Huawei DPU40D-N06A3 User manual

1
Issue: 05
Date: 2020-02-29
Copyright © Huawei Technologies Co., Ltd. 2020. All rights reserved.
1Overview
PSU Indicator
Color
Status
Meaning
Run indicator
Green
Off
The PSU has no power input (no AC input and no battery input
)
Steady on
Start / Self
-check / Load (instantaneous status during startup or upgrade)
Blinking slowly (0.5 Hz)
The PSU communicating with the host
properly
Blinking fast (4 Hz)
The PSU is not communicating with the host
properly
Fault indicator
Red
Off
The PSU is
proper
Steady on
The PSU is faulty: Rectifier Fault/Monitoring Address Conflict/Monitoring Unit Fault
Blinking slowly (0.5 Hz)
An alarm that can be cleared is generated on the PSU: Rectifier Protection/Power off/
Communication Failure/Rectifier Power Failure/Parallel Fail/AC
Overvoltage/AC Undervoltage
Power supply unit (PSU):
DPU40D-N06A3 (≈ 7.5 kg)DBU20B-N12A3 (≈ 20 kg)
DBU50B-N12A1 (≈ 26 kg)
Installation
Scenario
Installation
Method
Max.
Capacity/Layer
Max. System
Configuration
Small pole
Side
mounting
2 PSUs +2 lithium
batteries (Install
the first battery
exactly on the pole,
the second battery
on its left side, or
two PSUs on its
right side.)
4 DC PSUs (DPU40D)
+ 8 lithium batteries
(
DBU20B/DBU50B)
Small pole,
wall,
large pole,
channel steel,
angle steel
Flush
mounting
1 PSU + 1 lithium
battery or 2 PSUs
Lithium
Battery
Indicator
Color
Status
Meaning
Run indicator
(RUN)
Green
Off
The lithium battery has no power input or is
faulty
Steady on
Board startup / self
-check / loading / activation / board power-on when no software is loaded
Blinking slowly (0.5 Hz)
The lithium battery is communicating properly with monitoring
equipment
Blinking fast (4 Hz)
The lithium battery fails to communicate with monitoring
equipment
Alarm
indicator (ALM)
Red
Off
The lithium battery is
proper
Steady on
The lithium battery has alarms that cannot be cleared: Board Hardware Fault/Heater
Fault/Electrochemical cell fault/Duplicate address
Blinking slowly (0.5 Hz)
The lithium battery has alarms that can be cleared: Discharge Overcurrent Protection/Charge
Overcurrent
Protection/High Temperature protection/Low Temperature Protection/Abnormal
shutdown/Charge Overcurrent Protection/Discharge Overcurrent Protection
DPU40D-N06A3, DBU20B-N12A3, and DBU50B-N12A1 Distributed
Power Quick Guide
2Installation Scenarios
If the system
configuration
exceeds the
maximum
capacity/layer,
install the
modules on
different layers.
There are two pole-mounting scenarios. In the large pole scenario, the pole diameter is 114 mm to 400 mm. In the small pole scenario, the pole
diameter is 60 mm to 114 mm. Select an appropriate pole based on site requirements. The following uses the small pole scenario as an
example.
NOTE
•If multiple PSUs are configured, they can be cascaded by connecting BAT and LOAD ports or by interconnecting LOAD ports. It is
recommended that DC loads be equally distributed on the PSUs.
•This section uses a maximum of two lithium batteries as an example.
(Unit: mm)
Lithium
battery:
(Unit: mm)

2
1 Frequency + 3 PSU 4 PSU + 8 Lithium Battery
1 Sector/1 Frequency + 1 PSU 1 Sector/1 Frequency + 2 PSU
3Installation Preparations
Wear gloves during installation.
Never install a module with power on. Ensure that the angle between a module and the line vertical to the ground is within 10degrees.
Do not assemble a lithium battery with an RRU. Do not install a PSU on the left side of an RRU or lithium battery.
The paint on the module exterior should be intact. If paint flakes off, repaint the area to avoid corrosion.
An upstream AC SPD of at least 30 kA is required for the PSU.
When securing a large-pole mounting kit, ensure that the hoops are closely attached to the pole and that there are no sundries between the
hoops and the pole.
When the PSU is assembled with the RRU or lithium battery, ensure that the PSU, RRU, and lithium battery are installed in thesame direction
and that the handles are on the same side.
After unpacking the equipment, you must power it on within 24 hours. When the equipment is maintained, the power-off duration cannot
exceed 24 hours.
If a lithium battery sunshade is configured, install the sunshade on the outer side of the lithium battery after installing the PSU and lithium
battery.
(Unit: mm) (Unit: mm)
(Unit: mm)
(Unit: mm)
PSU
Lithium Battery
PSU
Lithium Battery
PSU
Lithium Battery
PSU
Lithium Battery

3
1
4Installing PSUs and Lithium Batteries
Installingthe RJ45 CommunicationsCable for a Lithium Battery4.1
A x 1 Install the pole mounting kits.
Required Accessories InstallationProcedure
Pole mounting kit
B x 1 C x 1
Flush Mounting on a Small Pole: 1 PSU as an Example (Pole Diameter: 60–114 mm)
4.2
Hanging kit x 1
Install the PSU hanging kit. Install the PSU to the pole.
Side Mounting on a Small Pole: 2 PSUs + 2 LithiumBatteries as an Example (Pole Diameter: 60–114 mm)
4.3
Required Accessories InstallationProcedure
Install the connecting kit.
Install the pole mounting kits. Install the hanging kit.
A x 3
Pole mounting kit
B x 1 C x 1
Hanging kit x 1
Connecting kit x 1
Connecting plate x 3
Install the lithium batteries to the
pole. Install the PSUs to the pole. Install the the connecting plates.
If a sunshade is configured, install the
sunshade on the lithium battery.

4
Flush Mounting on a Small Pole: 1 PSU + 1 Lithium Battery as an Example (Pole Diameter: 60–114 mm)
4.4
Attachment
kit x 2
Install the pole mounting
kits. Install the attachment
kit on lithium battery
right side.
Install the attachment kit and
connecting kit to the lithium battery.
Required Accessories InstallationProcedure
A x 1
Pole mounting kit
B x 1 C x 1
Install the lithium battery to
the pole. Install the PSU to the
lithium battery.
Assemble the large pole
installation kits. Secure the large pole installation
kits to the large pole.
Large pole
installation
kit x 2 sets
Hanging
kit x 1
Connecting
kit x 1
Flush Mounting on a Large Pole: 2 PSUs + 1 Lithium Battery as an Example(Pole Diameter: 114–400 mm)
4.5
A x 2 B x 2 C x 0
Pole mounting kit
Required Accessories InstallationProcedure
Front Rear
Ensure that the hoops
are attached closely to
the pole so that they
do not slide.
Attachment
kit x 1
Assemble the PSUs and
install the PSU hanging kit.
(Unit: mm)
Install the connecting plate.
Connecting plate x 1
Install the PSUs to
the upper layer of the
large pole.
Install the attachment kit and hanging kit
on lithium battery right side. Install the lithium battery to the
lower layer of the large pole.
Install the connecting
plate.
Connecting plate x 1
If a sunshade is configured,
install the sunshade on the
lithium battery.

5
Install
expansion
anchor bolts.
Install pole
mounting kit B. Install the attachment kit and hanging kit on
lithium battery left side.
Install the lithium battery
to the wall. Install the PSU to
the lithium battery.
Flush Mounting on a Wall (Mode 1): 1 PSU + 1 Lithium Battery as an Example
4.6
A x 1 B x 1 C x 0
Pole mounting kit
(Unit: mm)
The wall must be able to bear a weight four times the weight of all PSUs and lithium batteries and the bolts' pulling force of
1.25 kN vertical to the wall.
Required Accessories InstallationProcedure
Hole depth: 55–
60 mm
Install pole
mounting
kit A.
Attachment kit x 2
Install the attachment
kit on lithium battery
right side.
Connecting plate x 1
Install the connecting plate.
Flush Mounting on a Wall (Mode 2): 1 PSU + 1 Lithium Battery as an Example
4.7
The wall must be able to bear a weight four times the weight of all PSUs and lithium batteries and the bolts' pulling force of
1.25 kN vertical to the wall.
Required Accessories InstallationProcedure
Install expansion anchor bolts. Install the wall
mounting kit.
Wall mounting
kit x 1
Hole depth: 55–60 mm
Connecting
plate x 1
Attachment
kit x 2
Install the attachment kit and hanging kit on
lithium battery left side.
Install the lithium battery to
the wall. Install the PSU to
the lithium battery.
Install the attachment kit on
lithium battery right side. Install the connecting plate.
(Unit: mm)

6
Channel steel
size and
installation
method
Angle steel
size and
installation
method
As shown in the left figures, when
the narrow edge size of channel
steel is less than 40 mm, only
installation methods a and b are
supported.
Whenchannel or angle steel is
used for installation, each layer
supports a maximum of 1 PSU + 1
lithium battery or 2 PSUs. Refer to
the procedure for flush mounting
on a small pole.
Flush Mounting on Channel or Angle Steel
4.8
NOTE
Installing a Ground Cable
5.1
5Installing Cables
Site ground bar
PSU
Lithium battery
Core cross-sectional area: 10 mm²
Core cross-sectional
area: 16 mm²
NOTE
The following figure uses one
PSU and one lithium battery as
an example.
Preparing AC and DC Cables
5.2
Negative (blue)
Positive (red)
PE (green)
N/L2/HVDC negative (blue)
DC wiring terminal AC wiring terminal
L/L1/HVDC positive (brown)
Cable Type
Core Cross
-
Sectional Area
Cable Outer
Diameter
AC (3
-core)
2
–4 mm2
9.0
–14.5 mm
DC (2
-core)
3.3
–6 mm2(O-type
DC power cable)
4
–10 mm2 (D-type
DC power cable)
NOTE
PSU load cables and AC input cables should be prepared onsite. DC load cables are used as an example here. Refer to this procedure
when preparing AC cables.
Multi-core cables should be used as AC and DC power cables; otherwise, water may seep into the waterproof connectors.
Before assembling the waterproof connector, check whether the connection between the cable and terminal is firm and reliable.
Preparing DC Cables and Connecting Waterproof Connectors
•If the cable diameter is ≤ 6 mm2, prepare cables as follows:
(Unit: mm)
Scale line

7
•If the cable diameter is > 6 mm2,prepare cables as follows:
Heat gun
Scale
line
Bare crimp
terminal
Crimping
tool
Heat
shrink
tubing
(Unit: mm)
InstallingGround Clips for DC Load Cables Cable binding hole (4 mm2)Cable binding hole (≥ 6 mm2)
Waterproof tape Insulation tape Cable tie Load cable Ground cable
Cable tie
InstallingPower Cables and CommunicationsCables
5.3
1 PSU + 2 Lithium Batteries
DB15 Female Connector Definition
Pin
Signal Name
Description
Pin
Signal Name
Description
1
ALM1+
AC outage alarm
(High resistance:
alarm; low
resistance: normal;
< 3
0 V/4 mA)
9
RS485_RX+
Northbound RS485
reception +
2
ALM1
-10
RS485_RX
-
Northbound RS485
reception
–
3
ALM2+
A PSU is faulty.
11
ALM4+
Anyone PSU or lithium
battery has an alarm
that can be cleared.
4
ALM2
-12
ALM4
-
5
ALM3+
A lithium battery is
faulty.
13
NC
NC
6
ALM3
-
7
RS485_TX+
Northbound RS485
transmission +
14
CANH
CAN data transmission
and reception H
8
RS485_TX
-
Northbound RS485
transmission
–15
CANL
CAN data transmission
and reception L
The system does not simultaneously support AC input and DC input.
Ensure that caps and waterproof connectors are installed at all idle
ports on the modules.
Ensure that cables are securely connected to terminals.
The PSU is connected to the RRU and BBU
to communicate with the NetEco or U2000.
NOTE
Lithium battery
PSU
AC/DC input
Monitoring
device
Site ground bar
Ground clip
DC load
Lithium battery

8
RRU5520
The PSU connect with RRU5XXX
(RRU5520 as an example)
When the U2000 is used for management, if
port MON0 is occupied and port MON1 is used,
change the connection serial port number on
the U2000 to 1.
NOTE
The PSU connect with RRU3XXX
(RRU3936 as an example) The PSU connect with BBU
(BBU3910 as an example)
The PSU communicate
with RRU via MBUS.
NOTE
Label 1
connect to
EXT_ALM
of RRU;
Label
connect to
COM_ALM
of PSU.
NOTE
RRU3936
1. Check that the mounting kits are securely installed and all screws are tightened.
2. Check that all cables are reliably connected with correct polarity and there is no short circuit.
3. Check whether any screw hole is not installed with a screw. If yes, install a screw in the hole.
6Verifying the Installation
7Power-On Commissioning
1. Measure the PSU input voltage. Ensure that AC input voltage is in the range of 85–300 V AC and the HVDC input voltage is in the range of
90–400 V DC.
2. Check the indicators on the PSUs and lithium batteries. Ensure that the green indicators are blinking slowly and red indicators are off.
3. Measure the DC output voltage at each load port. Ensure that the voltage is in the range of–42 V DC to –58 V DC.
4. Observe the power system for about 15 minutes. If no alarm indicator is on, the system is running properly.
BBU3910
LIVE-C APP(Only PSU 02312NGM Supports This Function)
Installingthe LIVE-C APP
8.1
There is a mobile phone running Android 4.3 or later.
The mobile phone can properly connect to the Internet.
The PSU needs to support the mobile app function and the
connection mode is Bluetooth connection or WiFi connection.
1. Obtain the latest LIVE-C APP
installation package from Huawei
technical support.
2. Install the LIVE-C APP on the mobile
phone.
LIVE-C APP iCON
8
NOTE
LoggingIn to the LIVE-C APP
8.2
The mobile phone app may be occasionally disconnected due to difference in phone model
and Bluetooth signal strength. Please try again 5 minutes later.
Certain mobile phones may fail to connect in automatic Bluetooth pairing mode due to
Android system differences. Please select the manual pairing mode to connect. Locate the
pairing request in the notice column and enter the pairing PIN 0000 or 000000.
The power equipment SN and Bluetooth name have the same last six digits.
NOTE
•After the first login, change the password in time to ensure account security and prevent
unauthorized network attacks, such as data tampering.
•Huawei will not be liable for any security issues caused by your failure to change the
default password in time or password loss after changing. (The password cannot be
retrieved if it is lost.)
Prerequisite
The mobile phone should be within 10 m away from the power equipment.
Procedure
1. Tap the LIVE-C APP icon access the home page.
2. Tap Power System Delivery, access the login screen.
3. Tap Bluetooth connection in the login screen of the APP, to search and connect for
power equipment with Bluetooth nearby.
Password Change: System Settings > Change Password.
4. Enter the user name and password. (initial user name: liveapp, initial password:
Changeme_123)
5. Tap Login to access Main Function Menu and view the operating parameters of the
power equipment.

9
LIE APP
Follow-up Operations
1. Reinstall caps and waterproof connectors on all unused ports of the modules.
2. Ensure that the paint on the module exterior is intact. If paint has flaked off, repaint the area to avoid corrosion.
3. Clean the site and leave.
9
Huawei Technologies Co., Ltd.
Huawei Industrial Base, Bantian, Longgang
Shenzhen 518129 People's Republic of China
e.huawei.com
LIE APP
FAQ:How Do I Expand the Capacity of DC Loads?
DC load
Four-way connector
Other manuals for DPU40D-N06A3
1
This manual suits for next models
2
Table of contents
Other Huawei Power Distribution Unit manuals

Huawei
Huawei PDC-0038V4ACIOA User manual

Huawei
Huawei PDU8000 Series User manual

Huawei
Huawei PDU8000 Series User manual

Huawei
Huawei PDU8000 Series User manual

Huawei
Huawei PDU8000 Series User manual

Huawei
Huawei PDU8000 Series User manual

Huawei
Huawei PDU8000 Series User manual

Huawei
Huawei PDC-0038V4ACIOA User manual

Huawei
Huawei PDU8000 Series User manual

Huawei
Huawei PDU8000 Series User manual