HALFEN HTT Assembly Instructions
Deutsch English
Polski
HTT Sound Insulation Element
Pre-cast production
HTPL Joint sheets to be attached on the side wall following the stairway using the integrated self-adhesive tape. The
joints must be cleaned carefully and carried out without lack! Afterwards they have to be clossed with adhesive tape.
Bottom HTT nailing bar to be fixed to the formwork at the appropriate place. Insert HTT Element.
Top HTT nailing bar to be attached using a fixing structure (e.g. timber batten ) and placed on the HTT Impact
sound insulation unit from the top. The HTT Element must be aligned and fixed vertically and at the appropriate positi-
on.
Installation of site reinforcement according to accounts of the structural engineer. Concreting landing and stairway.
Shuttering in the pre-cast plant
Installation on the construction site