Table 2-3. Related Documentation
Document Literature Number
TMAG5124 product data sheet SLYS016
3 Hardware
The TMAG5124EVM is a small form factor, simple-to-use platform for evaluating the main features and
performance of the TMAG5124 across a wide voltage range. The EVM features a separate control board that
uses the INA303-Q1 that provides instantaneous feedback to the user in the form of LED indication for ON and
OFF, and an ALERT state that indicates that the loop is no longer sensing current. The individual TMAG5124
devices are mounted on separable coupon boards, which allows for seamless transition to adapt one of these
devices into an existing system for rapid prototyping.
3.1 Features
The layout of the TMAG5124EVM printed-circuit board (PCB) is designed to provide the following features:
• Separates TMAG5124 and control board for testing over distance of wire
• Small form factor board for external testing and prototyping capability
• Provides LED feedback to the user to quickly determine output state from the TMAG5124
• External control board that provides visual output for the correlation of trip points
See the TMAG5124 data sheet (SLYS016) for comprehensive information about the TMAG5124 device.
4 Quick Start
4.1 Option 1: Single 5-V Supply
Follow the procedure listed below to set up and use the TMAG5124EVM with a single 5-V supply:
1. Ensure that plug J5 is shorted.
2. Connect an external 5-V DC supply voltage to the VCC connection point. Ensure the 5-V supply is powered
down for now.
3. Connect a wire from "VCC_OUT" on the control board to the "VCC_OUT" port of the TMAG5124 device to be
evaluated. Repeat this process for "GND."
4. Turn on the supply. The blue "OFF" light turns on. This indicates that the device is turned on, and current is
flowing through the loop.
5. Test the TMAG5124EVM as outlined in section Section 4.3 below.
4.2 Option 2: Separate VCC and 5-V Supply
Follow the procedure listed below to set up and use the TMAG5124EVM with dual supplies, which allows the full
VCC range of the TMAG5124 to be tested:
1. Ensure that the shorting plug on J5 is removed.
2. Connect an external 5-V DC supply voltage to the 5-V connection point. Ensure that the 5-V supply is
powered down for now.
3. Connect an external DC supply voltage to the VCC connection point, which sets the voltage to the desired
level. Ensure this supply is powered down for now.
4. Connect a wire from "VCC_OUT" on the control board to the "VCC_OUT" port of the TMAG5124 device to be
evaluated. Repeat this process for "GND."
5. Power on the supply. The blue "OFF" light turns on. This indicates that the device is turned on, and current is
flowing through the loop.
6. Test the TMAG5124EVM as outlined in Section 4.3 below.
Hardware www.ti.com
4TMAG5124EVM SLYU055A – JANUARY 2020 – REVISED NOVEMBER 2020
Submit Document Feedback
Copyright © 2020 Texas Instruments Incorporated