1 Commissioning
1.1 App Preparation
①Install the Setup App and Monitoring App with latest version. Please refer to the product nameplate
on side of enclosure to get the application.
②Register an account on Monitoring APP. If you have got the account and password from the distribu-
tor/installer or Solinteg, skip this step.
1.2 Inspection Before Commissioning
Check the following items before staing the inveer:
①All equipment has been reliably installed.
②DC switch(es) and AC circuit breaker are in the "OFF" position.
③The ground cable is properly and reliably connected.
④ The AC cable is properly and reliably connected.
⑤ The DC cable is properly and reliably connected.
⑥The communication cable is properly and reliably connected.
⑦The vacant terminals are sealed.
⑧No foreign items, such as tools, are left on the top of the machine or in the junction box (if there is).
⑨The AC circuit breaker is selected in accordance with the requirements of this manual and local
standards.
⑩All warning signs & labels are intact and legible.
1.3 Commissioning Procedure
If all of the items mentioned above meet the requirements, proceed as follows to sta up the inveer for
the rst time.
① Turn on the AC breaker.
② Turn on the lithium batte breaker. Power on the batte pack manually if a batte is equipped.
③ Turn the DC switch, the DC switch may be integrated in the inveer or installed by the customer.
④ If the irradiation and grid conditions meet requirements, the inveer will normally operate. The
connection time for inveer to gird may take few minutes or even to more according to dierent count
code chosen in the initial settings and the real site grid condition.
⑤ Obsee the LED indicator to ensure that the inveer operates normally.