Advanced Air 2530 User manual

2530_IOM_1.1_Mar21_1
1
AIR CONTROL
INSTALLATION, OPERATION
AND MAINTENANCE MANUAL
MODEL 2530
FIRE & SMOKE DAMPER

2530_IOM_1.1_Mar21_2
2
Page
Introduction and Health & Safety 3
Fire & Smoke damper – Model 2530
Two hour flexible wall – AFS with drop rods one side 4
Two hour flexible wall – AFS with drop rods two sides 5
Two hour flexible wall – multi-section AFS with drop rods two sides 6
Two hour rigid wall – AFS with drop rods one side 7
Two hour rigid wall – AFS with drop rods two sides 8
Two hour rigid wall – HEVAC 9
Two hour – remote from wall 10
Two hour rigid floor – AFS 11
Two hour rigid floor – HEVAC 12
Operation and Maintenance 13
Wiring information
2530 14
2530 multi-section 15
DW145 Fire Damper Certificate 16
Index

2530_IOM_1.1_Mar21_3
3
Introduction
Advanced Air (UK) Ltd have been manufacturing a comprehensive range of fire dampers and fire smoke
dampers since 1975. We have always taken pride in our products and tested to the highest standards,
originally to BS476 and now more stringent testing to CE labelling under the Construction Product Regulation
which was introduced 1st July 2013.
All our fire, fire smoke and smoke control dampers have been tested to BS EN 1366-2 and BS EN 1366-10.
This is to cover a variety of installations used on sites today. Under CE labelling all dampers must follow the
Product Standards BS EN 15650 and BS EN 12101-8 which ensures the product is consistent and supplied to
the same specification and standard as tested. Any deviation or changes from the installations in this manual
would require the dampers to be subject to a new test or approval sought from Local Building Control.
In line with product standards we are pleased to oer this installation manual covering installation, operation
and maintenance instructions together with Health and Safety information. We have also included within this
manual an example of the Fire Damper Certificate DW145 Inspection and Handover Check Sheet which is to
be completed by the installer. A separate certificate is required per damper.
The installation contained in this manual cover most installation on site. However, there are still installation
which Advanced Air (UK) Ltd have not yet tested. We are continually reviewing requirements and continuously
developing the products. As additional installation tests are carried out and classified, installations will be
added to this manual, and the Declaration of Performance (DoP) updated accordingly.
Health and Safety
Any instruction contained within this manual must be undertaken by competent trained personnel. When
completing the installation standard PPE should be used, steel toe cap boots, hard hat, gloves, protective
eyewear along with any other specific site or material instructions.
The size and weight of dampers vary, and it may require two or more persons to safely handle and move
them. Do not lift the dampers by the blades or the actuator.
For the installation of dampers at high level, the correct lifting equipment shall be used in accordance with
the Work at Height Regulations 2005 and specific site rules.
All waste materials should be collected and disposed of defined by the suppliers.

2530_IOM_1.1_Mar21_4
4
FIRE & SMOKE 2530 ADJUSTABLE FRAME SYSTEM FOR TWO HOUR FLEXIBLE SUPPORTING CONSTRUCTION SUPPORT ONE SIDE
AFS bracket,
bracket slot,
and Z-piece
AFS rail
M10 drop rods
15mm thick gypsum boards
Two hour rated flexible supporting
construction to BS EN 1363-1:2020
Fire batt
Steel stud depth – 71 to 100mm
Thermal probe
Access door
Nom. duct size Width Height
Opening
min.
Opening
max.
Opening
min.
Opening
max.
200mm x 200mm
and above
Nom. duct
+194mm
Nom. duct.
+350mm
Nom. duct
+100mm
Nom. duct
+350mm
Below
200mm x 200mm 394mm 550mm 300mm 550mm
Circular duct
over 175mm
Nom. duct
+219mm
Nom. dia.
+550mm
Nom. dia.
+125mm
Nom. dia.
+375mm
Circular duct
under 175mm 394mm 550mm 300mm 550mm
Preparation
1 Ensure that the damper is kept
in a clean dry environment and
that there is no damage to the
damper.
2 Remove all the packaging
before installation.
3 Work out the opening size to be
cut using the adjacent table.
Installation sequence
4 The drywall will consist of two layers of 15mm plasterboard each side of steel studwork with an optional
50mm mineral wool insulation. The opening will be a letterbox construction with overlapping layers
of plasterboard with an opening clearance around the damper casing in line with the table above.
5 Two M10 drop rods shall be fitted on the side of the drywall to which the access side of the damper
will be positioned. These should be securely installed in line with the manufacturer’s fixing instructions
in a position to match the AFS rail.
6 The drop rods should have a nut screwed on for clamping the rail from above.
7 Slide the AFS rails on each side of the damper into the brackets and insert the “Z” piece into the
bracket slot pushing it up against the underside of the rail. Insert the 8mm bolt from above into the slot
through the “Z” piece fitting the nut until tight to secure the rail.
8 The damper should be mounted centrally in the opening with the access side flush with the wall, as
detailed in the drawing. The drop rods are to slide through the slots in the rail and a nut screwed on
to take the support of the damper rail. The damper must then be levelled and when in the correct
position the nut above the rail should be tightened against the rail.
9 The galvanised mild steel ductwork connecting to the damper spigots must overlap by up to 40mm,
leaving a minimum 10mm clearance for any duct expansion in a fire situation.
10 The galvanised mild steel ductwork connections must be sealed with an approved galvanised mild
steel ductwork sealer and fixed with low resistance fixings such as aluminium rivets that will melt at
high temperature allowing the duct to break away without aecting the integrity of the installation.
11 The connecting galvanised mild steel ductwork must be independently supported within one metre of
the connections and have been installed in accordance with DW144.
12 The gap between the damper and the wall opening will need filling with two layers of 50mm thick
140kg/m fire batt cut to an interference fit and pushed in to place. All cut edges must be sealed with
a fire batt sealant to BS EN 13501-2. A fire rated intumescent mastic to BS EN 13501-2 shall be applied
to each joint.
13 An access door should be fitted on the access side of the damper for inspection and maintenance of
the damper.
14 When the damper installation has been completed checks should be made to ensure the AFS rails are
secure and there is no movement, operation of the damper should be checked.
15 Complete DW145 Fire Damper Certificate.
PRODUCT 2530 W/AFS APPLICATION FLEXIBLE SUPPORTING CONSTRUCTION SUPPORT ONE SIDE
CLASSIFICATION REPORT NO. BRE 287810A CLASSIFICATION E120 VE I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.

2530_IOM_1.1_Mar21_5
5
PRODUCT 2530 W/AFS APPLICATION FLEXIBLE SUPPORTING CONSTRUCTION SUPPORT ONE SIDE
CLASSIFICATION REPORT NO. TBA CLASSIFICATION E120 VE I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.
FIRE & SMOKE 2530 ADJUSTABLE FRAME SYSTEM FOR TWO HOUR FLEXIBLE SUPPORTING CONSTRUCTION SUPPORT TWO SIDES
15mm thick gypsum boards
Two hour rated flexible supporting
construction to BS EN 1363-1:2020
Steel stud depth – 71 to 100mm
AFS bracket,
bracket slot,
and Z-piece
Fire batt
Thermal probe
AFS rail
M10 drop rods
Nom. duct size Width Height
Opening
min.
Opening
max.
Opening
min.
Opening
max.
200mm x 200mm
and above
Nom. duct
+194mm
Nom. duct.
+350mm
Nom. duct
+100mm
Nom. duct
+350mm
Below
200mm x 200mm 394mm 550mm 300mm 550mm
Circular duct
over 175mm
Nom. duct
+219mm
Nom. dia.
+550mm
Nom. dia.
+125mm
Nom. dia.
+375mm
Circular duct
under 175mm 394mm 550mm 300mm 550mm
Preparation
1 Ensure that the damper is kept
in a clean dry environment and
that there is no damage to the
damper.
2 Remove all the packaging
before installation.
3 Work out the opening size to be
cut using the adjacent table.
Installation sequence
4 The drywall will consist of two layers of 15mm plasterboard each side of steel studwork with a 50mm
mineral wool insulation. The opening will be a letterbox construction with overlapping layers of
plasterboard with an opening clearance around the damper casing in line with the table above.
5 Two M10 drop rods shall be fitted on both sides of the drywall. These should be securely installed in
line with the manufacturer’s fixing instructions in a position to match the AFS rail.
6 The drop rods should have a nut screwed on for clamping the rail from above.
7 Slide the AFS rails on each side of the damper into the brackets and insert the “Z” piece into the
bracket slot pushing it up against the underside of the rail. Insert the 8mm bolt from above into the slot
through the “Z” piece fitting the nut until tight to secure the rail.
8 The damper should be centrally positioned in the opening with the access side flush with the wall,
as detailed in the drawing. The drop rods are to slide through the slots in the rail and a nut screwed
on to take the support of the damper rail. The damper must then be levelled and when in the correct
position the nut above the rail should be tightened against the rail.
9 The galvanised mild steel ductwork connecting to the damper spigots must overlap by up to 40mm,
leaving a minimum 10mm clearance for any duct expansion in a fire situation.
10 The galvanised mild steel ductwork connections must be sealed with an approved galvanised mild
steel ductwork sealer and fixed with low resistance fixings such as aluminium rivets that will melt at
high temperature allowing the duct to break away without aecting the integrity of the installation.
11 The connecting galvanised mild steel ductwork must be independently supported within one metre of
the connections and have been installed in accordance with DW144.
12 The gap between the damper and the wall opening will need filling with two layers of 50mm thick
140kg/m fire batt cut to an interference fit and pushed in to place. A fire rated mastic will be applied
to each joint.
13 An access door should be fitted on the access side of the damper to enable the resetting of the
damper blades.
14 When the damper installation has been completed checks should be made to ensure the AFS rails are
secure and there is no movement, operation of the damper should be checked.
15 Complete DW145 Fire Damper Certificate.

2530_IOM_1.1_Mar21_6
6
PRODUCT 2530 MULTISECTION W/AFS APPLICATION FLEXIBLE SUPPORTING CONSTRUCTION
CLASSIFICATION REPORT NO. BRE 287810A CLASSIFICATION E120 VE I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.
FIRE & SMOKE 2530 MULTISECTION ADJUSTABLE FRAME SYSTEM FOR FLEXIBLE SUPPORTING CONSTRUCTION SUPPORT TWO SIDES
2530 Series multisection
fire & smoke damper
AFS bracket,
bracket slot,
and Z-piece
15mm thick gypsum boards
Fire batt
Two hour rated flexible supporting
construction to BS EN 1363-1:2020
Steel stud depth – 71 to 100mm
Thermal probe(s)
Access door
Nom. duct size Width Height
Opening
min.
Opening
max.
Opening
min.
Opening
max.
1,001 x 1,001mm
and above
Nom. duct
+194mm
Nom. duct.
+350mm
Nom. duct
+100mm
Nom. duct
+350mm
Circular duct
over 950mm
Nom. dia.
+219mm
Nom. dia.
+550mm
Nom. dia.
+125mm
Nom. dia.
+375mm
Preparation
1 Ensure that the damper is kept
in a clean dry environment and
that there is no damage to the
damper.
2 Remove all the packaging
before installation.
3 Work out the opening size to be
cut using the adjacent table.
Installation sequence
4 The drywall will consist of two layers of 15mm plasterboard each side of steel studwork with an optional
50mm mineral wool insulation. The opening will be a letterbox construction with overlapping layers of
plasterboard with an opening clearance around the damper casing in line with the table above.
5 Two M10 drop rods shall be fitted on either side of the drywall. These should be securely installed in
line with the manufacturer’s fixing instructions in a position to match the AFS rail.
6 The drop rods should have a nut screwed on for clamping the rail from above.
7 Slide the AFS rails on each side of the damper into the brackets and insert the “Z” piece into the
bracket slot pushing it up against the underside of the rail. Insert the 8mm bolt from above into the slot
through the “Z” piece fitting the nut until tight to secure the rail.
8 Additional drop rods should then be passed through the top and bottom rails and fully tightened.
9 The damper should be mounted centrally in the opening with the access side flush with the wall, as
detailed in the drawing. The drop rods are to slide through the slots in the rail and a nut screwed on
to take the support of the damper rail. The damper must then be levelled and when in the correct
position the nut above the rail should be tightened against the rail.
10 The galvanised mild steel ductwork connecting to the damper spigots must overlap by up to 40mm,
leaving a minimum 10mm clearance for any duct expansion in a fire situation.
11 The galvanised mild steel ductwork connections must be sealed with an approved galvanised mild
steel ductwork sealer and fixed with low resistance fixings such as aluminium rivets that will melt at
high temperature allowing the duct to break away without aecting the integrity of the installation.
12 The connecting galvanised mild steel ductwork must be independently supported within one metre of
the connections and have been installed in accordance with DW144.
13 The gap between the damper and the wall opening will need filling with two layers of 50mm thick
140kg/m fire batt cut to an interference fit and pushed in to place. All cut edges must be sealed with
a fire batt sealant to BS EN 13501-2. A fire rated intumescent mastic to BS EN 13501-2 shall be applied
to each joint.
14 An access door should be fitted on the access side of the damper for inspection and maintenance.
15 When the damper installation has been completed checks should be made to ensure the AFS rails are
secure and there is no movement, operation of the damper should be checked.
16 Complete DW145 Fire Damper Certificate.
While we have tested a damper 2,000 x 2,000mm, larger sizes can be supplied in sections but the installation will need to be checked by a
competent structural engineer as stated in the Extended Fields of Applications BS EN 15882-2:2015. With all larger sizes there should be a risk
assessment carried out and a full method statement documented to ensure the correct lifting gear and safety precautions are in place prior to
the installation being carried out.
NOTE
The multi-section damper will be supplied enclosed in one large casing up to a
maximum spigot size of 2,000mm.

2530_IOM_1.1_Mar21_7
7
PRODUCT 2530 W/AFS APPLICATION RIGID SUPPORTING CONSTRUCTION, SUPPORT ONE SIDE
CLASSIFICATION REPORT NO. TBA CLASSIFICATION E120 VE I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.
FIRE & SMOKE 2530 ADJUSTABLE FRAME SYSTEM FOR TWO HOUR RIGID SUPPORTING CONSTRUCTION SUPPORT ONE SIDE
135mm (or thicker) blockwork,
masonry or homogeneous
concrete wall to BS EN 1363-1:2020
AFS bracket,
bracket slot,
and Z-piece
Fire batt
Thermal probe
AFS rail
M10 drop rods
Nom. duct size Width Height
Opening
min.
Opening
max.
Opening
min.
Opening
max.
200mm x 200mm
and above
Nom. duct
+194mm
Nom. duct.
+350mm
Nom. duct
+100mm
Nom. duct
+350mm
Below
200mm x 200mm 394mm 550mm 300mm 550mm
Circular duct
over 175mm
Nom. duct
+219mm
Nom. dia.
+550mm
Nom. dia.
+125mm
Nom. dia.
+375mm
Circular duct
under 175mm 394mm 550mm 300mm 550mm
Preparation
1 Ensure that the damper is kept
in a clean dry environment and
that there is no damage to the
damper.
2 Remove all the packaging
before installation.
3 Work out the opening size to be
cut using the adjacent table.
Installation sequence
4 Two M10 drop rods per fire damper shall be fitted on one side of the drywall. These should be securely
installed in line with the manufacturer’s fixing instructions in a position to match the AFS rail.
5 The drop rods should have a nut screwed on for clamping the rail from above.
6 Slide the AFS rails on each side of the damper into the brackets and insert the “Z” piece into the
bracket slot pushing it up against the underside of the rail. Insert the 8mm bolt from above into the slot
through the “Z” piece fitting the nut until tight to secure the rail.
7 The damper should be centrally positioned in the opening with the access side flush with the wall,
as detailed in the drawing. The drop rods are to slide through the slots in the rail and a nut screwed
on to take the support of the damper rail. The damper must then be levelled and when in the correct
position the nut above the rail should be tightened against the rail.
8 The galvanised mild steel ductwork connecting to the damper spigots must overlap by up to 40mm,
leaving a minimum 10mm clearance for any duct expansion in a fire situation.
9 The galvanised mild steel ductwork connections must be sealed with an approved galvanised mild
steel ductwork sealer and fixed with low resistance fixings such as aluminium rivets that will melt at
high temperature allowing the duct to break away without aecting the integrity of the installation.
10 The connecting galvanised mild steel ductwork must be independently supported within one metre of
the connections and have been installed in accordance with DW144.
11 The gap between the damper and the wall opening will need filling with two layers of 50mm thick
140kg/m fire batt cut to an interference fit and pushed in to place. All cut edges must be sealed with
a fire batt sealant to BS EN 13501-2. A fire rated intumescent mastic to BS EN 13501-2 shall be applied
to each joint.
12 An access door should be fitted on the access side of the damper to enable the inspection and
maintenance of the damper.
13 When the damper installation has been completed checks should be made to ensure the AFS rails are
secure and there is no movement, operation of the damper should be checked.
14 Complete DW145 Fire Damper Certificate.

2530_IOM_1.1_Mar21_8
8
PRODUCT 2530 W/AFS APPLICATION RIGID SUPPORTING CONSTRUCTION, SUPPORT TWO SIDES
CLASSIFICATION REPORT NO. BRE 287810D CLASSIFICATION E120 VE I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.
FIRE & SMOKE 2530 ADJUSTABLE FRAME SYSTEM FOR TWO HOUR RIGID SUPPORTING CONSTRUCTION SUPPORT TWO SIDES
135mm (or thicker) blockwork,
masonry or homogeneous
concrete wall to BS EN 1363-1:2020
AFS bracket,
bracket slot,
and Z-piece
Fire batt
Thermal probe
AFS rail
M10 drop rods
Nom. duct size Width Height
Opening
min.
Opening
max.
Opening
min.
Opening
max.
200mm x 200mm
and above
Nom. duct
+194mm
Nom. duct.
+350mm
Nom. duct
+100mm
Nom. duct
+350mm
Below
200mm x 200mm 394mm 550mm 300mm 550mm
Circular duct
over 175mm
Nom. duct
+219mm
Nom. dia.
+550mm
Nom. dia.
+125mm
Nom. dia.
+375mm
Circular duct
under 175mm 394mm 550mm 300mm 550mm
Preparation
1 Ensure that the damper is kept
in a clean dry environment and
that there is no damage to the
damper.
2 Remove all the packaging
before installation.
3 Work out the opening size to be
cut using the adjacent table.
Installation sequence
4 Two M10 drop rods shall be fitted on either side of the drywall. These should be securely installed in
line with the manufacturer’s fixing instructions in a position to match the AFS rail.
5 The drop rods should have a nut screwed on for clamping the rail from above.
6 Slide the AFS rails on each side of the damper into the brackets and insert the “Z” piece into the
bracket slot pushing it up against the underside of the rail. Insert the 8mm bolt from above into the slot
through the “Z” piece fitting the nut until tight to secure the rail.
7 The damper should be centrally positioned in the opening with the access side flush with the wall,
as detailed in the drawing. The drop rods are to slide through the slots in the rail and a nut screwed
on to take the support of the damper rail. The damper must then be levelled and when in the correct
position the nut above the rail should be tightened against the rail.
8 The galvanised mild steel ductwork connecting to the damper spigots must overlap by up to 40mm,
leaving a minimum 10mm clearance for any duct expansion in a fire situation.
9 The galvanised mild steel ductwork connections must be sealed with an approved galvanised mild
steel ductwork sealer and fixed with low resistance fixings such as aluminium rivets that will melt at
high temperature allowing the duct to break away without aecting the integrity of the installation.
10 The connecting galvanised mild steel ductwork must be independently supported within one metre of
the connections and have been installed in accordance with DW144.
11 The gap between the damper and the wall opening will need filling with two layers of 50mm thick
140kg/m fire batt cut to an interference fit and pushed in to place. All cut edges must be sealed with
a fire batt sealant to BS EN 13501-2. A fire rated intumescent mastic to BS EN 13501-2 shall be applied
to each joint.
12 An access door should be fitted on the access side of the damper to enable the inspection and
maintenance of the damper.
13 When the damper installation has been completed checks should be made to ensure the AFS rails are
secure and there is no movement, operation of the damper should be checked.
14 Complete DW145 Fire Damper Certificate.

2530_IOM_1.1_Mar21_9
9
PRODUCT 2530 W/HEVAC FRAME APPLICATION RIGID SUPPORTING CONSTRUCTION
CLASSIFICATION REPORT NO. BRE 287810B CLASSIFICATION E120 VE I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.
FIRE & SMOKE 2530 HEVAC FOR RIGID SUPPORTING CONSTRUCTION WALL
Turnback ties
4:1 mortar mix
HEVAC frame
Lintel
150mm thick two hour rated
rigid construction to
BS EN 1363-1:2020
Thermal probe
Access door
Ductwork
support
Installation sequence
4 In the opening, mark the positions for the turnback tabs on the HEVAC frame.
5 Create 20mm deep pockets for the HEVAC tabs to be located in.
6 Oer up the damper into the opening and support from the bottom of the damper so that it sits
centrally within the opening and has an even space on all four sides.
7 Bend the HEVAC tabs so that they lock into the pockets.
8 A 4:1 mortar mix can then be gradually applied between the wall and the damper, ensuring the mortar
is only filled up to the HEVAC frame and not the damper spigots. This ensures the damper can move
within the HEVAC frame.
9 The galvanised mild steel ductwork connecting to the damper spigots must overlap by up to 40mm,
leaving minimum 10mm clearance for any duct expansion in a fire situation.
10 The galvanised mild steel ductwork connections must be sealed with an approved galvanised mild
steel ductwork sealer and fixed with low resistance fixings such as aluminium rivets that will melt at
high temperature allowing the duct to break away without aecting the integrity of the installation.
11 The connecting galvanised mild steel ductwork must be independently supported within one metre of
the connections and have been installed in accordance with DW144.
12 An access door should be fitted on the access side of the damper for inspection and maintenance.
13 When the damper installation has been completed, checks should be made to ensure the damper is
secure and there is no movement, operation of the damper should be checked.
14 Complete DW145 Fire Damper Certificate.
Preparing the opening
1 Ensure that the damper is kept
in a clean dry environment and
that there is no damage to the
damper.
2 Remove all the packaging and
transit ties before installation.
3 Work out the opening size to be
cut using the table adjacent.
Nom. duct Opening width /
height min.
Opening width /
height max.
200 x 200mm
and above Nom. duct +170mm Nom. duct +200mm
199 x 199mm
and below 370 x 370mm 400 x 400mm
Circular duct Opening width /
height min.
Opening width /
height max.
175mm and over Nom. duct +195mm Nom. duct +225mm
174mm and under 395mm 425mm

2530_IOM_1.1_Mar21_10
10
PRODUCT 2530 W/AFS APPLICATION DUCT MOUNTED, TWO HOUR REMOTE FROM WALL
CLASSIFICATION REPORT NO. TBA CLASSIFICATION E120 VE I O E30 VE I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.
FIRE & SMOKE 2530 TWO HOUR REMOTE FROM WALL
Fire-rated ductwork
tested to BS EN 1366-8
Ductwork insulation 3.5mm drywall screws
Mineral wool insulation 85-115 kg/m
15mm thick gypsum boards
2x 12.5mm thick gypsum boards, forming pattress
Access door Thermal probe
50x50x5mm
stiening angle
Group A 122mm (or thicker) two hour rated flexible
supporting construction to BS EN 1363-1:2020
Steel stud
This is an example illustration –
installations through the wall may vary and
should be carried out in accordance with
the ductwork manufacturer’s instructions.
*
Preparation
1 Work out the opening size to be cut 120mm larger than the
nominal duct width/height, at a tolerance of ±5mm (for example
a 1,000 x 1,000mm duct requires a 1,120 x 1,120mm opening).
Installation sequence
2 Drill and rivet at 150mm centres, the 50x50x5mm stiening
flange to the galvanised mild steel ductwork.
3 Pass the duct through the opening, so that the flange is
centralised in the wall.*
4 Drop rod anchor points, and M10 drop rods to support the
galvanised mild steel ductwork, should be positioned within
350mm of the wall, on both sides.*
5 Install Unistrut to the drop rods with M10 fixings, and adjust to
that they fully support the weight of the galvanised mild steel
ductwork, using a spreader plate. The position of the duct
should be adjusted so that the stiening flange is centralised in
every axis.
6 Fill the wall opening around the duct with 85-115kg/m2mineral
wool insulation, on both sides of the wall.*
7 Fit two layers of 200mm wide, 12.5mm thick plasterboard
around the damper, overlapping the joints, to form a pattress
around the galvanised mild steel ductwork on both sides of the
wall. The pattress must be axed with drywall screws which bite
into the steel stud channel at 150mm centres, and sealed with
a bead of intumescent acrylic sealant to BS EN 13501-2, which
shall be applied to back of each pattress section before it is
fitted.*
8 The damper is mounted to the duct using self tapping fixings, at
150mm centres. When the duct is slid over the damper spigot,
an overlap of up to 40mm is permitted, allowing for 10mm for
duct expansion.
9 Support the damper case using a single piece of Unistrut, hung
on M10 drop rods.
10 Galvanised mild steel ductwork and sealing of the duct should
be in accordance with DW144.
11 The damper operation should be checked to ensure that it fully
opens and closes.
12 When the damper installation has been completed, checks
should be made to ensure the installation is secure, and there is
no movement.
13 Complete DW145 Fire Damper Certificate.

2530_IOM_1.1_Mar21_11
11
PRODUCT 2530 W/AFS APPLICATION CONCRETE FLOOR
CLASSIFICATION REPORT NO. TBA CLASSIFICATION E120 HO I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.
FIRE & SMOKE 2530 ADJUSTABLE FRAME SYSTEM FOR RIGID SUPPORTING CONSTRUCTION FLOOR
Three layers of
50mm fire batt
Thermal probe
Two hour rated
rigid supporting
construction to
BS EN 1363-1:2020
Suitable bolts
Supporting
Z-angle
Access door
2530 Series
fire damper
AFS bracket AFS rail
(40x40x4mm)
by others
Nom. duct size Width Height
Opening
min.
Opening
max.
Opening
min.
Opening
max.
200 x 200mm
and above
Nom. duct
+100mm
Nom. duct.
+350mm
Nom. duct
+130mm
Nom. duct
+350mm
Below
200 x 200mm 300mm 550mm 330mm 580mm
Circular duct
over 175mm
Nom. duct
+125mm
Nom. dia.
+375mm
Nom. dia.
+155mm
Nom. dia.
+375mm
Circular duct
under 175mm 300mm 550mm 330mm 580mm
Preparation
1 Ensure that the damper is kept
in a clean dry environment and
that there is no damage to the
damper.
2 Remove all the packaging
before installation.
3 Work out the opening size to be
cut using the adjacent table.
Installation sequence
4 Install 40mm x 40mm x 4mm angle through the AFS brackets ensuring they are of enough length to
extend past the opening on each side by 100mm.
5 Position the damper evenly in the centre of the opening.
6 Secure the angles to the floor. Mark the hole positions on the angle at least 50mm away from the
opening and install M8 steel anchors and bolt the angle to the floor.
7 ‘Z’ angles are required to support the first layer of fire batt. These measure 50mm x 150mm x 50mm
by 100mm wide and 1.6mm thick – they are to be positioned on all fire batt joints on the bottom layer
and evenly spaced on a 500mm minimum pitch.
8 The gap between the damper and the wall opening will need filling with three layers of 50mm think
150kg/m3fire batt cut to an interference fit and pushed into place. All cut edges must be sealed with
a fire batt sealant to BS EN 13501-2. A fire rated intumescent mastic to BS EN 13501-2 shall be applied
to each joint.
9 The galvanised mild steel ductwork connecting to the damper spigot must overlap by 40mm, leaving
a 10mm clearance for any duct expansion in a fire situation.
10 The galvanised mild steel ductwork connections must be sealed with an approved galvanised mild
steel ductwork sealer and fixed with low resistance fixings such as aluminium rivets that will melt at
high temperature allowing the duct to break away without aecting the integrity of the installation.
11 The connecting galvanised mild steel ductwork must be independently supported within one metre of
the connections and have been installed in accordance with DW144.
12 An access door should be fitted on the access side of the damper for inspection and maintenance.
13 When the damper installation is complete the operation of the damper should be checked.
14 Complete DW145 Fire Damper Certificate.

2530_IOM_1.1_Mar21_12
12
PRODUCT 2530 W/HEVAC APPLICATION RIGID CONSTRUCTION FLOOR
CLASSIFICATION REPORT NO. BRE 287810C CLASSIFICATION E120 HO I O S
TESTED INSTALLATION METHOD SHOWN. DIFFERING INSTALLATION METHODS TO THIS MUST BE APPROVED BY THE BUILDING CONTROL AUTHORITY (BCA) BEFORE PROCEEDING.
FIRE & SMOKE 2530 HEVAC FOR RIGID SUPPORTING CONSTRUCTION FLOOR
Turnback ties
HEVAC frame 2530 Series
fire & smoke damper
Rigid construction
Fire batt
Installation sequence
4 In the opening, mark the positions for the turnback tabs on the HEVAC frame, making sure that the
HEVAC casing will sit flush with the floor surface..
5 Create 20mm deep pockets for the HEVAC tabs to be located in.
6 Oer up the damper into the opening from below or clamp angles spanning the opening.
7 Bend the HEVAC tabs so that they lock into the pockets.
8 Fire batt of a minimum 25mm thickness and a density of 140kg/m shall be installed under the damper
frame to serve as shuttering to facilitate installation of the penetration seal all around the damper.
9 A 4:1 mortar mix can then be gradually applied between the wall and the damper, ensuring the mortar
is only filled up to the HEVAC frame and not the damper spigots. This ensures the damper can move
within the HEVAC frame.
10 The fire batt shall remain in situ after the mortar has been applied.
11 The galvanised mild steel ductwork connecting to the damper spigots must overlap by up to 40mm,
leaving minimum 10mm clearance for any duct expansion in a fire situation.
12 The galvanised mild steel ductwork connections must be sealed with an approved galvanised mild
steel ductwork sealer and fixed with low resistance fixings such as aluminium rivets that will melt at
high temperature allowing the duct to break away without aecting the integrity of the installation.
13 The connecting galvanised mild steel ductwork must be independently supported within one metre of
the connections and have been installed in accordance with DW144.
14 An access door should be fitted on the access side of the damper for inspection and maintenance.
15 When the damper installation has been completed, checks should be made to ensure the damper is
secure and there is no movement, operation of the damper should be checked.
16 Complete DW145 Fire Damper Certificate.
Preparing the opening
1 Ensure that the damper is kept
in a clean dry environment and
that there is no damage to the
damper.
2 Remove all the packaging and
transit ties before installation.
3 Work out the opening size to be
cut using the table adjacent.
Nom. duct Opening width /
height min.
Opening width /
height max.
200 x 200mm
and above Nom. duct +170mm Nom. duct +200mm
199 x 199mm
and below 370 x 370mm 400 x 400mm
Circular duct Opening width /
height min.
Opening width /
height max.
175mm and over Nom. duct +195mm Nom. duct +225mm
174mm and under 395mm 425mm

2530_IOM_1.1_Mar21_13
13
Initial operating check
The 2530 damper should only be commissioned once it is fully installed and connected to electrical power.
The damper installation should be inspected thoroughly to ensure that it is clean and free of any internal
debris before the damper actuation is tested as per the following instructions:
• Isolate the power.
• Remove the access door.
• Test the damper manually by using the Allen key provided and
turning it clockwise until the damper is fully opened, mechanically
lock the actuator by using a screwdriver to turn the STOP SHAFT 5.
• Visually inspect the damper checking that the damper is in its fully
opened position.
• Close the damper by turning the Allen key clockwise and releasing
it, the spring action of the actuator will wind the damper to its fully
closed position.
• Visually inspect through the access door that the blades are fully
closed.
• Reapply power to the actuator. The actuator will start to travel, and
a GREEN light will be lit on the Thermal Release housing, it will take
90 seconds to fully open.
• The switch on the Thermal Release housing can be pressed to
simulate activation of the thermal release, the LED light will turn
RED and the actuator will spring return to its unpowered position,
it should take 15 seconds to complete this cycle.
• Release the switch and the damper will return to its fully opened
position.
• Visually inspect through the access door that the blades are fully
open and then re-fit the access door.
• Damper not fully opening or closing?
• Obstruction to the blades – remove the obstruction.
• Incorrect set up of the actuator – the actuator has been adjusted by others from the Factory Set
position.
• For other faults contact Advanced Air Sales Oce.
• Complete any relevant reports.
Maintenance
2530 dampers are installed as a life safety product and it is essential that they are always maintained so they
are in a good, clean working condition. In accordance with BS9999 Annex W.1 maintenance and inspection
should be undertaken annually.
Maintain the dampers as follows;
• Remove the access door to internally inspect the damper.
• Visually inspect all damper components for signs of corrosion, obstructions and build-up of dirt/dust.
• Remove any obstructions, wipe away all dirt and dust from the damper blades, sides seals and duct
surfaces.
• The damper blades are fitted to sintered metal, self-lubricated bearings which do not normally require
any attention.
• Check that the thermal release probe is intact and does not show signs of damage.
• After internal inspections are complete a functional check of the damper should be made.
• The 2530 damper is fitted with an electrical thermal release probe and its housing has a LED light and
an On/O toggle switch.
• A GREEN light indicates that there is a power supply and that the thermo sensor is OK.
• A RED light indicates a power supply but there is a fault.
• No light indicates that there is no power supply.
• Push and hold the toggle switch to simulate over-temperature. This simulates the response of the
release, enabling the proper functioning test of the actuator and damper. It should take 15 seconds for
the damper to close and during the test the LED light will turn RED.
• After checking that the blades on the damper are fully closed, release the switch and the actuator
will power to its open position and the light will turn GREEN, check that the blades are in the open
position.
• Refit the access door and complete maintenance reports as appropriate.
2530 OPERATION AND MAINTENANCE
STOP SHAFT
– turn 5º
Allen key slot
LED Light
Switch
RED
Operating voltage OK. Thermo sensor defect.
GREEN
Operating voltage OK. Thermo sensor OK.
DARK
No operating voltage.

2530_IOM_1.1_Mar21_14
14
WIRING INSTRUCTIONS 2530
12345678
G:\PRODUCTS\DMP - 2500 Series\02 Engineering\Drawings\D2500 - ES - Electrical\2530\2530CE ES001 - Wiring diagram dampers\D2530CE ES001 Rev C - 2530 General Wiring.dwg
Wiring detail for dampers fitted with spring return actuators AA230TS18 or AA24TS18.

2530_IOM_1.1_Mar21_15
15
WIRING INSTRUCTIONS 2530 MULTISECTION
12345678
G:\PRODUCTS\DMP - 2500 Series\02 Engineering\Drawings\D2500 - ES - Electrical\2530\2530CE ES001 - Wiring diagram dampers\D2530CE ES001 Rev C - 2530 General Wiring.dwg
Wiring detail for multi-section dampers fitted with spring return actuators AA230TS18 or AA24TS18.

2530_IOM_1.1_Mar21_16
16
Fire Damper Certificate
CE-020
CE Certification
Rev 01
June 2019
S Manning
DW 145 Inspection & Handover Check Sheet to be completed by the installer with a separate
certificate for each damper.
No.
Question
Guidelines
Tick
1 Are the dampers the correct type?
Fire Damper Model 0160, 0400MAN
Fire Damper Model 2550, 2530, 26SCD
and 0400FME
2 Are the dampers correctly identified?
Identification label clearly shows the
damper individual reference number
3 Are the dampers located correctly?
The damper position matches the
position as detailed on the
manufactures installation instructions
4
Have supports for both the damper and
the adjacent ductwork been installed in
accordance with the approved method?
5
Are the dampers fitted in the correct
orientations?
The dampers are installed the correct
way up relative to airflow and access
6 Is access, through the ductwork to the
damper unobstructed?
There is unobstructed space to allow
safe access to damper, also through
ceiling void and adjacent services
7
Confirm the space around the damper has
not been used for the passage of other
services
The presence of other services will
invalidate the installation method
8
Using the access opening provided,
confirm that the damper has been left in
the open position
9
Release the damper catch to simulate the
thermal release mechanism (damper drop
test)
Ensure the blade operation is free from
interference
10 Check damper blades for damage
With the damper in the closed position
inspect for damage
11 Re-set damper and replace access panel
After resetting check that if supplied
the visual position indicator is correct
12 Is the fire barrier and penetration seal
complete?
Confirm at handover if installation is
complete and if no then other trades
will be required to finish
13 Handover damper installation for
commissioning
Obtain relevant acceptance of the
damper installation from the
nominated person responsible
Project
Installer Name
Damper ID No:
Company
Location
Date
Type
I hereby confirm the damper detailed has been installed and
tested according to the manufactures recommendations
Model No:
Signature
Table of contents
Other Advanced Air Fire And Smoke Damper manuals
Popular Fire And Smoke Damper manuals by other brands

Swegon
Swegon Actionair SmokeShield PTC installation guide

ETS NORD
ETS NORD NORDfire manual

mercor
mercor mcr WIP LD Operation and maintenance manual

Helios
Helios BTK Series Installation and operating instructions

LUCOMA
LUCOMA DRK Installation, operation and maintenance instructions

Ideal Heating
Ideal Heating EVOMAX 2 40 Installation