
EN
13
register this, stop the plant, and
trigger the alarm. Adjustment of
the flow control is done as
follows:
19. Push the flow control all the
way down.
20. Let the dosing pump operate
for 15 minutes, until it is
warm and all air has
escaped from the pump.
21. Lift the dosing control until
the control signal disappears,
and then lower it just enough
to make the signal reappear.
22. Check that the dosing nipple
(the dosing location) is tight,
and the plant is ready for
operation.
See also diagram for standard
adjustments of the dosing pump.
Important!
The stroke length of the dosing
pump must not set below 50 %.
Every week the tank
shall be emptied and
flushed and then refilled
with new antiscalant.
Every 3rd month the
tank is flushed and
cleaned before new
antiscalant is filled in.
Above-mentioned dosing amount
is calculated on basis of our
standard dimensioning
conditions. If you have doubts,
BWT A/S offers to calculate the
correct amount for your plant.
12. CIP-CLEANING
OF MEMBRANES
(OPTION)
Introduction
A CIP unit is not installed on the
plant as standard. This unit is
available as an option. However,
the plant is prepared for this
mechanically.
During normal operation,
dependent on inlet, water quality,
temperature, operating conditions
etc. the RO membranes will lose
capacity successively due to the
water’s varying content of
mineral salts, biological matter,
colloid particles and other
insoluble, organic particles.
These deposits will accumulate
during operation and cause an
increased pressure loss across the
membrane and thus a drop in
capacity and poorer water
quality.
Membranes must be CIP-cleaned
minimum once/year or
immediately when the capacity
has dropped 10 % compared to
the original capacity.
Please be aware that the
capacity drops by lower water
temperatures (approx. 3 % per
C), CIP-cleaning is not needed if
this is the case.
Conditions
it is necessary to perform the CIP
cleaning with chlorine-free water
of a good quality at a
temperature of approx. 20C.
During circulation of cleaning
fluid in the membranes, the
temperature may never exceed
35 C and the pH value shall be
kept between 2 and 11.5.
The flow direction during CIP
cleaning must be the same as
during operation.
BWT CIP 4 is an acid cleaning
agent used for dissolving
inorganic layers including iron,
whereas the alkaline cleaning
agent BWT CIP 10 is used for
dissolving organic layers
including oil.
Never use sulphuric acid H2SO4
for CIP cleaning as there will be
a risk of precipitation of gypsum
(calcium sulphate).
When mixing cleaning agents,
preferably use permeate; soft
water can also be used. However
you have to use a larger amount
of acid or alkaline to obtain the
desired pH value, which for acid
must be approx. pH 4 and for
alkaline solutions must be
approx. pH 10.
BWT CIP 4 is sold by BWT Item
No.: 70 19 57 020
BWT CIP 10 is sold by BWT
Item No.: 70 19 57 010
While the plant is operating, fill
the CIP tank with permeate.
Open valve V8 (See diagram of
principle)
When the CIP tank has been
filled with permeate, stop the RO-
plant and press "stop".
High pressure pump P1 may
never operate during CIP
cleaning.
Adjust the valves as follows:
Close valve: V2, V10 (See
diagram of principle).
Open valve: V7, V8, V9 (See
diagram of principle).
Mix the cleaning agent.
It is of advantage if the
temperature is kept at approx. 35
°C during the CIP cleaning.
Start the CIP cleaning on the
panel front.
P2 and HE1 start and the CIP-
agent now circulates across the
membranes.
Check that there is enough CIP
agent in the tank, so that P2 does
not run dry.