
dimensions, install overhead beam to top of columns BEFORE drilling anchors for
offside column to insure column level.
STEP 10:
After overhead beam is assembled drill and anchor offside column as described in steps 7
and 8.
STEP 11:Figure 6 Page 20
Install the equalizing cables: Refer to figure for general cable arrangement for both Floor
Plate Style and Overhead Beam Style Lifts. Set carriages on the first safety latch
engagement. Be sure each carriage is at the same height by measuring from the top of the
base to the bottom of the carriage. Double check the latches before working under the
carriages. This dimension should be with in 1/4” Run first cable as in Figure 6. Tighten nut
on one cable stud so that the end of stud passes the nylon on the nut. Pull the other end of
cable and run nut on it; tighten both nuts. Repeat above for second cable.
STEP 12: Figure 8-9 Pages 22-23
Install the cylinders: put one cylinder into each carriage by sliding it all the way down
through the top of the cylinder mount at column base. Make sure the “Tip” on the bottom of
the cylinder will fit into the center hole on top of the cylinder mount in base. Pull the
pre-attached leaf chain in both sides up and over the chain sheave on top of the cylinders.
Refer to Figure 8 for Floor Plate Style Lift and Figure 9 for Overhead Beam Style Lift.
STEP 13: Figure 8-9 Pages 22-23
Connecting the hydraulic hoses: as shown on Figure 8 for Floor Plate Style Lift and Figure
9 for Overhead Beam Style Lift.
STEP 14:Figure 9 Page 23
Mount the power unit on lift as Figure 9.
STEP 15:
Installing cut off cable: Take the 2- eye bolts included in the parts box and install them in the
holes located in the front of each upright about 6” from the top. Install a nut, and lock washer
on either side, to make them secure.
Starting on the left side (offside), attach the 1/16” cable to the eye bolt located near the top
of the left side upright using the small aluminum ferrules. Loop the cable through the ferrule,
then through the eye of the bolt and back through the ferrule. Crimp the ferrule to hold the
cable. Pass the cable through the eye bolt on the right side (main side) and down to the
power unit. Loop the cable through the eye on the cutoff switch post, located on top of the
upswitch junction box, secure with ferrule. Make it as tight as you can without tripping the
cutoff switch.
9
Floor Plate/Overhead Style Lifts