Advanced Air 2500 Series User manual

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
1
General Description
Construction Product Regulation
To meet the requirements of the Construction
Products Regulation 1st July 2013 Advanced Air fire
dampers meet the requirements of the Product
Standard BS EN 15650 with a classification under BS
EN 13501-3 as stated in our Declaration Of
Performance that has been assessed by the notified
certification body BRE who have issued a Certificate
of Consistency of Performance No:0832-CPR-P0005.
The model 2550 is designed to prevent
the spread of fire and smoke through
ventilation ductwork in walls and floors.
From receiving an alarm the power to
the damper actuator is removed
releasing the actuator spring to release
closing the damper. The dampers also
include electrical thermal sensor and a
secondary mechanical fusible link that
prevent the damper from opening if the
temperature has reached 720C.
With the introduction of Construction
Product Regulation on the 1st July
2013 all fire dampers are required to
meet the product standard BS EN
15650. To achieve this standard the
damper has to be tested to BS EN
1366-2 dynamic fire test. The dampers
are then classified to BS EN 13501-3
that clearly states the integrity of the
damper also in the way that damper
was installed in the furnace. The
standard also now included testing of
fusible link to ISO 10294-4 that
comprises of a dynamic release and
holding tests.
The maximum single section unit
tested was 1000mm x 1000mm for both
the HEVAC and AFS frame. The
damper has been tested both ways
round in both wall and floor
installation's so there is no issue in co-
ordination caused by working out which
side the fire will be on.
The damper is supplied complete with
actuator pre-wired into a junction box
complete with test button reducing time
and work on site. The dampers can be
supplied with long spigots for installing
access doors (optional) or short to
reduce on space.
Installation Damper/Model Classification
Blockwork Wall 2550- Motorised
Fire Dampers E120 (ve i<—>o) s
Drywall 2550- Motorised
Fire Dampers E120 (ve i<—>o) s
Floor 2550-Motorised
Fire Damper E120 (ho i<—>o) s
(PATENT PENDING)

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
2

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
3
Operation Features
Blades: Double skin 1.0mm galvanised mild seal or option 430 stainless steel
Centres 125.0mm
Casing: 1.2mm galvanised mild steel or option 430 stainless steel
Corners: Welded mitre corners finish with aluminium aerosol spray
Linkage: External, enclosure within frame, out of airstream, zinc electroplated
mild steel
Bearings: Oil filed sintered bronze up to 200°C
Axles: 12.7mm diameter zinc electroplated mild steel bolted directly through
the blade
Jackshaft: 12.7mm diameter zinc electroplated mild steel
Side Jamb: Cambered grade 430 stainless steel
Top & Bottom
Jambs:
Profiled grade 430 stainless steel riveted to damper frame
Minimum Duct
Size
Rectangular : 100mm x 100mm (case size 250mm x 250mm)
Circular: 100mm diameter (case size 250mm x 250mm)
Flat Oval: 100mm x 100mm (case size 250mm x 250mm)
Maximum Single
Section Duct Size
Rectangular :1000mm x 1000mm
Circular: 1000mm diameter
Flat Oval : TBC
Hand Locking Quadrant – The HLQ will be riveted directly to the casing, to open the damper blades
the handle is turned in an anti-clockwise direction, they can be locked in the required position by
means of a wing nut on the quadrant assembly.
Actuator – The damper can be supplied with a 230V AC or 24V AC/DC factory fitted actuator. For
wiring details refer to the wiring diagram fitted on the damper casing and also to the actuator
manufacture instructions.
Switch Packs – The damper can be supplied with switch pack which will provide ‘True Blade
Indication’. The switch pack is suitable for 24V and 230V operation and has a rated current of 10A,
for wiring details options refer to Advanced Air.
Product Details

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
Fire Damper Testing Details
4
Test House & Test Fire Test Integrity Classification BS EN 13501-3
BRE - 284807
Efectis No: R0261a
HEVAC
BS EN 1366-2 120 min E120 (ve i↔o) s
Efectis No: R0169b & R0169c
HEVAC BS EN 1366-2 120 min E120 (ho i↔o) s
BRE - 284809
BRE - 284808
AFS - Partition Wall
BS EN 1366-2 120 min E120 (ve i↔o) s
TBC
AFS - Blockwork Wall BS EN 1366-2 120 min E120 (ve i↔o) s
AFS - Adjustable Frame System (PATENT PENDING)
With the tighter requirements of the CPR
and Building regulations with regard to CE
labelling and that dampers have to be
installed as tested Advanced Air through our
design and development program are
please to launch the AFS installation
system that simplifies damper installations
for customers.
This new system is unique to Advanced Air
and offers one solution for fire smoke
damper installation in walls. Using Firebatt
that is the accepted standard on sites to
finish damper installation. Our fire smoke
dampers have been successfully tested to
BS EN 1366-2 with the same method in
both Blockwork and Drywalls.
The added benefit of this system it is
adjustable allowing the drop rod supports to
be positioned to suit the site conditions

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
5
Sizing Information — 2550 Fire Smoke Damper With Rectangular Spigot & AFS Hanging System
———————————————————————————————————————————————————————————————-
Sizing Information — 2550 Fire Smoke Damper With Rectangular Spigot & HEVAC/HVCA Installation Frame

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
6
2500 Series Opening Torque Chart
(Based on 10.5m/s Velocity)
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
259 329 454 579 704 829 954 1000
Maximum Duct Height
(Number of BladesIn Brackets)
(
For multi-section (joined) units multiply by 1.2
The results above were gained by experimentation using 750mm wide
units, tests performed in a clean system at suitable pressures and are
(( ( ((( (
Pressure Drops - Fully Open
1
10
100
1000
110100
V e lo city (m /s )
Pressure drop (Pa)
610X
914X
DAMPER BLADE LEAKAGE
1
10
100
1000
10000
1 10 100 1000
AVERAGE LEAKAGE l/s/m 2
UNDERPRESSURE
P
2500 Series Nett Weights
Width
(mm) 200 300 400 600 750 1000
H 150 8 10 11 15 17 19
e 300 11 13 15 19 23 27
i 450 14 16 19 24 28 32
g 600 17 19 22 28 32 36
h 750 20 23 26 32 37 41
t 900 22 26 29 36 42 46
1000 25 28 32 39 45 49
All weights are approximate and in Kilograms
1. The weights stated are standard Rectangular Spigotted
2. Hevac/Hvca frames + further 50% max
3. Please note above weights do not include for actuators
Please note that the above figures are currently due for verification.

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
7
HEVAC Wall Installation - E120
Installation & Maintenance Instructions
Installation Procedure
1. Vertical builders work barrier to have an appropriately
sized lintel to ensure an opening clearance for the
expansion frame.
2. The opening in the wall must be cleaned, free of dust and
any other contaminants which could impair the mortar
adhesion. A clearance gap 25mm (min) to 50mm (max)
must be maintained around the expansion frame of the
fire damper (barrier contractor).
3. The damper shall be fitted centrally in the wall opening.
4. The tabs on the factory fitted galvanized steel expansion
frame shall be bent out to tie the damper into the wall with
the penetration seal.
5. The “Penetration Seal” must have a structural and fire
rated compatibility with both the barrier and the damper
and have sufficient strength to retain the fire damper
within the wall in a fire situation. (4:1 Mortar Mix).
6. The Mortar Mix will be applied up to the installation frame
face, take care not to leave any air pockets in the mix.
7. The ductwork connecting to the damper spigots must
overlap by 40mm, leaving a 10mm clearance for any duct
expansion in a fire situation.
8. All ductwork connections must be sealed with an
approved ductwork sealer, and fixed with low resistance
fixings such as: aluminium alloy rivets or nylon bolts.
9. All connecting ductwork must be independently supported
within 1meter of the connections.
10. An Access cover should be fitted on the appropriate side
of the barrier to enable inspections and maintenance
work.
Pre Installation Notes
1. Ensure that the damper is kept in a clean dry
environment and that there is no damage to the damper.
2. Remove all packaging and transit ties before installation.
Maintenance Procedure
These dampers are installed as a life-safe product and will require regular physical and visual examinations. It is essential
that that the assembly is kept in a clean, dust free condition at all times.
It is essential that an access door has been provided in the adjacent ductwork to facilitate the inspection and maintenance.
Ensure that no physical restriction of the blades has occurred during the installation process.
Remove any dirt or debris built up in the damper, apply a little WD lubricant or light oil, any excessive oils should be wiped
away.
Check the operation of any ancillary products that may be fitted.
Examine the fusible link to ensure that no corrosion has occurred and that the plates are free from distortion and are in good
condition to operate when required.
Close the blade pack by manual operation and examine the blades to ensure;
They are in the fully closed position and have located in the ramps.
They are all position in the frame correctly i.e. square to the frame.
They are all in a clean condition.
The period between maintenance checks can best be ascertained by system conditions or as directed by local regulations
for ventilation plant and ancillaries, but should not exceed a maximum interval in excess of twelve months.
The report should be completed following the Maintenance Procedure included within this document.

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
HEVAC Floor Installation - E120
Pre Installation Notes
1. Ensure that the damper is kept in a
clean dry environment and that there
is no damage to the damper.
2. Remove all packaging and transit ties
before installation.
Installation Procedure
1. The opening in the floor slab must be cleaned, free of dust and any other contaminants which could impair the mortar
adhesion. A clearance gap 25mm (min) to 50mm (max) must be maintained around the expansion frame of the fire damper
(barrier contractor).
2. The tabs on the factory fitted galvanized steel expansion frame will be bent out to tie the damper into the floor with the
penetration seal.
3. The damper should be fitted flush to the top edge of the opening.
4. The underside of the damper should be shuttered up with 25mm rigid rock wool firebatt Min Density 140kg/m3 cut to
interference fit and supported from below, this must be left in situ.
5. The “Penetration Seal” must have a structural and fire rated compatibility with both the barrier and the damper and have
sufficient strength to retain the fire damper within the floor slab in a fire situation. (4:1 Mortar Mix).
6. Pour the Mortar Mix into the gap between damper and floor slab to half way and ensure all the small gaps are filled, leaving
no air pockets. Then pour the top layer up to the installation frame face smoothing off if necessary.
7. The ductwork connecting to the dampers long spigot must overlap by 40mm. The ductwork connecting to the short spigot
must overlap the spigot by 40mm, leaving 10mm clearance for any duct expansion in a fire situation.
8. All ductwork connections must be sealed with an approved ductwork sealer, and fixed with low resistance fixings such as:
aluminium alloy rivets or nylon bolts.
9. All connecting ductwork must be independently supported within 1meter of the connections.
Maintenance Procedure
These dampers are installed as a life-safe product and will require regular physical and visual examinations. It is essential
that that the assembly is kept in a clean, dust free condition at all times.
It is essential that an access door has been provided in the adjacent ductwork to facilitate the inspection and maintenance.
Ensure that no physical restriction of the blades has occurred during the installation process.
Remove any dirt or debris built up in the damper, apply a little WD lubricant or light oil, any excessive oils should be wiped
away.
Check the operation of any ancillary products that may be fitted.
Examine the fusible link to ensure that no corrosion has occurred and that the plates are free from distortion and are in good
condition to operate when required.
Close the blade pack by manual operation and examine the blades to ensure;
They are in the fully closed position and have located in the ramps.
They are all position in the frame correctly i.e. square to the frame.
They are all in a clean condition.
The period between maintenance checks can best be ascertained by system conditions or as directed by local regulations for
ventilation plant and ancillaries, but should not exceed a maximum interval in excess of twelve months.
The report should be completed following the Maintenance Procedure included within this document.
Installation & Maintenance Instructions
8

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
AFS Blockwork Installation - E120
(PATENT PENDING)
Maintenance Procedure
These dampers are installed as a life-safe product and will require regular physical and visual examinations. It is essential
that that the assembly is kept in a clean, dust free condition at all times.
It is essential that an access door has been provided in the adjacent ductwork to facilitate the inspection and maintenance.
Ensure that no physical restriction of the blades has occurred during the installation process.
Remove any dirt or debris built up in the damper, apply a little WD lubricant or light oil, any excessive oils should be wiped
away.
Check the operation of any ancillary products that may be fitted.
Examine the fusible link to ensure that no corrosion has occurred and that the plates are free from distortion and are in good
condition to operate when required.
Close the blade pack by manual operation and examine the blades to ensure;
They are in the fully closed position and have located in the ramps.
They are all position in the frame correctly i.e. square to the frame.
They are all in a clean condition.
The period between maintenance checks can best be ascertained by system conditions or as directed by local regulations for
ventilation plant and ancillaries, but should not exceed a maximum interval in excess of twelve months.
The report should be completed following the Maintenance Procedure included within this document.
Pre Installation Notes
1. Ensure that the damper is kept in a clean
dry environment and that there is no damage to the
damper.
2. Remove all packaging and transit ties before
installation.
Installation Procedure
1. Vertical builders work barrier to have an appropriately
sized lintel and opening clearance for the fire damper
and Firebatt.
2. The opening in the wall must be cleaned, free of dust
and any other contaminants which could impair the
acrylic sealant. A clearance gap of 25mm (min) -
100mm (max) gap for the Firebatt must be maintained
around the fire damper (barrier contractor).
3. The damper shall be mounted so that the supported
side of the damper is flush with the wall opening. It
shall be hung by M10 drop rods using the slotted rail
and bolted tight to steel anchors in the slab or soffit
above.
4. The gap between the damper and the wall opening will
need filing in with 3 layers of 140kg/m3 50mm Firebatt
cut to interference fit and pushed in place.
5. All joints and gaps shall be sealed using intumescent
Acrylic Sealant.
6. The ductwork connecting to the damper spigots must
overlap by 40mm, leaving a 10mm clearance for any
duct expansion in a fire situation.
7. All ductwork connections must be sealed with an
approved ductwork sealer, and fixed with low
resistance fixings such as: aluminium alloy rivets or
nylon bolts.
8. All connecting ductwork must be independently
supported within 1meter of the connections.
9. An Access cover should be fitted on the appropriate
side of the barrier to enable inspections and
maintenance work.
Installation & Maintenance Instructions
9

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
AFS Drywall 2 Hour - 120
(PATENT PENDING)
Maintenance Procedure
These dampers are installed as a life-safe product and will require regular physical and visual examinations. It is essential
that that the assembly is kept in a clean, dust free condition at all times.
It is essential that an access door has been provided in the adjacent ductwork to facilitate the inspection and maintenance.
Ensure that no physical restriction of the blades has occurred during the installation process.
Remove any dirt or debris built up in the damper, apply a little WD lubricant or light oil, any excessive oils should be wiped
away.
Check the operation of any ancillary products that may be fitted.
Examine the fusible link to ensure that no corrosion has occurred and that the plates are free from distortion and are in good
condition to operate when required.
Close the blade pack by manual operation and examine the blades to ensure;
They are in the fully closed position and have located in the ramps.
They are all position in the frame correctly i.e. square to the frame.
They are all in a clean condition.
The period between maintenance checks can best be ascertained by system conditions or as directed by local regulations for
ventilation plant and ancillaries, but should not exceed a maximum interval in excess of twelve months.
The report should be completed following the Maintenance Procedure included within this document.
Pre Installation Notes
1. Ensure that the damper is kept in a clean
dry environment and that there is no damage to the
damper.
2. Remove all packaging and transit ties before
installation.
Installation Procedure
1. The Drywall which will consist of two layers of 15mm
plasterboard each side of steel studwork with a 50mm
Rockwool insulation. The opening will be a letterbox
construction with overlapping layers of plasterboard
with an opening clearance of 25mm (min) - 100mm
(max) all around the fire damper casing (barrier
contractor).
2. Two M10 drop rods shall be fitted each side of the wall
fixed by steel anchors into the slab or soffit above.
3. The access side of the damper (denoted by extended
spigot with actuator) must always be installed flush with
the surface of the dry wall.
4. The gap between the damper and the wall opening will
need filling in with at least 2 layers of 140kg/m3 50mm
Firebatt cut to interference fit and pushed in place.
5. The ductwork connecting to the damper spigots must
overlap by 40mm, leaving a 10mm clearance for any
duct expansion in a fire situation.
6. All ductwork connections must be sealed with an
approved ductwork sealer, and fixed with low
resistance fixings such as: aluminium alloy rivets or
nylon bolts.
7. All connecting ductwork must be independently
supported within 1meter of the connections.
Installation & Maintenance Instructions
10

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
Installation Safety Information
The installation of Fire Dampers must be done by competent trained persons who are familiar with
the type of product. They should follow the following essential safety practices:
Wear appropriate PPE gloves, footwear, safety hat etc. comply with the safety policies of the
particular site.
Ensure that access to the installation position has been made safe and is suitable for the
handling of the damper.
Use correct manual handling techniques when moving the damper, use team lifting techniques
when installing large dampers.
If lifting equipment is used; inspect the condition of the equipment before using it.
11

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
12

Due to continuous product development Advanced Air (U.K.) Ltd
reserves the right to change any information without prior notice.
Burrell Way,
Thetford, Norfolk,
IP24 3QU, England
Tel: +44 (0) 1842 753624
Fax: +44 (0) 1842 762032
Email: sales@advancedair.co.uk
2500 Series
Fire Smoke Dampers
Date Issue Spec. No. Page No.
04/03/14 Rev 2 CE –FSD Sub
PATENT APPLIED FOR
Operation / Task Result
Damper reference
Date of inspection
Check actuator wiring for damage (where applicable)
Check end-switch wiring for damage (where applicable)
Check damper for cleanliness and clean where necessary
Check the condition of the blades and seals, rectify and report
where necessary
Confirm the safety closure operation of the fire damper according
to the manufacturer’s instructions
Confirm operation of the damper to OPEN and CLOSE by use of
physical observation of the damper, rectify and report where neces-
sary
Confirm operation of OPEN and CLOSED end-switches, rectify and
report (where necessary)
Confirm that the damper fulfills its function as part of the control
system (where necessary)
Confirm that the damper is left in its normal working position
Maintenance Report
13
This manual suits for next models
1
Table of contents
Other Advanced Air Fire And Smoke Damper manuals
Popular Fire And Smoke Damper manuals by other brands

ETS NORD
ETS NORD NORDfire manual

NuTone
NuTone RDFUWT installation guide

amalva
amalva Komfovent UVS30M Installation instruction

Lindab
Lindab SDR2-M technical information

Greenheck
Greenheck SMD Series Flange Mounted Installation

Val-Matic
Val-Matic FrostSafe Two-Way Damper Operation, maintenance and installation manual