Airspan AS4000 Guide

605-0000-432 Airspan Communications Corporation
Issue 1.3a Date 18th October 1999
AS4000
Wireless Local Loop System
Central Terminal
Installation and Commissioning

AS4000 Central Terminal Installation and
Commissioning Preface
605-0000-432
Issue 1.3a Date 18th October 1999
Page 2 of 8
This Page Intentionally Blank

AS4000 Central Terminal Installation and
Commissioning Preface
605-0000-432
Issue 1.3a Date 18th October 1999
Page 3 of 8
Notice
1. This manual is subject to revision.
2. All rights reserved.
3. Right of modification reserved.
4. This manual is supplied without liability for errors or omissions.
5. No part of this manual may be reproduced or used except as authorised by contract or
other written permission.
6. This equipment is conditioned by the requirement that no modifications will be made to
the equipment unless the changes or modifications are expressly approved by ACC
Communications
7. Prerequisite skills: Personnel installing, commissioning, and maintaining the Airspan
products must have a basic knowledge of telephony and radio communications, and have
experience in installing, commissioning and maintaining telecommunications products.
ACC provides a range of comprehensive training courses specifically aimed at providing
operators/users of Airspan products with the prerequisite skills to install, commission and
or maintain the product. The courses can be tailored to provide the level of training
required by the operator/user.
8. Airspanand Sitespanare Registered Trademarks of Airspan Communications
Corporation.
For additional information on Airspan Systems, please call your ACC Representative, or
contact ACC at: Cambridge House
Oxford Road
Uxbridge
Middlesex
UB8 1UN
Call (44) 895 4677100

AS4000 Central Terminal Installation and
Commissioning Preface
605-0000-432
Issue 1.3a Date 18th October 1999
Page 4 of 8
This Page Intentionally Blank

AS4000 Central Terminal Installation and
Commissioning Preface
605-0000-432
Issue 1.3a Date 18th October 1999
Page 5 of 8
Safety Instructions - Warnings and Cautions
SAFETY
1. Read and follow all warning notices and instructions marked on the product or included in
this manual
2. Do not allow anything to rest on the power cord and do not locate the product where
persons could step or walk on the power cord.
3. When installed in the final configuration, the product must comply with the applicable
Safety Standards and regulatory requirements of the country in which it is installed. If
necessary, consult with the appropriate regulatory agencies and inspection authorities to
ensure compliance.
4. No hazardous RF radiation is emitted from the equipment. Measured at the surface of
the CRU radome, when transmitting, the maximum total power radiated from the CRU is
0.01% of the UK National Radiological Protection Board basic restriction per kg. of body
part.
WARNING - HAZARDOUS VOLTAGES
On AC installations, hazardous voltages exist. Use caution when verifying or working with
AC power. Remove metal jewellery that could come into contact with AC power.
On DC sections, short circuiting the low voltage, low impedance circuits can cause severe
arcing that may result in burns or eye damage. Remove rings, watches etc. to avoid shorting
DC circuits.
Electro-Static Discharge ESD
Electro-Static Discharge. Many circuits contain devices which are susceptible to damage
from high impedance voltage sources. To avoid such risks always follow anti-static
procedures where marked.

AS4000 Central Terminal Installation and
Commissioning Preface
605-0000-432
Issue 1.3a Date 18th October 1999
Page 6 of 8
NOTE
Airspan products do not contain hazardous substances (as defined in UK ‘Control of
Substances Hazardous to Health Regulations 1989’, and the ‘Dangerous Substances
Regulations 1990’). At the end of any Airspan product’s life cycle, the customer should
consult with DSC to ensure that the product is disposed of in conformance with the relevant
regulatory requirements
The Symbol on an Airspan product signifies that it has been certified according to the
EMC directive 89/336/EEC. The product fulfils the requirements according to the following
standards:
EN50082-1 for Immunity.
EN55022 Group 1 Class A for the Central Terminal Emissions.
EN55022 Group 1 Class B for the Subscriber Terminal Emissions.
NOTE
The Subscriber Terminal equipment has been tested and found to comply with the limits for a
Class B digital device, pursuant to part 15 of the FCC Rules.

AS4000 Central Terminal Installation and
Commissioning Preface
605-0000-432
Issue 1.3a Date 18th October 1999
Page 7 of 8
User Response Form
Mail: Airspan Communications Limited Fax: (44) 895 4677182
Cambridge House
Oxford Road
Uxbridge
Middlesex
UB8 1UN
Document Rating Excellent Good Average Below Average Poor
Accuracy / Completeness qqqqq
Clarity / Organisation qqqqq
Figures qqqqq
Table of Contents/Index qqqqq
The nature of this response is Addition qDeletion qCorrection q
Please enter details of response below (include precise reference to Section, Page, Paragraph)
Please Complete the following for acknowledgement/response:
Name: ........................................ Address ..........................................
Company ........................................ ..........................................
Job Title ........................................ ..........................................
Department ........................................ ..........................................
Telephone ........................................ ..........................................
Thank you for your co-operation and assistance.

AS4000 Central Terminal Installation and
Commissioning Preface
605-0000-432
Issue 1.3a Date 18th October 1999
Page 8 of 8
This Page Intentionally Blank

AS4000 Central Terminal Installation and
Commissioning ICL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 1 of 2 © Copyright Airspan Communications Corporation 1999
ISSUE CONTROL LIST
Title Issue Date Issue Details
Title Page 1.3 April 1999
ICL-001 1.3 April 1999
IXL-001 1.3 April 1999
GSI-001 1.3 April 1999
GSI-002 1.3 April 1999
GSI-003 1.3 April 1999
DLP-001 1.3 April 1999
DLP-002 1.3 April 1999
DLP-003 1.3 April 1999
DLP-004 1.3 April 1999
DLP-005 1.3 April 1999
DLP-006 1.3 April 1999
DLP-007 1.3 April 1999 Content Removed
DLP-008 1.3 April 1999
DLP-009 1.3 April 1999
DLP-010 1.3 April 1999
DLP-011 1.3 April 1999
DLP-012 1.3 April 1999
DLP-013 1.3 April 1999
DLP-014 1.3 April 1999 Changes to LCU operation
DLP-015 1.3 April 1999
DLP-016 1.3 April 1999
DLP-017 1.3 April 1999
DLP-018 1.3 April 1999
DLP-019 1.3 April 1999
DLP-020 1.3 April 1999 Content Removed
DLP-021 1.3 April 1999
DLP-022 1.3 April 1999

AS4000 Central Terminal Installation and
Commissioning ICL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 2 of 2
CHANGE TYPE/DATE PURPOSE PAGES AFFECTED
Issue #, Month Year
1.0
1st July 98
Re structured and
Renumbered from
157-032-200
All
1.1
27th August 98
New logo and product
numbering. Changes
to commissioning
process
All
1.2
19th November 98
Changes to Rxsetup
uising LCU DLP14
1.3
7th April 99
Changes to Band
names. References to
Element Manager
removed

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 1 of 10 © Copyright Airspan Communications Corporation 1999
INDEX TASK LIST
PREFACE:
Safety Instructions Warnings and Cautions
User Response Form
ACCESS: ICL, IXL
Issue Control List ................................................................................................ICL-001
Index Task ListIXL-001
GENERAL SYSTEM INFORMATION: GSI
Introduction.......................................................................................................... GSI-001
1. Purpose of Document..............................................................................................1
2. Prerequisite skills....................................................................................................1
Overview ..............................................................................................................GSI-002
1. Installation Tasks...................................................................................................1
2. Safety ....................................................................................................................1
2.1. Electromagnetic Radiation ..................................................................................1
2.2. Hazardous Voltages ............................................................................................1
2.3. ESD....................................................................................................................2
Technical Specifications....................................................................................... GSI-003
1. Central Terminal.....................................................................................................1
DETAILED LEVEL PROCEDURES: DLP
Preparatory Tasks .............................................................................................. DLP-001
1. Installation Tools and Equipment............................................................................1
1.1. Required Tools....................................................................................................1
1.2. Required Equipment ...........................................................................................2
2. Site Readiness.........................................................................................................2
2.1. Power Availability ..............................................................................................2
2.2. Site Earth............................................................................................................3
2.3. Flooring..............................................................................................................3
2.4. Cable Trays.........................................................................................................3
2.5. Delivery Inspection.............................................................................................3
2.6. Unpacking Inspection..........................................................................................4
AS4000 Release 3 Rack Installation. .................................................................. DLP-002

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 2 of 10
1. Positioning and Securing.........................................................................................1
1.1. In a Suite.............................................................................................................1
1.2. To a Wall............................................................................................................2
2. Rack Earthing.........................................................................................................3
AS4000 Release 4 Rack Installation.................................................................... DLP-003
1. Positioning and Securing Racks..............................................................................1
1.1. Installing Rack in a Suite ....................................................................................1
1.2. Securing Rack Base ............................................................................................2
1.3..............................................................................................................................3
Securing the rack using overhead Ironwork ................................................................3
1.4..............................................................................................................................4
Securing a Rack to a Wall...........................................................................................4
2. Rack Earthing.........................................................................................................5
CT Power and Alarm Cabling ........................................................................... DLP-004
1. DC Power...............................................................................................................1
2. Shelf Identity Settings.............................................................................................2
3. Alarm Unit (Type 55B) External Connections.........................................................4
AS4000 Release 3 2Mbit/s Cabling. ...................................................................DLP-005
1. 2Mbit/s Cabling 75ΩCoax.....................................................................................1
2. 2Mbit/s Cabling 120ΩTwisted Pair........................................................................4
3. Channel Bank .........................................................................................................4
AS4000 Release 4 2Mbit/s Cabling. ...................................................................DLP-006
1. 2Mbit/s Cabling 75ΩCoax .....................................................................................1
2. 2Mbit/s Cabling 120ΩTwisted Pair........................................................................3
3. Channel Bank .........................................................................................................4
Reserved for future use.......................................................................................DLP-007
Connection to Sitespan .......................................................................................DLP-008
1. Modem Connection to Sitespan...............................................................................1
2. Fixed Link Connection to Sitespan..........................................................................2
Card Installation. ................................................................................................DLP-009
3. Preliminary.............................................................................................................1
4. Card Insertion.........................................................................................................2
4.1..............................................................................................................................4
Initial installation of cards in a newly provided rack ...................................................4
4.2. Installation of card sets when providing Modem Shelf 3.....................................6
4.3. Installation of card sets when providing Modem Shelf 2 or 4 ..............................7
Commissioning Process Flowcharts....................................................................DLP-010
2. Commissioning racks for use with SiteSpan............................................................1
2.1. Using Level Control Unit....................................................................................2

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 3 of 10
2.2. 2.0-2.3GHz Band Using Test CRU .....................................................................3
2.2. 2.3-2.5GHz Band Using Test CRU .....................................................................4
2.3. 3.4-3.6GHz Band Using Test CRU .....................................................................5
Rack Turn-up......................................................................................................DLP-011
1. Rack Turn-Up and Measuring Input Voltage(Test 1a).............................................1
2. Switching on the rack. (Test 1b)..............................................................................1
3. PSU Voltage: (Test 2).............................................................................................1
Configuration and System Set-up.......................................................................DLP-012
1. Disconnect 2Mbit/s feeds........................................................................................1
2. Alarm and Status Indications (Test 3).....................................................................1
3. Insert Test Modem Card..........................................................................................4
4. Configuration and System Set-up............................................................................4
5. Self Test (Test 4) ....................................................................................................6
6. System Soak...........................................................................................................6
7. Reset RF Card.........................................................................................................6
1.....................................................................................Error! Bookmark not defined.
Test TX Output Power........................................................................................DLP-013
1. Test TX Output Power (Test 5)...............................................................................1
Setting Of RX Gain Control using Level Control Unit...................................... DLP-014
1. Setting Of RX Gain Control. (Test 6)......................................................................1
2. Setting up RX sensitivity using the Level Control Unit...........................................1
3. Re-Connecting The 2Mbit/s Ports On The Modem Shelf.........................................5
4. Remove Test Modem..............................................................................................5
CT Tx and Rx Power Set-up (2.0-2.3GHz Band) Using Test CRU ...................DLP-015
1. Tools and equipment needed...................................................................................1
2. Preparation .............................................................................................................1
3. Test TX Output Power. (Test 5)..............................................................................2
4. Connecting Test CRU.............................................................................................3
5. Setting Of RX Gain Control....................................................................................5
6. Re-Connecting The 2Mbit/s Ports On The Modem Shelf.........................................6
7. Remove Test Modem..............................................................................................7
CT Tx and Rx Power Set-up (2.3-2.5GHz Band) Using Test CRU ...................DLP-016
1. Tools and equipment needed...................................................................................1
2. Preparation .............................................................................................................1
3. Test TX Output Power. (Test 5)..............................................................................2
4. Connecting Test CRU.............................................................................................4
5. Setting Of RX Gain Control....................................................................................6
6. Re-Connecting The 2Mbit/s Ports On The Modem Shelf.........................................7
7. Remove Test Modem..............................................................................................7
Setting of 3.4-3.6GHz Band TX and RX Gain Control using Test CRU...........DLP-017
1. Tools and equipment needed...................................................................................1

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 4 of 10
2. Preparation .............................................................................................................1
3. Test TX Output Power. (Test 5)..............................................................................2
4. Connecting Test CRU.............................................................................................3
5. Setting Of RX Gain Control (Test 6).......................................................................4
6. Re-Connecting The 2Mbit/s Ports On The Modem Shelf.........................................5
7. Remove Test Modem..............................................................................................6
VF Tests ..............................................................................................................DLP-018
1. Functionality Tests (Test 7SC)................................................................................1
2. Remove Test Modem..............................................................................................1
Setting The Rack into service..............................................................................DLP-019
1. Setting the rack into service:...................................................................................1
2. Connecting Antenna Feeder Tails ...........................................................................1
3. Using a single Antenna...........................................................................................1
4. Termination Of Spare RF Ports...............................................................................2
5. Switch on Rack.......................................................................................................2
Reseved for future use......................................................................................... DLP-020
Set Up Channel Bank .........................................................................................DLP-021
1. Setting Up AS4000 To Use Litespan-120 (LS-120) Channel Bank..........................1
1.1. Cable Termination E1 Tx and Rx........................................................................1
1.2. Set up AS4000....................................................................................................1
1.3. Signalling File Configuration Using SiteSpan .....................................................1
Test Results .........................................................................................................DLP-022
2. Commissioning racks for use with SiteSpan............Error! Bookmark not defined.
2.1. Using Level Control Unit....................................................................................2
2.2. 2.0-2.3GHz Band Using Test CRU .....................................................................3
2.2. 2.3-2.5GHz Band Using Test CRU .....................................................................4
2.3. 3.4-3.6GHz Band Using Test CRU .....................................................................5
2.4. Test Equipment Calibration.................................................................................7
Site Acceptance....................................................................................................DLP-022
1. Site Acceptance ......................................................................................................1
1.1. Site Inspection ...................................................................................................1
2. Site Acceptance Forms............................................................................................1
2.1. Purpose..............................................................................................................1

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 5 of 10
List of Figures
Figures Page
DLP-001
Figure 1. Packaging for CT Site 3
DLP-002
Figure 2. Central Terminal Rack. 1
Figure 3. Typical Overhead Ironwork Support 2
Figure 4 Securing a AS4000 Release 3 rack to a wall 3
DLP-003
Figure 5. AS4000 Release 4 Central Terminal Rack. 1
Figure 6. Securing Rack Base 2
Figure 7. Typical Overhead Ironwork Support 3
Figure 8. Securing Rack To Wall 4
Figure 9. Rack Earthing 5
DLP-004
Figure 10. DC Termination On Combiner Shelf. 2
Figure 11. Rack Power Wiring 3
Figure 12. AS4000 Alarm Unit Connections 4
Figure 13. Station Alarm Connection 4
DLP-005
Figure 14. AS4000 Release 3 Rack Cable Runs 2
Figure 15. Rack Cabling 3
Figure 16. Shelf Interface Connections. 3
Figure 17. 120 balanced connections 4
DLP-006
Figure 18. AS4000 Release 4 Rack Cable Runs 1
Figure 19. Rack Cabling 2
Figure 20. 120 balanced connections 3
Figure 21. Shelf Interface Connections. 4
DLP-007
Figure 22. AS4000 Connections to X.25 Network Error! Bookmark not defined.
Figure 23. Typical EM X.25 PAD to CT Rack Connections Error! Bookmark not defined.
DLP-008
Figure 24. Sitespan Modem Connections 1
Figure 25. Sitespan E1 Fixed Link Connection 2
Figure 26. D-Type Wiring Details (1) 3
Figure 27. D-Type Wiring Details (2) 4
DLP-009
Figure 28. Part of RF Combiner Shelf showing Circuit Breakers. 1
Figure 29. Card Insertion 2
Figure 30. DIL Switch (Typical Settings) 5
Figure 31. Coupler Connection 6
DLP-011
Figure 32. PSU Voltage Test. 1
DLP-012

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 6 of 10
Figure 33. Combining Shelf Alarm Indications 3
Figure 34. Modem Shelf Alarm Indications 4
DLP-013
Figure 35. Power Level measurement Test Set-up 1
DLP-015
Figure 36. Power Level measurement Test Set-up 3
Figure 37. Test Set-Up Modem Shelves (2.0-2.3GHz Band) 4
Figure 38. Test CRU Connections. 5
Figure 39. RF Gain Settings 5
DLP-016
Figure 40. Power Level measurement Test Set-up 3
Figure 41. Test Set-Up Modem Shelves (2.3-2.5GHz Band) 5
Figure 42. Test CRU Connections. 5
Figure 43. RF Gain Settings 6
Figure 44. Power Level measurement Test Set-up 2
Figure 45. Test Set-Up Modem Shelves (3.4-3.6GHz band) 4
Figure 46. Setting Receiver Sensitivity 5
DLP-018
Figure 47. RF Antenna Connections 1
DLP-020
Figure 48. AS4000 using LS120 as a Channel Bank 1
Figure 49. Edit Menu 2
Figure 50. Modem Shelf Properties 3
List of Tables
Table Page
Table 1. Physical Characteristics. 1
Table 2. Environmental Specifications. 1
Table 3. Power Requirements. 2
Table 4. Required Test Equipment. 2
DLP-004
Table 5. DC Power Cables. 1
Table 6. Shelf Identity Settings 2
DLP-009
Table 7. Shelf Identity Settings 1
DLP-012
Table 8. RF Combiner Shelf DIP/LNA1 Card LED Indications. 1
Table 9. RF Combiner Shelf RF Card LED Indications. 1
Table 10. RF Combiner Shelf Monitor Card 1 LED Indications. 2
Table 11. RF Combiner Shelf PA Card LED Indications. 2
Table 12. RF Combiner Shelf PSU Card LED Indications. 2
Table 13. Modem Shelf Controller Card LED Indications. 2
Table 14. Modem Shelf Tributary Unit Card LED Indications. 2
Table 15. Modem Shelf Analogue Card LED Indications. 2
Table 16. Modem Shelf Modem Card LED Indications. 3

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 7 of 10
List of Charts
Table Page
DLP010
Chart 1. Card Insertion 3
Chart 4. Commissioning ALL-Bands connecting to Sitespan using Level Control Unit. 2
Chart 5. Commissioning 2.0-2.3GHz Band connecting to Sitespan using Test CRU. 3
Chart 6. Commissioning 2.3-2.5GHz Band connecting to Sitespan using Test CRU. 4
Chart 7. Commissioning 3.4-3.6GHz Band connecting to Sitespan using Test CRU. 5
DLP 022
Chart 10. Commissioning ALL-Bands connecting to Sitespan using Level Control Unit. 2
Chart 11. Commissioning 2.0-2.3GHz Band connecting to Sitespan using Test CRU. 3
Chart 12. Commissioning 2.3-2.5GHz Band connecting to Sitespan using Test CRU. 4
Chart 13. Commissioning 3.4-3.6GHz Band connecting to Sitespan using Test CRU. 5

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 8 of 10
Abbreviations
AC Alternating Current
AGC Automatic Gain Control
AU Analogue Unit
BER Bit Error Rate
CAS Channel Associated Signalling
CDMA Code Division Multiple Access
CPE Customer Premises Equipment
CRU Customer Radio Unit
CT Central Terminal
DC Direct Current
DMM Digital Multi Meter
DRS Digital Radio System
ERP Effective Radiated Power
HCI Human Computer Interface
ISDN Integrated Services Digital Network
ITU-T International Telecommunications Union -Telecommunications
LCU Level Control Unit
LD Loop Disconnect
LED Light Emitting Diode
MF Multi-Frequency
NTU Network Termination Unit
PC Power Control
POTS Plain Old Telephony Service (analogue)
PSU Power Supply Unit
RF Radio Frequency
Rx Receive
SC Shelf Controller
ST Subscriber Terminal
TU Tributary Unit
Tx Transmit
VDU Video Display Unit
VF Voice Frequency
Definitions
dBm Decibels relative to 1 milli-watt
dBr Decibels relative to the network PCM level
Downlink The communication channel from the CT to the ST
Uplink The communications channel from the ST to the CT
Symbols
IEC Earth

AS4000 Central Terminal Installation and
Commissioning IXL 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 9 of 10
Related Documentation
605-0000-430 AS4000 System Overview
605-0000-431 AS4000 Operations And Maintenance
605-0000-433 AS4000 Central Terminal - Antenna/Feeder
Installation & Commissioning
605-0000-434 AS4000 Subscriber Terminal -
Installation & Commissioning
605-0000-437 AS4000 D128 Terminal Converter
605-0000-435 Material Return and Repair
605-0000-427 AS8100 Sitespan 2.5

AS4000 Central Terminal Installation and
Commissioning GSI 001
605-0000-432
Issue 1.3a Date 18th October 1999
Page 1 of 2 © Copyright Airspan Communications Corporation 1999
INTRODUCTION
1. Purpose of Document
This document describes the installation and commissioning of the ACC AS4000™
Central Terminal (CT) Rack and associated shelves to AS4000 specifications. This
document covers new rack installations and the incremental addition of modem
shelves.
2. Prerequisite skills
Personnel installing and commissioning the Airspan products must have a basic
knowledge of telephony and radio communications, and have experience in installing
telecommunications products. ACC provides a range of comprehensive training
courses specifically aimed at providing operators/users of Airspan products with the
prerequisite skills to install, commission and or maintain the product. The courses can
be tailored to provide the level of training required by the operator/user.
This manual is intended for use by persons familiar with the AS4000 product having
attended the ACC CT Installation and Commissioning training course prior to
performing the procedures in this practice.
Other manuals for AS4000
6
Table of contents
Other Airspan Microphone System manuals
Popular Microphone System manuals by other brands

Sennheiser
Sennheiser Industry Acoustic System IAS-MO 2000 Instructions for use

Steren
Steren WR-057 instruction manual

Lectrosonics
Lectrosonics SMWB/E07 Series instruction manual

Twin Disc
Twin Disc Technodrive TMC 40M operating manual

ZF Marine
ZF Marine ZF 335 Family manual

Rockville
Rockville RWM-66 owner's manual