FRICK® POWERPAC™
INSTALLATION
170.600-IOM (JUN 11)
Page 7
The unit may be top heavy. Lifting
operators must use extreme care to
check the level and stability of the
load before lifting the load more than a few inches. Impose
an imbalance by sequentially adding weight to each corner
and carefully observing the load reaction to make sure the
load does not shift. Balancing chains, cables or straps are
essential in both directions to prevent load shift and
instability during rigging. Call Johnson Controls-Frick
Engineering for an estimate of the location of the center
of gravity of the package if one is not given. The center
of gravity may NOT be located in the center of the package.
NOTES:
Figure 5
INSTALLATION
FOUNDATION
NOTE: Allow space for servicing at both ends of the unit.
A minimum of 24 inches (610 mm) is recommended.
HANDLING AND MOVING
DO
NOT USE A FORKLIFT. Refer to the engineering drawings
provided with the unit for shipping weight.
Spreader bars should be used on
both the length and width of the
package to prevent damage to the
package. CAUTION must also be used in locating the lifting
ring. Appropriate adjust ment in
the lifting point
should be
made to compensate for the center of gravity.
Figure 4