vita Vacumat 500 User manual

VITA - Vacumat 500
Operating Manual

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 1
Table of Contents
1 Technical Specifications................................................................................................................ 2
2 Safety advice................................................................................................................................... 3
3 Installation and Starting-Up........................................................................................................... 3
4 Control panel................................................................................................................................... 4
4.1 Description (Block A) ................................................................................................................. 4
4.2 Description Pre-drying (Block B)................................................................................................ 4
4.3 Description Heating-up (Block C)............................................................................................... 5
4.4 Description Firing temperature & End temperature (Block D) ................................................... 5
4.5 Description Vacuum (Block E)................................................................................................... 5
4.6 Description Slow / Fast cooling (Block F) .................................................................................. 6
4.7 Description of Keyboard & Lift position keys (Block G).............................................................. 6
4.8 Operating Block B – Pre-drying temperature & Pre-drying time ................................................ 7
4.9 Operating Block C - Heating up ................................................................................................. 8
4.10 Operating Block D - Firing temperature & End temperature .................................................. 9
4.11 Operating Block E - Vacuum parameters............................................................................. 10
4.12 Operating Block F - Slow cooling ......................................................................................... 11
5 Adjusting the firing chamber temperature................................................................................. 12
6 Protection against Power failure................................................................................................. 12
7 Utilities........................................................................................................................................... 13
8 Changing the muffle..................................................................................................................... 14
9 Error Messages / Service............................................................................................................. 15
10 Additional service advice............................................................................................................. 15
11 Firing Cycle ................................................................................................................................... 16

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 2
1 Technical Specifications
Dimensions: Height: 560 mm
Width: 360 mm
Depth: 335 mm
Firing Chamber (interior space): Diameter: 96 mm
Height: 70 mm
Weight: 19 kg
Power Supply: 110/230 Volts A.C., 50/60 Hz
Max. power consumption: 1,5KW
Classification: Safety Class I
Fuse: 230V / 8 amp, 110V / 2 amp
Max. firing chamber temperature: 1200°C
Power supply for vacuum pump: 110/230 Volts A.C., 50/60 Hz, max. 0,2 KW
Vacuum pump (optional): Type PJ 9080-023.3, 110/230 Volts A.C., 50/60 Hz, IP 20
Weight: approx. 6,4 kg
Supply schedule:
Special shipping carton, containing:
1 VITA VACUMAT 500 furnace
1 control panel
1 firing tray
1 mains power lead
1 pair of furnace tweezers
1 set of firing stands A+B, grey
1 set of firing stands G, grey
1 Operating Manual
1 vacuum pump (only supplied on special order)
supplied with painted casing: 1 aluminium-plate for depositing hot firing trays
If any items are missing, contact your supplier immediately. Save the carton and packaging materials in case
you ever need to relocate the furnace.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 3
2 Safety advice
This furnace may only be operated with the supplied mains power lead!
Prior to making the electrical connection, make sure that
- the furnace power switch is OFF.
- the furnace voltage matches your power supply. Confirm the line voltage for your furnace by checking the
line voltage designation on the rating plate on the back of furnace.
- the protection fuse and the wiring system in your laboratory are suitable to carry the total electric load of
the furnace (see rating plate and/or technical specifications).
- the wiring system in your laboratory has an efficient earth connection in compliance with rules and laws in
force.
- the plug is inserted into a suitable wall socket which can easily be reached.
- the mains power lead is laid out in such way as to ensure that it does not come into contact with any hot
surfaces or objects and that it does not obstruct any passage way.
!The manufacturer disclaims any liability in case these accident-preventing rules are not observed !
This is a warning symbol about dangerous electrical current. Disconnect furnace
from the mains power supply before opening it for maintenance or repair work.
Contact your VITA dealer or a qualified service technician if your furnace needs
to be repaired or serviced.
Typ PJ 9080-023.3
or This label gives information on the power connection of the vacuum pump.
Typ PJ 9081-023.3
It is not necessary to clean the inside of the firing chamber, but only to wipe the
surface of the insulation at the lower edge of the firing chamber regularly with a
damp cloth. This applies also to the O-ring on the lift support plate.The casing
can likewise be cleaned using a damp cloth. In order to ensure smooth gliding of
the firing tray lift at all times, the lift guide rails should be wiped regularly with a
dry cloth.
Never use cleaning agents or flammable liquids for cleaning the furnace
3 Installation and Starting-Up
(see also Safety Advice)
1. When positioning the furnace, the minimum distance between all sides of the furnace and any wall
should be at least 25 cm.
2. Make sure the furnace power switch is OFF. Connect the furnace to the mains outlet, using the supplied
mains power lead.
3. Connect the plug of the vacuum pump to the socket at the rear of the furnace and then slide the vacuum
hose onto the nozzle.
4. Attach the operating panel to the front of the casing and connect the spiral cable to the right or left side.
5. Press the Power ON/OFF switch at the left to switch on the fuirnace. The firing tray lift will descendto ist
lower position. The LCD indicators in Block A display the current firing chamber temperature and the time
of day.
6. Place the firing tray onto the lift support plate.
Notice: Never operate the VITA VACUMAT 500 without the firing tray on the lift support plate. It may
cause damage to the furnace.
7. Press the "Start" key. The firing tray ascends into the firing chamber, and the temperature starts
risinguntil it has reached the factory-set starting temperature of 500°C.
Once the starting temperature has been reached, the furnace is ready for use with any firing program.
For further operating information, see the appropriate section of the Operating Manual.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 4
4 Control panel
4.1 Description (Block A)
Firing chamber temperature 20°C - 1200°C
1. Program No. 0 Close withaut heating
2. Program No. 1 - 200 Firing programs
3. Program No. 250 - 295 Utility programs
VACUUM in millibar during active vacuum program
4.2 Description Pre-drying (Block B)
Pre-Drying LED
1. flashes when Input-Mode PRE-DRYING is active
2. „ON“ when PRE-Drying is a step of the selected program
3. flashes when PRE-DRYING is active
Display shows:
1. Stand-by temperature 200°C-800°C
2. PRE-DRYING temperature 200°C-800°C
3. PRE-DRYING time 0:00 min - 40:00min
Acivates Input-Mode
1. Changes PRE-DRYING temperature
2. Changes PRE-DRYING time
3. Calls set-points (temperature&time) during running program
LED min:sec
1. „ON“ when Input-Mode for PRE-Drying time is active
2. „ON“ for approx. 3 sec. when selected PREY-DRYING time is called during
running program
LED °C
1. „ON“ when Input-Mode for PREY-DRYING temperature is active
2. „ON“ for approx. 3 sec. when selected PREY-DRYING temperature is called
during running program
Block A Block B Block C Block D Block E Block F Block G

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 5
4.3 Description Heating-up (Block C)
Heating-UP LED
1. flashes when Input-Mode is active
2. „ON“ indicates a firing program has been selected
3. flashes when HEATING-UP is in program
Display shows:
temperature rising rate in 20°C - 130°C
Actives Input-Mode for temperature rising rate
4.4 Description Firing temperature & End temperature (Block D)
END temperature LED
1. flashes when Input-Mode END temperature is active
2. „ON“ when HOLD time for End temperature is a step of the selected program
3. flashes when HOLD time of END temperature is active
Display schows:
1. END temperature 200°C-1200°C
2. HOLD time of END temperature 0:00 min - 40:00 Min
Actives Input-Mode
1. Changes END temperature
2. Changes HOLD time for END temperature
LED min:sec
1. „ON“ when Input-Mode HOLD time of END temperature is active
2. „ON“ for approx. 3 sec. when selected HOLD time is called during running
program
LED °C
1. „ON“ when Input-Mode END temperatur is active
2. „ON“ for approx. 3 sec. when selected END temperature is called during
running program
4.5 Description Vacuum (Block E)
VACUUM LED
1. flashes in Input-Mode
2. „ON“ when VACUUM is a step of the selected program
3. flashes when VACUUM is active
Display shows:
VACUUM time 0:00 min - 40:00 min
Activates Input mode
1. Changes VACUUM time
VACUUM start always when HEATING-UP starts

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 6
4.6 Description Slow / Fast cooling (Block F)
COOLING LED
1. flashes when Inpu-Mode COOLING is a active
2. „ON“ when COOLING is a step of the selected program
3. flashes when COOLING ist active
Display shows:
COOLING temperature 300°C - 1000°C
Activates Input-Mode
1. COOLING temperature 300°C - 1000°C
2. Select programm FAST COOLING of firing chamber to 50°C below STAND-
BY temperature
4.7 Description of Keyboard & Lift position keys (Block G)
INPUT Keybord
Lift „ASCEND“
Lift „DESCEND
ENTER - Key
DELETE - Key
Program „STOP“
1. Program „START“
2. STAND-BY program „START“ (firing chamaber closed and HEATING-UP to STAND-BY)

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 7
4.8 Operating Block B – Pre-drying temperature & Pre-drying time
Select program using
keyboard and press
Enter-Key '#''
flashing PRE-DRYING LED
PRE-DRYING time LED min/sec."ON"
LCD shows preselected PRE-DRYING time
Change PRE-DRYING
time?
YES
NO
enter value using keyboard
and press Enter-Key '#'
flashing PRE-DRYING LED min:sec
PRE-DRYING temp. LED °C 'ON'
LCD shows PRE-DRYING temperature °C
Valid Input: 200°C - 800°C
Change PRE-DRYING
temperature?
NO
YES
enter value using keyboard
and press Enter-Key '#'
PRE-DRYING LED 'ON'
LCD shows PRE-DRYING temperature
Valid Input: 0 min - 40:00 min
E N D
Press
Enter-Key '#'
Press
Enter-Key '#'
Input-Mode may be interrupted
at any time by pressing
the 'STOP'-Key.
Invalid entries will result
in error message 'Err'.
Activate Input-Mode with
PRE-DRYING Key
After program start PRE-DRYING values may be changed until PRE-DRYING LED is flashing.
Thereafter program sequence is active and changes are no longer possible.
When Input-Mode is active,
PRE-DRYING key will switch
between input of PRE-DRYING time
and PRE-DRYING temperature.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 8
4.9 Operating Block C - Heating up
Select program using
keyboard and press
Enter-Key '#'
flashing HEATING-UP LED
LCD shows ???
Change temperature
rising rate?
YES
NO
enter value using keyboard
and press Enter-Key '#'
HEATING-UP LED 'ON'
LCD shows value °C/min
E N D
Press
Enter-Key'#'
Input-Mode may be interrupted
at any time by pressing
the 'STOP' - Key
Invalid entries will result
in error message 'Err'
Activate Input-Mode with
HEATING-UP key
Valid Input: 20°C - 120°C/min
After program start HEATING-UP values may be changed until HEATING-UP LED is flashing.
Thereafter program sequence is active and changes are no longer possible.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 9
4.10 Operating Block D - Firing temperature & End temperature
select program using
keyboard and press
Enter-Key '#'
flashing END temperature LED
LED min:sec HOLD time "ON"
LCD shows End temp. HOLD time
Change
HOLD time?
YES
NO
enter value using keyboard
and press Enter-Key '#'
flashing END temperature LED
LED °C END temperature "ON"
Valid Input: 0 min - 40:00 min
Change
END temperature?
NO
YES
enter value using keyboard
and press Enter-Key '#'
END temperature LED 'ON'
LCD shows END temperature °C
Valid Input: 200°C - 1200°C
E N D
Input-Mode may be interrupted
at any time by pressing
the 'STOP' key
Invalid entries will result
in error message 'Err'
Activate Input-Mode with
END temperature key
After program start END temperature and END temperature HOLD time may be changed until
LED °C or LED min:sec are flashing.
Thereafter program sequence is active and changes are no longer possible.
When Input-Mode is active,
END temperature key will switch
between input of
END temperature and
End temperature HOLD time
LCD zeigt Endtemperatur
Press
Enter-Key '#'
Press
Enter-Key '#'

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 10
4.11 Operating Block E - Vacuum parameters
Select program using
keyboard and press
Enter-Key '#'
enter value using keyboard
and press Enter-Key '#'
E N D
Press
'*'-Key
Input-Mode may be interrupted
at any time by pressing the
'STOP' key
Invalid entries will result in
error message 'Err'.
Activate Input-Mode with
VACUUM key
Change
VACUUM time?
ja
NO
flashing VACUUM LED
LCD shows VACUUM time in min:sec
(see *)
flashing VACUUM LED
LCD shows VACUUM time in min:sec
Valid Input: 0 min - 40:00 min
* VACUUM time:
Based on the selected temperature rising rate (°C/min), VACUUM time is calculated and
preselected automatically.
The VACUUM pump starts as soon as the temperature starts rising.
When END temperature has been reached, VACUUM stops.
The calculated VACUUM active time is equal to the temperature rising time, i.e. until
END temperature has been reached.
If either a longer or shorter VACUUM time is required, change the preselected
VACUUM time as described above.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 11
4.12 Operating Block F - Slow cooling
Select program using
keyboard and press
Enter-Key '#'
flashing COOLING LED
LCD shows COOLING temp. °C
enter value using keyboard
and press Enter-Key '#'
COOLING LED 'ON'
LCD shows COOLING temp. °C
Press
Enter-Key '#'
Input-Mode may be
interrupted at any time by
pressing the 'STOP' key.
Invalid entries will result
in error message 'Err'.
Activate Input-Mode with
COOLING key
Change
COOLING temp. ?
YES
NO
E N D
After program start COOLING values may be changed until COOLING LED'S are flashing.
Thereafter program seqeunce is active and changes are no longer possible.
Valid Input: 300°C - 1000°C

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 12
5 Adjusting the firing chamber temperature
The VITA - VACUMAT 500 furnace is supplied with a digitally controlled potentiometer for automatic
adjustment of the firing chamber temperature. The factory-set temperature test circuit is adjusted as follows:
At 1000°C a voltage of 9.25 millivolt may be measured at the built-in thermocouple (PtRhPt). Should the
measurements differ during the life of the furnace, the adjustment may be checked and corrected using the
supplied program.
The adjustment program is selected as follows:
1. Select program No: 294 and press the "#"-Key
The program displays the following settings:
Pre-drying temperature: 600°C
Pre-drying time: 6:00 min
Heating-up time: 66°C / min
Final temperature: 1000°C
Hold-time for final temperature: 5:00 min
2. press the "Start"-Key
The program starts, parameters may not be changed, the program must be stopped by pressing the "Stop"
Key.
The LCD-Display in Block A indicates the temperature of the firing chamber in °C (degrees Celsius).
The LCD-Display in Block B indicates the value in millivolt.
After two minutes in the hold-phase at a temperature of 1000°C, a short signal sounds which indicates the lift-
keys "UP / DOWN" may now be used for adjustment. Using the "UP / DOWN" keys (UP = Increase, DOWN =
Decrease), the voltage value may now be adjusted to 9.25 millivolt. At a temperature range of 1000°C a
change of 0.01 millivolt causes a change in the firing chamber temperature of 1°C.
6 Protection against Power failure
The VITA VACUMAT 500 is protected against power failure. This backup device is activated immediately in
the event of a mains power failure during a firing or stand-by program. If the power failure lasts for less than
20 seconds the program continues. In case of power failure for more than 20 seconds the program is aborted
and the following is displayed:
The LCD-Display of Block B indicates the phase where the program aborted:
Phase 1 = Pre-drying phase
Phase 2 = Heating-up phase
Phase 3 = Hold-temperature phase
Phase 4 = Cooling phase
Pressing of the "STOP"-key deletes all messages and the furnace is once more ready for use.
Notice: In case of the mains power supply in the laboratory being turned off accidentally with the furnace in
operation or on stand-by, the same symptoms as those of a power failure will be indicated after the
power resumes.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 13
7 Utilities
All programs listed may be selected by entering the respective program number using the keyboard (BlockH).
The selection must be confirmed by pressing the "#"-Key. The programs may only be selected if no firing
program is active. To stop or cancel a program, press the "Stop"-Key
Number Program Description Display Operating
Keys
276 + # Show Operating Hours Display in hours and minutes LCD Block A
277 + # Show Software Version displays software version LCD Block A
281 + # Stand-by temperature Entry: 200°C - 800°C (500°C ∂)LCD Block B Keys
Block G + #
282 + # Set signal on program end Selection 1 = signals once
Selection 2 = continuous signal ∂LCD Block B Pre-Drying
Key + #
283 + # program termination with
‘Stop’ Key Selection 1 = press ‘Stop’ 2x
Selection 2 = press ‘Stop’ once ∂LCD Block B Pre-Drying
Key + #
284 + # start firing program when
temperature of firing chamber
is higher than stand-by
temperature
Selection 1 = start when temp. is
higher than stand-by temperature ∂
Selection 2 = start at stand-by
temperature
LCD Block B Pre-Drying
Key + #
285 + # Set volume select ‘0’ - ‘9’ LCD Block B Keys
Block G + #
289 + # Initialization all factory-set time/date values are
read into memory (VITA settings) LCD Block B
291+ # Liftpositions:
Pre-Drying and Cool-Down Pos.1, 1st pre-drying step
Value 0 - 40
Pos.2, 2nd pre-drying step
Value 30 - 60
Pos.3, 3rd pre-drying step
Value 50 - 150
Pos.4, cool-down step
Value 30 - 120
Inv., intervall time
Value 10 - 60 sec
LCD Block B input with
Block G + #
keys
select pos.
with
pre-drying
key
292 + # Lift speed select S up 0 - 99
select S down 0 - 99 lower LCD
Block B Keys Block
G + #
select using
pre-drying
key
293 + # Lift stop select L up 0 - 99
select L down 0 - 99 lower LCD
Block B Keys Block
G + #
select using
pre-drying
key
294 + # Temperature-Adjustment see description ‘Adjusting the firing
chamber temperature
0 close firing chamber without
heating Keys
Block G + #
∂Factory settings

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 14
8 Changing the muffle
•Only to be carried out by a qualified service technician!
•Contact your VITA dealer or authorized service personnel!
Switch off furnace and disconnect from the mains power supply!
1. Unscrew the 2 screws on the rear panel and remove it.
2. Unscrew the six screws on the to casing of the furnace.
3. Lift off top casing of the furnace
4. Unscrew and remove tthe screws (22254) on the top cover of ring chamber.
5. Disconnect all wires from the thermocouple.
6. Lift out insulation stone complete with thermocouple.
7. Disconnect the wires from the defective quartz gless spiral muffle and then lift it out.
8. Place new muffle into position, then reassemble the furnace in reverse order to that given above
CAUTION: Do not forget to reconnect the earthed condactor wire to the furnace top casing!

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 15
9 Error Messages / Service
The VITA - VACUMAT 500 furnace is equipped with a self - checking system which detects and indicates
possible errors. The following error messages may occur:
Err 1 the required i.e. the preselected temperature has been exceeded by 80 °C.
1. Hardware failure, change CPU-board
Err 2 Rupture of thermocouple
1. Defective temperature sensor, change thermocouple
Err 3 Error in vacuum system
1. Check and clean lift plate seal and lower edge of firing chamber
2. Check/change seals at firing chamber connections.
3. Check vacuum pump, change of membran and/or valve flap may be required.
Err 4 Furnace does not heat
1. Check/change fuse T8H 110 V at back of furnace
2. Check/change firing muffle
Err M Should the lift not have reached ist upperor lower within a certain time, the error message „errM“
will appear in flash mode in the temperature indicator °C. At the same time, this monitors the
microswitches for the upper lift positions.
The error message „errM“ will also appear if the microswitch contact is defect. To delete the error
message „errM“, press „STOP“ key. The time lapse until this error message appears can be set
using programm 901 and key #. The time value can be selected in the range 10 - 20 seconds; the
factory stored value is 15 seconds. The time selected must be longer than the time the lift drie takes
to move from the lower to the upper position. If the time is too short, the motor will switch off too
early and the lift will be unable to reach ist nd position. In case of incorrect input of program
parameters, a short signal indicates the error and the last valid input is assumed. In order to
recognize the reliable closing contact of the mocroswitches, the debounce-time is set via program
no. 902 and key #. The range for the setting is 2 - 10 ( number x 15 msec. = debounce time ). The
factory-set value is 3. This setting should not be altered.
In case of incorrect input of program parameters, a short signal indicates the error and the last valid input is
assumed.
In case of recurring "Err"-Messages after Power OFF/ON, please contact the VACUMAT service Department
of your local VITA distributor.
10 Additional service advice
Daily usage of the VITA VACUMAT 500 is highly demanding. Due to external influence, such as very fine
dust, the lift drive system needs to be cleaned regularly with a dry cloth.
The following problems/changes may be solved using the supplied utilities:
1. Lift drive too slow : Program 292 increases/decreases the lift speed.
2. Change lift position „Pre-Drying" and „Cooling": Program 291 will change the respective positions.
For servicing, the VITA VACUMAT 500 may only be shipped in special packing cases. If the original packing
case is unavailable, special packing cases may be ordered.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 16
11 Firing Cycle
VITA OMEGA Progr.
no.
Pre-
Drying
°C min. °C/min.
Temp.
approx
°C min. VAC
Oxidation firing 1 600 0.00 110 980 5.00 ---
NEW (1) 1st opaque firing (powder) 2 600 2.00 55 970 1.00 x
1st opaque firing (paste) 52 500 6.00 110 950 1.00 x
NEW (1) 2st opaque firing (powder) 3 600 2.00 55 950 1.00 x
2st opaque firing (paste) 53 500 6.00 55 930 1.00 x
Dentine firing 4 600 6.00 55 930 1.00 x
2nd dentine firing 5 600 6.00 55 920 1.00 x
3nd dentine firing 6 600 6.00 55 910 1.00 x
Glaze firing 7 600 0.00 110 930 1.00 ---
Glaze firing with VITACHROM
DELTA Fluid / Akzent Fluid 8 600 4.00 110 930 1.00 ---
Glaze firing with
Glasurmasse 740 / Akz 25 9 600 4.00 100 900 1.00 ---
Margin porcelain firing "MARGIN∗"10 600 6.00 55 950 1.00 x
(1) = Firing of opaque porcelains marked with an asterisk at approx. 20°C higher.
The vacuum time, indicated in the "VAC" column by an „X", resuluts automatically from the given temperature
rise °C/min. The vacuum switches on at the biginning of the temperature rise and switches off again when the
end temperature is reached. Follow manufacturer’s instructions !
VITA OMEGA 900 Progr.
no.
Pre-
Drying
°C min. °C/min.
Temp.
approx
°C min. VAC
Oxidation firing 41 Follow manufacturer’s instructions !
1st opaque firing (powder) 42 600 2.00 75 900 2.00 x
1st opaque firing (paste) 54 500 6.00 50 900 3.00 x
2st opaque firing (powder) 43 600 2.00 75 900 1.00 x
2st opaque firing (paste) 55 500 6.00 50 900 2.00 x
Dentine firing 44 600 6.00 50 900 1.00 x
2nd dentine firing 45 600 6.00 50 890 1.00 x
3nd dentine firing 46 600 6.00 50 890 1.00 x
Glaze firing 47 600 0.00 75 900 2.00 ---
Glaze firing with VITACHROM
DELTA Fluid / Akzent Fluid 48 600 4.00 75 900 2.00 ---
Glaze firing with
Glasurmasse 740 / Akz 25 49 600 4.00 75 900 1.00 ---
Margin porcelain firing
"LUMINARY" 50 600 6.00 50 900 2.00 x
Alloys with a thermal expansion coefficient ≥14.5 x 10-6 x K-1should be fired using slow cooling from the 1st
dentine firing onwards. Slow cooling from firing temperature to starting temperature should take no less than
5 minutes. This increases the leucite content in the metal ceramic and raises the thermal expansion
coefficient of the ceramic.
The vacuum time, indicated in the "VAC" column by an "X", resuluts automatically from the given temperature
rise °C/min. The vacuum switches on at the biginning of the temperature rise and switches off again when the
end temperature is reached.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 17
VITA VMK 95 Progr.
no.
Pre-
Drying
°C min. °C/min.
Temp.
approx
°C min. VAC
Oxidation firing 11 600 0.00 110 980 5.00 ---
1st opaque firing (powder) 12 600 2.00 55 950 1.00 x
1st opaque firing (paste) 52 500 6.00 110 950 1.00 x
2st opaque firing (powder) 13 600 2.00 55 930 1.00 x
2st opaque firing (paste) 53 500 6.00 55 930 1.00 x
Dentine firing 14 600 6.00 55 930 1.00 x
2nd dentine firing 15 600 6.00 55 930 1.00 x
3nd dentine firing 16 600 6.00 55 920 1.00 x
Correction porcelain firing
CORRECTIVE -*) 600 4.00 50 900 1.00 ---
Glaze firing 17 600 0.00 110 930 1.00 ---
Glaze firing withVITACHROM
DELTA Fluid / Akzent Fluid 18 600 4.00 110 930 1.00 ---
Glaze firing with
Glasurmasse 740 / Akz 25 19 600 4.00 100 900 1.00 ---
Margin porcelain firing "MARGIN" 20 600 6.00 55 930 1.00 x
∗) = Enter program number yourself
The vacuum time, indicated in the "VAC" column by an "X", resuluts automatically from the given temperature
rise °C/min. The vacuum switches on at the biginning of the temperature rise and switches off again when the
end temperature is reached.
VITA VMK 68 Progr.
no.
Pre-
Drying
°C min. °C/min.
Temp.
approx
°C min. VAC
Oxidation firing 21 600 0.00 110 980 5.00 ---
1st opaque firing 22 600 2.00 110 950 1.00 x
2st opaque firing 23 600 2.00 55 930 1.00 x
Dentine firing 24 600 6.00 55 930 1.00 x
2nd dentine firing 25 600 6.00 55 920 1.00 x
3nd dentine firing 26 600 6.00 55 910 1.00 x
Glaze firing 27 600 0.00 110 930 1.00 ---
Glaze firing withVITACHROM
DELTA Fluid / Akzent Fluid 28 600 4.00 110 930 1.00 ---
Glaze firing with Glasurmasse 740 /
Akz 25 29 600 4.00 100 900 1.00 ---
VMK 68 N porcelains should all be fired at approx. 10°C higher.
The vacuum time, indicated in the "VAC" column by an "X", resuluts automatically from the given temperature
rise °C/min. The vacuum switches on at the biginning of the temperature rise and switches off again when the
end temperature is reached.

VITA – Vacumat 500
39/03/04 Zahfabrik H.Rauter GmbH &Co.KG D 79704 Bad Säckingen 18
VITADUR ALPHA Progr.
no.
Pre-
Drying
°C min. °C/min.
Temp.
approx
°C min. VAC
Hard core porcelain 31 600 0.00 90 1.120 2.00 x
Hard core porcelain with provile ∗)600 0.00 90 1.120 2.00 x
Dentine firing 32 600 6.00 60 960 1.00 x
1st +2st corection firing 33 600 6.00 60 950 1.00 x
Glaze firing 34 600 0.00 60 940 1.00 ---
Glaze firing withVITACHROM
DELTA Fluid / Akzent Fluid 35 600 4.00 110 940 1.00 ---
Glaze firing with
Glasurmasse 740 / Akz 25 36 600 4.00 110 920 1.00 ---
∗) = Enter program number yourself
The vacuum time, indicated in the "VAC" column by an "X", resuluts automatically from the given temperature
rise °C/min. The vacuum switches on at the biginning of the temperature rise and switches off again when the
end temperature is reached.
Additional programs Progr.
no. ∗
∗∗
∗)
Pre-
Drying
°C min. °C/min.
Temp.
approx
°C min. VAC
Metall - Corrector 91 600 2.00 75 1.040 1.00 ---
Spectra-Gold 92 550 0.00 90 820 1.00 ---
Furnace soldering 1 93 600 5.00 40 800 3.00 ---
Furnace soldering 2 94 600 1.00 50 800 4.00 ---
Soldering in the VITA VACUMAT
Method 1: Method 2:
Preheat the restoration,complete with Preheat the restoration, with flux
flux and beads solder, in a preheating but without solder, in apreheating
furnace for 15 – 20 min. at 400°C. furnace for 15 – 20 min. at 400°C.
Program no. 93 Program no. 94
End temperature is the working temperature End temperature is the working temperature
of the chosen soldering material + 50°C. of the chosen soldering material + 50°C.
Pre-drying time: 5.00 min Pre-drying time: 1.00 min
Heating-up time: 40°C/min Heating-up time: 50°C/min
Hold time: 3.00 min Hold time: 4.00 min