
9
© Copyright 2008 Zoeller Co. All rights reserved.
Outdoor Prepackaged System Installation Instructions
1. Review the drawing in Fig. 3 on page 8 and the actual system
to become familiar with the components in the packaged
grinder pump system. Review where the unit will be installed.
Determine where the power feed, inlet pipe, and discharge
pipe will be located.
2. Remove the unit from packing. Prepackaged outdoor systems
are preassembled at the Zoeller Company and require a
minimum of field assembly work. Float switches are set and
tethered for proper operation from the Factory. Systems using
an automatic unit, WD or WH series, have an integral “on/off”
float switch. See Fig. 4 on page 5 for adjustment instructions.
The alarm switch should be located 3” above the pump “on”
level. Three float systems used with a control panel are placed
at 27”, 24”, and 15” from the bottom of the basin. Four float
systems used with a control panel are placed at 30”, 27”, 24”,
and 15” from the bottom of the basin. If the invert location is at
or below the level of the float switches, contact the factory.
3. Float switches are tied in place for shipping purposes on all
model prepackaged systems. Cut the cable tie around each
float switch bulb or the unit will not operate properly. Verify that
where the float switches are set will work for your application.
Verifying that the float switches are set properly and will
not hang up inside the basin is the responsibility of the
installing contractor.
4. Dig a hole for the basin. The hole should be at least 24”
larger in diameter than the basin diameter to provide 12” of
backfill all around and deep enough to provide either 12” of
compacted backfill or 6” when a concrete pad is required.
Note: Care must be taken when excavating in order to
avoid underground utilities and disturbance of existing
structure foundations. The hole should be located at least
tenfeetfromadjacentstructures. Additionaldistancemay
be required to sufficiently locate the basin outside of the
loading area of the adjacent structures.
5. The location of the inlet hub is determined by the depth of the
inlet pipe. The inlet hub must be used with 4” pipe. It is best
to install the inlet on the side of the basin opposite the float
switches. To install, use a 4” hole saw to drill into the side of the
basin at the correct elevation. Center the hub inner diameter
with the hole in the basin. Attach the hub to the side of the
basin using the sealant and hardware provided.
6. The bottom of the excavation can now be properly backfilled,
compacted and leveled. Set basin in hole. Ensure the
removable cover extends above the finished grade line and
the grade slopes away from the unit. Backfill and subbase
should be 1/8” –3/4” pea gravel or 1/8” –1/2” crushed stone.
(Reference basin installation instructions included with unit.)
Connect the 4” inlet pipe to the inlet hub.
7. Pouring a concrete anchor around system can now be
completed. Basin should be filled with water when pouring
concrete to minimize movement of the system. Backfill
around basin with specified media. Care should be used
to avoid damaging components or leaving voids when back
filling. Refer to Basin installation reference guide on more
specific requirements.
8. PVC or HDPE discharge piping is connected to the 1¼”
threaded fitting located in the basin sidewall. Support
discharge piping with sufficient backfill.
9. On basin depths of 72” and greater, the system’s disconnect
assembly is shipped loose and must be screwed into the
discharge piping. Apply pipe dope to threaded connection.
10. Connect pull rod to Pump assembly. Connect lift cable to top
of pump. Lower the pump into basin ensuring the discharge
pipe bracket slides into the disconnect fitting.
11. Note: The grinder basin is a sewage holding tank. Vent
connection should be installed in accordance with all
national, state and local plumbing codes.
12. Dig a trench for the electrical conduit. The conduit should be
located below the frost line. Follow all applicable electrical
codes.
13. Connect electrical conduit and wiring to junction box
according to wiring instructions included in this manual and
wiring diagram in box. Use the potting kit provided with the
junction box. Follow the instructions for sealing the conduit
connection at the junction box.
14. Mount the control panel within sight of the system. Connect
float switches and pump cords according to the “Pump Wiring
Instructions” found later in this manual and located inside the
panel enclosure.
15. Remove any debris from the basin. Using clean water, check
the system for proper operation.
16. Seal and secure the lid using the proper bolts and sealant
when using a lid without a formed gasket.
17. Test system for leaks and proper pump operation.
18. Record system start up data for future reference.
This set of instructions is for factory prepackaged outdoor grinder systems only. If this is a field assembled
outdoor system you can use these instructions as a guideline. If this is an indoor system then go back to pages 6-7 in this manual
that covers indoor systems.