20 Mounting and installation work 2596642-C_EN_2010_Condair GS_IM
5.3 InstallationSpaceRequirements
In preparation for installation of the Condair GS humidier ensure that the following installation space
requirements are satised. Report any discrepancies to the site engineer.
– The installation space must comply with the applicable local and national regulations for the instal-
lation of gas-red appliances.
– The room in which the Condair GS is to be installed should be lockable if possible.
– The installation room must be protected against dripping water and must have the following tem-
perature and humidity values throughout the year:
Room temperature: +15°C to +30°C
Room humidity: 15 %rh to 75 %rh (non condensing)
– There must be no ammable materials (e.g. wooden oors, carpets, etc.) or other sensitive materials
in the installation room.
– Sufcient space must be available for operation and maintenance at the place of installation of the
Condair GS humidier.
– The oor surface or wall surface on which the Condair GS humidier is mounted must be level, have
sufcient load-bearing capacity (for maximum operating weights, see Table 2) and be suitable for
mounting (no vibrating, hot or very cold surfaces).
– The oor surface or wall surface on which the Condair GS humidier is mounted must be able to
withstand temperatures of 60-70 °C.
– There should be a oordrain in the installation room that is connected to the building's waste water
line. If there is no oor drain in the room, the room must be equipped with a leakage monitoring
device which automatically shuts off the water supply in the event of a water leak.
– It must be possible to install the Condair GS humidier in the room in such a way that the maximum
permissible length of the steam line between the humidier and the steam distributor(s) is not ex-
ceeded, the minimum bend radii of the steam line are observed and that the steam pipe/steam hoses
can be laid with a constant upslope or downslope (see notes on steam installation in Section 5.6).
– A water supply connection (drinking water, RO water or deionized water) must be available or be
made in the installation room. Please note the information on water supply in Section 5.7).
– In the installation room, depending on the location of the Condair GS humidier and the steam
distributor(s), there must be one or two open drain funnels with trap, which is/are connected to the
building's waste water line (see notes on water installation in Section 5.7.
– The building's waste installation must be made of heat-resistant material that is designed for drain-
age water of up to 100 °C.
– The room in which the Condair GS humidier is to be installed must have a sufciently large air sup-
ply opening (in-room air installation) or a combustion air supply via a pipe from the outside (room
seal installation). Please note the information in Section 5.8.
– The room in which the Condair GS humidier is to be installed must allow exhaust gas discharge to
the outside. Please note the information on exhaust gas installation in Section 5.9.
– In the installation room a gas supply connection must be available or be made. Please note the
information on gas installation in Section 5.10).
– The installation room must be equipped with a 230V/1~/50-60 Hz power supply. Please note the
information on electrical installation in Section 5.12).