Please see the DL2 Installation manual for power requirement to CU-M001-SA and JB70D2-
SA units.
The Junction box JB12-SA is only a terminal box with no requirement for power.
The CU-M001-SA Display operator unit may be positioned in the same area as the replaced
DL850 Operator unit was. The CU-M001-SA is of less physical size than the replaced display
unit.
The JB70D2-SA Electronic unit includes In/Outputs for external equipment. This require the
JB70D2-SA to be positioned close to the wheel house area to route the external equipment
cabling.
The communication cable requirement for DL2 is 3 twisted pair individually shielded. 1 pair
used to supply 24VDC power from JB70D2-SA to Sensor DL2SE-SA. The dimmension of
cable may limit the maximum length of cable.
The DL850 cable is a 4 pair cable so it is recommended two use two pair in double for the
24VDC.
Example: Minimum spec of DL850 cable is 0.325sq.mm. 2 x 0.325 = 0.65sq.mm.
The maximum length of cable 0.65 sq.mm is 180m.
An alternative may be to supply 24VDC at junction box by replacing JB12-SA with JB40POW-
SA.
The DL2SE-SA sensor is included a moulded in 40m cable.This assures a completly water
tight sensor and will not be destroyed by ooded sensor area such as the old DL850 sensor
did.
INSTALLING THE DL2