6
5
To ensure delivery of purer and healthier water, a micro-processor is installed in the purifier that performs the
following functions:
UV Stabilization Delay: To ensure that the UV lamp is pre-heated and is working at its optimum level before it starts
disinfecting water, the controller provides a two second delay to the UV lamp when the purifier is switched on.
During this period, only the UV lamp is switched on and other electrical devices of the purifier are switched off.
Purification Delay: To ensure that the idle water lying in the internal pipes and in the UV chamber is disinfected
before being passed into the storage tank, the system provides a 5 second delay when the purifier is switched on.
During this time, the UV lamp kills all micro-organisms that may be in the water inside the UV chamber. After this
delay, all other electrical devices such as the booster pump and solenoid valve are switched on to start normal
purification process.
Alarm: To ensure delivery of purer water, A M I Ul t im a t e built-in micro controller controls and senses various vital
components.
Computer Controlled Operation
Automatic Operation
n The purifier automatically shuts off when the
storage tank is full
n The purifier does not start if the inlet water supply
2
pressure falls below 4.267 (psi /10°cm )
n The purifier automatically restarts when the water
level drops below the maximum
n The purifier does not allow any water rejection in
absence of electricity/when tank is full
TM
The AMI Ultimate Mineral RO Water Purifier is a product of advanced technology, which ensures safe and clean
drinking water. The purifier is easy and convenient to install.
Recommended Site Preparations:
nSingle Phase 100-250 V AC, 50-60 Hz. connection not more than 118 inches away from the point of installation
of the purifier
nRaw water supply with ½ inch nipple not more than 3 meters away
nDrain for rejected water not more than 3 meters away
nSpace as per the dimensions of the purifier
nWall/plane surface for optional mounting two screws and holding the machine or set on sink cabinet surface
nThe system and installation must comply with state and local laws & regulations
Specific Instructions:
n TM
AMI Ultimate Mineral RO Water Purifier is an optionally wall mountable purifier. Avoid installation on
wooden and metallic stands
n It is preferable to install the purifier under or near a sink so that the inlet and reject water lines are easily
available
Installation Instructions
Installation Procedure:
Wall Hanging Diagram (Optional)
1. Paste the central drill sticker on a wall as per your convenience.
2. Ensure that the sticker is pasted straight on the wall, then drill holes as per the space provided on the sticker
3. Now, insert the puff up with the help of a hammer
4. Screw in two 10X50 self-taping screws, 5.4 inches (138 mm) apart horizontally
5. Carefully hang the purifier on the wall with the help of wall-mounting slot holes provided on back side of the purifier
Note:
1. If the wall is not straight or the screws are not properly drilled in an even position, it will damage your purifier
2. Keep the device away from heat or direct sunlight
1. First fix the SS ball valve (marked no. 4) to the 1/4 inch port of the 3-way connecter (marked no. 2) shown in
figure 2.
2. Connect the 3-way connector to the raw water supply (marked as no. 1) as shown in the figure 3. The 3-way
connector is fitted in line with the raw water supply.
3. The other end of the 3-way connector can be connected to a tap (marked no.3) as shown in figure 4 or can be
plugged off if not required.
Step-2
Figure 1. Figure 2. Figure 4.Figure 3.
1
2
3
44
213
Step-1
Before connecting the power supply, it is important that you perform the
following functions:
1. Open the SS ball valve (handle parallel to the ball valve) to start the
flow of water into the purifier, as shown in the figure.
2. Wait for 2-3 minutes to ensure that the filters are soaked in water.
1. Now connect one end of the white pipe to the SS ball valve and the
other end to the upper push-fit elbow fitting to the left hand side of
the purifier labeled WATER IN, as shown in figure 1.
2. Similarly, connect one end of the white pipe to the lower elbow fitting
connector labeled REJECT WATER and connect the other to the
drain saddle assembly, as shown in fig 2.
3. Now connect one end of white pipe to push fit elbow fitting to the
right hand side of purifier and the other end to the 90 degree ball
valve fitted in the tank as shown in fig 3.
Step-3
Step-4
1. Connect the power supply.
2. Installation is complete.
Step-5
Figure 2.
Figure 3.
Figure 1.
Drill a 1/4” hole in the drain pipe, just below the sink. Install the Drain Clamp by first
applying the foam gasket inside the front half of the drain saddle. Punch out the cut-
out hole in the center of the pad, remove the adhesive backing, and adhere to the
inside of the drain saddle, ensuring the holes are aligned. Align the hole drilled in the
drain pipe with the hole in the drain saddle. Use Phillips screwdriver to tighten the
clamp. Avoid over-tightening. Insert tubing from the Reject Water line to t the quick
connect fitting on the drain line and check the seal.
Step-6