Quick Installation Guide
X3-MEGA G2 20kW-60kW
Packing List
Mounting the inverter on the wall
AC protective shield x1
Double offset ring wrench x1
Inverter x1 Bracket x1
Communication terminal x1 M8 Bolt x2
Female DC connector x12
Male DC connector x12
Wi-Fi (Optional)
Documents
M8x80 Expansion bolt x4
Bracket
Nut
- Use the bracket as a template for marking the - Hammer the M8x80 expansion screw
into four holes.
- Drill the four holes with a Φ12 drill.
- Depth: at least 65mm. - Screw in the nut firmly with socket wrench.
- Lift up the inverter.
- Two methods are available
by two installers or lifting ring
position of holes with a level and marker.
Expansion screw
-Hang it onto the bracket - Fix it on the wall bracket with M8 bolts
Mounting the inverter on the stand
Bracket
Nut
- Use a bracket as a template for marking the - Screw in the corresponding screw into holes.
- Drill the four holes with a Φ10 drill.
- Tighten the nut firmly with corresponding
socket wrench.
position of the holes with a level and marker.
Screw
- Lift up the inverter.
- Two methods are available
by two installers or lifting right
- Hang it onto the bracket - Fix it on the stand with M8 bolts
- Insert the stripped section into OT terminal.
- Pull the heat-shrink tubing over grounding cable
- And crimp with crimping tool
A=B+(2~3mm)
B
- Strip the grounding cable insulation
- Select OT copper terminal
C=A+2 cm
- The tubing must be at below stripped cable section
- Pull the heat-shrink tubing onto crimped section of OT terminal
- Use hot-air blower to shrink it
so that they are in firm contact with OT terminal
- Connect the grounding cable to grounding
point on the inverter
- Tighten it with torque 10-12 N·m.
Grounding connection
- Install the fastening head and AC protective shield
- And pre-tighten the fastening head
- Strip the 35 50 AC cable insulation - mm²
L1/L2/L3: 70±5, N/PE: 100±5
- Select OT copper terminal
Unit: mm
- Disassemble the AC protective shield
- Pull the heat-shrink tubing over AC cable
Heat-shrink tubing
Heat-shrink tubing
- Insert the stripped section into OT terminal
and crimp with crimping tool
- Pull the heat-shrink tubing onto crimped section of OT terminal
- Use hot-air blower to shrink it
so that they are in firm contact with OT terminal
- Disassemble the five screws and connect the AC cable
to the corresponding AC terminal with cross screwdriver
- Tighten the screw with torque 6 N·m.
- Loosen the fastening head and fix the AC protective shield
with cross screwdriver
- Clockwise screw in the screws to fix it with 1 N·m.
-Tighten the fastening head again
Grid connection
PV connection
- Disassemble the DC contactor
Positive DC contactor
Positive PV pin
Positive terminal
Fastening head
Negative DC contactor
Negative PV pin
Negative terminal
Fastening head
6 mm
Cable size: 4-6 mm²
- Strip the PV cable insulation
- Connect the PV cable to the corresponding PV port
Fastening head, Blue rubber seal ring, Orange ring Red ring Black part Protective shield
M50X1.5 (16-20)
M50X1.5 (20-26)
M50X1.5 (26-32)
*Note: Select the corresponding rubber seal ring in accordance with cable size used. The black part no longer used.
I
I
Tighten the fastening head
Positive DC
PV pin
Negative DC
PV pin
Clamp pin
(Torque: 1.2+/-0.1 N·m.)
Positive terminal
Negative terminal
*Note: The double offset ring wrench in the accessory box is used to remove the screws on the front cover of the inverter. Keep it in a safe place
*Note: Screws used for stand installation are not in the accessory box. Please prepare them in advance.
*Note: The “Delta Grid” in “Setting”-”Grid Protection”- “FunctionChoose” is set as “Enable” in default.
In this condition, the Neutral wire is not required to be connected.
Please set “Delta Grid” to “Disable” before connecting the Neutral wire for the inverter.