Fuel gas quality. e appliance has been de-
signed to operate with gas free of impurities; oth-
erwise it is advisable to t special lters upstream
from the appliance to restore the purity of the gas.
Storage tanks (in case of supply from LPG
depot).
- New LPG storage tanks may contain residual
inert gases (nitrogen) that degrade the mixture
delivered to the appliance casing functioning
anomalies.
- Due to the composition of the LPG mixture,
layering of the mixture components may occur
during the period of storage in the tanks. is
can cause a variation in the heating power of
the mixture delivered to the appliance, with
subsequent change in its performance.
1.4 HYDRAULIC CONNECTION.
Important: In order not to void the warranty
before making the boiler connections, carefully
clean the heating system on the primary heat
exchanger (pipes, radiators, etc.) with special
pickling or de-scaling products to remove any
deposits that could compromise correct boiler
operation.
Treatment of the water of the heating and water
system is required, in compliance with the
technical standards in force, in order to protect
the system and the appliance from deposits (e.g.
limescale), slurry or other hazardous deposits.
Hydraulic connections must be made in a
rational way using the couplings on the boiler
template. e boiler safety valve outlet must be
connected to an appropriate drain. Otherwise,
the manufacturer declines any responsibility in
case of ooding if the drain valve cuts in.
Attention: the manufacturer declines all liability
in the event of damage caused by the installation
of an automatic lling system that is not its own
brand.
In order to meet the system requirements
established by the regulations in terms of
pollution of drinking water, we recommend
installing the IMMERGAS anti-backow kit to be
used upstream of the cold water inlet connection
of the boiler. It is also recommended that the heat
transfer uid (e.g. water + glycol) entered in the
primary circuit of the boiler (heating circuit),
complies with the local regulations in force.
Important: to preserve the duration of appliance
eciency features, in the presence of water whose
features can lead to the deposit of lime scale,
installation of the “polyphosphate dispenser” kit
is recommended.
1.5 ELECTRICAL CONNECTION.
e Mini Nike 24 4 ErP boiler has an IPX4D
protection rating for the entire appliance. Elec-
trical safety of the unit is reached when it is cor-
rectly connected to an ecient earthing system
as specied by current safety standards.
Important: the manufacturer declines any
responsibility for damage or physical injury
caused by failure to connect the boiler to an ef-
cient earth system or failure to comply with the
reference standards.
Also ensure that the electrical installation
corresponds to maximum absorbed power
specications as shown on the boiler data-plate.
Boilers are supplied complete with an “X” type
power cable without plug. e power supply
cable must be connected to a 230V ±10% /
50Hz mains supply respecting L-N polarity and
earth connection . is network must also
have an omnipolar circuit breaker with class III
over-voltage category. When replacing the power
supply cable, contact a qualied company (e.g.
the the Authorised Aer-Sales Technical Assis-
tance Service). e power cable must be laid as
shown. In the event of mains fuse replacement
on the P.C.B., use a 2A quick-blow fuse. For the
main power supply to the appliance, never use
adapters, multiple sockets or extension leads.
a variety of users in existing buildings. e
boiler takes the combustion air directly from
the installation room and is equipped with
draught-breaker/anti-wind device. Due to
lower eciency, any other use of this boiler
must be avoided as it would lead to greater
consumption and higher operating costs.
Important: Wall mounting of the boiler must
guarantee stable and ecient support for the
generator.
e plugs (standard supply) are to be used only in
conjunction with the mounting brackets or xing
template to x the appliance to the wall; they only
ensure adequate support if inserted correctly (ac-
cording to technical standards) in walls made of
solid or semi-hollow brick or block. In the case of
walls made from hollow brick or block, partitions
with limited static properties, or in any case walls
other than those indicated, a static test must be
carried out to ensure adequate support.
N.B.: the hex head screws supplied in the blister
pack are to be used exclusively to x the relative
mounting bracket to the wall.
ese boilers are used to heat water to below
boiling temperature in atmospheric pressure.
ey must be connected to a central heating
system and hot water circuit suited to their
performance and capacity.
1.3 GAS CONNECTION.
Our boilers are designed to operate with methane
gas (G20) and LPG. Supply pipes must be the
same as or larger than the 3/4”G boiler tting.
Before connecting the gas line, carefully clean
inside all the fuel feed system pipes to remove any
residue that could impair boiler eciency. Also
make sure the gas corresponds to that for which
the boiler is prepared (see boiler data-plate). If
dierent, the appliance must be converted for op-
eration with the other type of gas (see converting
appliance for other gas types). e dynamic gas
supply (methane or LPG) pressure must also be
checked according to the type used in the boiler,
which must comply with the regulations in force,
as insucient levels can reduce generator output
and cause malfunctions.
Ensure correct gas cock connection by follow-
ing the mounting instructions illustrated in
the gure. e gas supply pipe must be suitably
dimensioned according to current regulations in
order to guarantee correct gas ow to the burner
even in conditions of maximum generator output
and to guarantee appliance eciency (technical
specications). e coupling system must con-