
Manual 02035 Load Sharing Module
Woodward 13
Phase Correction Procedure
If this procedure is followed, the correct connection of the current transformers is
assured; the correct CT will be connected to the correct input on the Load
Sharing Module with the correct polarity. Use this procedure only if the Phasing
Check indicates that the phasing is incorrect.
A CT for any phase (A, B, or C), will produce the most positive load signal
voltage when it is connected, in the proper polarity, to the terminals on the Load
Sharing Module which correspond to the same phase. Any other connections of
this CT will produce a less positive load signal voltage. This procedure makes
trial connections of the first CT to all three CT inputs on the Load Sharing
Module, polarized both ways on each CT input. The load signal voltage is
recorded for each connection, and the CT is then connected to the CT input
terminals that produced the most positive load signal voltage and with the polarity
that produced the most positive load signal voltage.
In a like manner, the second CT is tried on each of the two remaining CT input
terminals in each polarity, then connected, in the correct polarity, to the terminals
which produced the most positive load signal voltage.
The remaining CT is then connected to the remaining CT input and the load
signal checked for each polarity. This CT is then connected to the CT input,
polarized so that it produces the most positive load signal voltage.
When the procedure is completed, all three CTs are connected to the proper CT
inputs on the Load Sharing Module, with the correct polarity, and are now labeled
with their correct designations.
The procedure for correcting phase wiring requires that the generator set be shut
down and the current transformers disconnected many times. For convenience
during the phasing check, the temporary method of connecting the current
transformers shown in Figure 3-1 is recommended. By connecting a burden
resistor (a 0.5 Ω, 20 W resistor), across each current transformer, that current
transformer can be disconnected from the Load Sharing Module after removing
all load. The connections between the terminal strip and the Load Sharing
Module can be changed with the generator set running; however, remove all load
before any changes in connections are made. Do not disconnect a wire from a
current transformer with load on the system. After completion of the procedure
remove the terminal strip and the resistors.
HIGH VOLTAGE—A high voltage across open CTs (current
transformers) can cause death or serious injury. Do not disconnect a
CT from the Load Sharing Module while the engine is running. The
CTs can develop dangerously high voltages and may explode if open
circuited while the engine is running.
For this procedure, the generator set must be running isochronously, not
paralleled, and with a power factor greater than 0.8.
1. Start with the generator shut down.
2. Label each CT wire with the phase and polarity that you think it should be.
Even though this identification may prove to be wrong during this procedure,
this step is necessary so that the individual wires may be identified during
the description of the procedure.