conduit connections,
material lists will vary slightly.

Rev. 1.0 (12/19/2022) 12
Trenches must be 18”-24” deep, per code.
Installers must use warning tape above place conduit or direct burial cable before
backfilling.
Trenches must be backfilled with clean fill, free of large rocks or sharp objects.
Conduit should be secured per NEC code.
7.) Terminations
1. Install ground rod(s) at the enclosure. Ground and bond to NEC code at the
disconnect.
2. After all trenching and conduit has been completed, pull wire to all designated
locations according to design. Ensure wire sizing is per NEC code based on system
sizing.
IMPORTANT: Power output to load from RaVolt enclosure MUST be protected at the
home service entrance or prior to connecting to a load with a circuit breaker of NO
MORE THAN 200AMPS. Failure to do so could result in fire, damage, injury or death.
Generator/Grid Input:
1. Ensure there is no power on the grid/generator cables using a voltmeter.
2. Remove screws and remove the front plate from the disconnect.
3. All external AC power sources will be terminated within the disconnect on the side
of the RaVolt enclosure. This external AC power can be from the grid, a generator, or
a combination of the two.
4. After cable has been pulled from the service disconnect or the generator to the
disconnect on the side of the RaVolt enclosure, begin to make terminations in the
appropriate locations, per NEC code. Utilize the one line document for detailed
termination direction.
5. Label the incoming cable and ensure the two hot legs have been terminated in the
correct lugs. Ensure the lugs have been torqued to manufacturer specifications.

Rev. 1.0 (12/19/2022) 13
6. Ensure both the neutral and ground have been terminated in their correct locations
and torqued to manufacturer specifications.
7. If there will be both a grid and generator input, land the grid input on the line side of
the disconnect. The generator input will be terminated on the “GEN” breaker on the
Sol-Ark.
8. The RaVolt enclosure arrives pre-wired and pre-configured to allow the load side of
this disconnect to flow through the inverter, into the load center and into the home.
After landing the grid and/or generator inputs, this disconnect is complete.
AC Output:
1. Ensure there is no power to the load center using a voltmeter.
2. Remove screws and remove the front plate from the load center.
3. After cable has been pulled from the load center on the RaVolt enclosure to the AC
disconnect on the side of the home or dwelling, begin to make terminations in the
appropriate locations within the load center.
4. Ensure cables have been labeled and terminated on the load side of the 200 A
breaker according to the manufacturer specifications, and per NEC code.
5. Ensure both the neutral and ground have been terminated in the correct locations
within the load center.
6. The RaVolt enclosure arrives pre-wired and pre-configured to connect the load
center to the inverter. After terminating this AC out cable, this load center is
complete.
PV Input:
1. Ensure there is no power on the incoming PV cable. DO NOT MAKE MC4 HOME RUN
CONNECTIONS BEFORE TERMINATING THIS DC DISCONNECT.
2. Ensure cables have been correctly labeled to clearly indicate different strings,
positive and negative.
3. Run PV cables from the array, into a drip loop, into the weather head. This will run
directly into the DC disconnect on the side of the enclosure.
4. Place the switch in the “off” position and remove the screws from the DC disconnect
cover. Remove the cover.
5. Begin to make terminations within the DC disconnect according to the manufacturer
specifications. Refer to the one line document for detailed termination
instructions.
6. After terminations are made and verified, replace screws and DC disconnect cover.

Rev. 1.0 (12/19/2022) 14
7. The RaVolt enclosure arrives pre-wired and pre-configured to connect the DC
disconnects to the MPPT’s on the Sol-Ark inverter. After the incoming wires have
been terminated, these disconnects are done.
Two Wire Start:
1. If a generator is present, it will likely need a two wire start circuit. This circuit will
typically consist of 2 #10 AWG THHN/THWN wires.
2. Run these wires from the generator, through the disconnect, and into the RaVolt
enclosure.
3. Ensure there is no power to the Sol-Ark.
4. Terminate these wires on the Sol-Ark inverter using pin terminals at terminal blocks
7 +8. Please refer to the Sol-Ark manual for further instruction if necessary.
5. Terminate the generator side of the two wire start circuit at the designated two wire
start terminals. Refer to the generator’s manufacturer manual and specifications for
specific instructions.
Trickle Charge Circuit
1. If a generator is present, it will likely need a trickle charge circuit to continuously
charge the battery of the generator. This circuit will typically consist of 3 #10 AWG
THHN/THWN wires.
2. Run these wires from the generator, through the disconnect, and into the RaVolt
enclosure.
3. Ensure there is no power to the terminal blocks within the RaVolt enclosure.
4. Label these wires and terminate at the terminal blocks at the top right corner of the
RaVolt enclosure. The hot wire will be terminated at block 1, neutral at block 2,
ground at block 3.
5. Terminate the generator side of the trickle charge circuit at the designated 120 VAC
input location. Refer to the generator’s manufacturer manual and specifications for
specific instruction.
8.) Enclosure Labeling
1. The RaVolt enclosure will arrive with a packet of required labels. Ensure the labels
are present and not damaged.
2. Place the labels at their appropriate locations on the RaVolt enclosure. See the
below photo for location references.

Rev. 1.0 (12/19/2022) 15
This is the minimal labeling required, please confirm with AHJ and local utility that all
labeling requirements have been met. Please see the last page of guidelines for
additional labeling that may be required.

Rev. 1.0 (12/19/2022) 16

Rev. 1.0 (12/19/2022) 17

Rev. 1.0 (12/19/2022) 18
9.) QA/QC Walkthrough
1. After all conduit, trenching, terminations and labeling has been completed to a
satisfactory level, begin the QA/QC walkthrough using the “RaVolt QA/QC
Inspection Sheet”.
2. Thoroughly inspect all aspects of the completed work. The inspection sheet
highlights all important components to be inspected.
3. The “RaVolt QA/QC Inspection Sheet must be completed and signed off on by a
representative of the install team for warranty registration.
4. Correct any issues seen during the inspection and document these corrections on
the inspection sheet.
10.) Commissioning & Photos
Take photos of the following items for documentation:
1. RaVolt enclosure and pad placement
2. Installed anchoring hardware
3. Drip edge installed on top of enclosure
4. All conduit connections
5. All grounding & neutral to ground bond
6. Load center terminations (AC Output-2 hot, 1 neutral, 1 ground)
7. Disconnect terminations (Grid/Gen Input-2 or 4 hot, 1 or 2 neutral, 1 or 2 ground)
8. DC Disconnect terminations (Each PV string within disconnect)
9. Two wire start termination at Sol-Ark inverter
10. Trickle charge termination at terminal blocks within RaVolt enclosure
11. Battery communication cables
12. Heater setting
13. Fan setting
14. Any notable issues or blemishes on equipment
15. All placed labels
16. All communication connections
17. Functioning Wi-Fi dongle
18. Any additional RaVolt options (Project specific details)
Commissioning Steps

Rev. 1.0 (12/19/2022) 19
1.) After all terminations are made and the QA/QC walkthrough has been successfully
completed, the RaVolt system is ready to be turned on. Follow the steps in order to ensure
equipment is safe and functional.
2.) Make sure ALL breakers and disconnects are set to OFF prior to powering up any aspect
of the system.
PV Commissioning
3.) Make the MC4 home run connections on string one at the array to provide DC power to
the DC disconnect.
4.) Use a voltmeter to measure voltage on string one.
5.) Disconnect string one and repeat this process on all available pv strings coming to the
DC disconnect.
6.) Once all string voltages are verified and correct, replace the DC disconnect cover and
make all MC4 homerun connections at the array.
7.) Turn the DC disconnect dial from the “OFF” position to “ON”. This will send power to the
Sol-Ark inverter.
8.) Turn the PV disconnect switch on the Sol-Ark inverter from the “OFF” position to “ON”.
(Disconnect switch is “ON” in the horizontal, depressed position. “OFF” is the vertical
position.)
9.) The inverter should recognize the incoming DC voltage and light up the screen. Verify
the voltage reading on the inverter are the same voltages verified with the voltmeter. The
PV voltages can be seen by pressing the battery icon on the Sol-Ark.
Battery Commissioning
10.) Ensure all battery switches are in the “OFF” position. Also check to make sure all
communication cables are connected.
11.) Turn one battery on and verify the voltage using a voltmeter. Check to make sure the
Sol-Ark is reading a similar voltage.
12.) Turn the battery off and repeat this process with all batteries in the cabinet.

Rev. 1.0 (12/19/2022) 20
13.) Balance all batteries individually to within one tenth of a volt (.1 V) using the incoming
solar, making sure that the inverter is charging all batteries at an equal rate.
Disconnect Commissioning
14.) Turn off all batteries and the Sol-Ark. Remove the cover from the disconnect.
15.) With all disconnects, breakers, and equipment off, turn on the incoming power to the
disconnect. This may be a generator or the grid, test individually if both.
16.) With the disconnect set to “OFF” use a voltmeter to check the incoming voltage on the
line side of the disconnect. Check both phase to ground and phase to phase voltage to
ensure the incoming voltage is balanced.
17.) After voltages are verified from both the grid and gen inputs at the disconnect, turn the
power back off to the disconnect. Replace the cover to the disconnect.
18.) Turn the power on to the disconnect. After power is on, throw the disconnect switch to
allow power to the Sol-Ark.
19.) Flip the “Grid” and “Gen” disconnects on the Sol-Ark to “ON”. The Sol-Ark should
recognize the power and turn on.
20.) Verify voltage readings on the Sol-Ark screen coming from the grid and gen.
21.) With the battery disconnect off, turn the batteries on individually.
22.) Turn the battery disconnect on and verify that the grid and/or gen input is charging
the batteries.
IMPORTANT! Ensure that neutral and ground are bonded together at exactly ONE location
in the entire electrical system. This will be in the disconnect on the side of the RaVolt
enclosure.
Load Center Commissioning
23.) Remove the cover of the load center.
24.) Using a voltmeter, measure the voltage of the load side. Measure both phase to ground
and phase to phase voltages to verify that the voltages are balanced.
Table of contents
Popular Solar Panel manuals by other brands

Roto
Roto ZMA SF Rx manual

Jinergy
Jinergy JNMP60 series installation guide

Amerisolar
Amerisolar AS-6P18 installation manual

Solimpeks
Solimpeks Wunder CLS 2510 instruction manual

TrickleStar
TrickleStar TS601P-2 100 W Setup guide

Solar Stik
Solar Stik SOLAR VENTURE 300W PHOTOVOLTAIC ARRAY Operator and maintenance manual