Rockwell Automation Publication 2500-IN001E-EN-P - April 2019 7
Preface
This publication provides procedures to the following:
• How to receive and handle a CENTERLINE® 2500 shipment.
• How to install the received columns.
•Howtoinstallcables.
• How to access internal components.
• How to install and remove units.
• How to start up (commission) a newly installed motor control center.
• How to maintain the motor control center.
Summary of Changes This publication contains new and updated information as indicated in the
following table.
Topic Page
Updated product photos to reflect Series D features. Throughout
Added introductory paragraph to Preface section. 7
Updated artwork and table 2, and added tables 4 and 6 in Figure 2. 12
Updated artwork, and added both notes in Figure 5. 14
Updated table information in Technical Data section. 15
Added bullet-pointed text about cable entry and exit points in Location Planning section. 21
Added Important table about column air gap requirements. 26, 27
Added table row for 500 mm column width in Figure 10. 27
Updated Seal IP42 and IP54 Enclosures Before Connection section to include IP42 enclosures. 28
Converted step 5 to Attention table in Seal IP42 and IP54 Enclosures Before Connection section. 28
Updated table information in Seismic Information section. 36
Added content to Access the Power Bus section for main and withdrawable units. 37
Added Figures 14 and 15, and revised artwork in Figure 16 (formerly Figure 14). 38
Expanded Figure 17, and added Figure 18 for power bus splicing configurations. 42
Increased number of PE conductors that can be present from three to four. 46
Updated horizontal PE photograph in step 1 of Splice the PE Conductor subsection. 46
Added the second paragraph in Control and Network Cables subsection. 48
Added label examples and expanded table footnote inTorque Specifications section. 48
Added last sentence to third paragraph about cable strain on the termination blocks. 49
Added Important table to Cable Bracing section. 51
Added last paragraph, Table 5, and Important table in Secure LoadWires section. 52
AddedType 5 to Form 4b in first bullet point and to corresponding picture. 52
Added Rotary-operator Handle Sizes section. 55
Revised artwork in Figure 20 with newer handle design. 55
Revised steps 2…4 and the corresponding artwork in Open the Unit Door in the ON/I Position
subsection.
56
Revised step 2 and the photograph in Lock Units in the OFF/O Position subsection. 57
Added Lock Units in the ON/I Position subsection and Figure 18. 57
Added Medium Rotary-operator Handles subsection. 58
Revised Figure 21 to remove the medium rotary-operator handle art. 65
Updated both photographs and their callouts in Figure 21. 67
Updated photograph and callouts in Figure 22. 68
Updated photograph in Figure 24 to show an Ethernet network connection. 69
Switched‘withdraw lever’and ‘locking mechanism’in step 2 and in graphic. 70
Consolidated separate withdrawable position graphics into new Figure 26. 71
Added‘Clean ventilation mesh’to step 13 of Suggested Maintenance Guidelines. 83
Changed Stratix switch model to 5700 in first sentence of Cable Routing subsection. 86
Added Appendix B. 101