Page 5
2
1. Connect electricity supply. Make sure that the supply cable is at least 4mm at 220V
Note: Make sure that the facility supply voltage and frequency are the same as shown on
the equipment name plate.
2. Connect to power supply AC 220V. Switch on the equipment. The LED display will show the
normal voltage as 220V.
3. Set time and power according to the requirements of paint used for curing to achieve the
best curing result (usually, the values are set at 15 mins in time and 70% in power).
4. Adjust the distance from heat source to paint surface (usually, keeping a distance of
45cm from the paint surface is the best).
5. Protect the lamp against shocks and vibrations even when it is cold.
6. During the curing process, the paint surface must be clean without water and impurities.
7. Preferably do not touch quartz with bare hands. If grease or chemical compound have
been deposited on quartz, simply clean before lighting with cloth moistened with alcohol.
Install machine
Data displayed
on screen
Set up temperature
Switch off
Connect input
power
Switch on
30-60cm
ON
OFF
Set up time
ON
OFF
Heat source parallel
to paint surface at a
distance of 30-60cm
00
10
20
30
40
50
60
ON
5. Operation