6 - Installation and Commissioning
Installation must meet valid rules and may be done only by qualified staff. The tank shall be placed on the
floor, as close to the heat source as possible.
Defects caused by improper installation, use or handling are not covered by warranty.
6.1 - Connection to heat sources
Connect heating circuits to the inlets to and outlets from heating coils. The heat source for the tank -
a stainless-steel coil - connects with G 3/4” coupling.
6.2 - Connection to a solar system
The tank can be used with a solar system. In such a case, the inlet for hot heat-carrying liquid coming from the
solar system shall be connected to the G 3/4” upper sleeve of the heating coil and the lower outlet to the return
piping to the solar system. Insulate all the piping between the tank and the solar system.
6.3 - Heating rod installation
The G 6/4“ side sleeve is designed to accommodate an electric heating rod. Heating rods of output up to 6 kW
can be used (depending on the tank diameter and rod length), connected either directly to the mains (thermostat-
equipped rods), or to a heating system controller. The installation may be done by qualified staff only.
Warning: Electric heating elements shall be protected by a safety thermostat.
6.4 - Connection to water mains
DHW piping shall be done according to valid rules. G 3/4” threaded couplers are used to connect the tank to
a cold water inlet and hot water outlet. A 6bar safety valve shall be installed at the cold water inlet, installation
of a reducing valve is recommended. If the pressure from water mains exceeds 6 bar, a reducing valve is
necessary. In order to prevent water loss, an expansion tank should be installed at the cold water inlet as well
(8l volume for NBC 200, 12l volume for NBC 300).
Should the water be too hard, install a water softener before the tank. In case the water contains mechanical
impurities, install a strainer.
A suitable thermostatic mixing valve should be installed at the hot-water outlet from the tank, preventing too
hot water from entering the taps.
Install a drain valve to the lowest point of the tank.
Complete DHW piping shall be properly insulated.
6.5 - Electronic anode installation
An electronic anode is already installed in the tank. Its advantage compared to a magnesium anode rod is
a longer service life and easier check. A visual check of the electronic anode indication lamp is sufficient.
Unlike with a magnesium anode rod, there is no need to take it out for check.
6.6 - Commissioning
The tank shall be earthed prior to commissioning. The earth bolt with M6 nut is located under the
insulation, for access open the zipper for about 10 cm. Having connected a ground wire, close the zipper
again.
Fill the heating circuits with the appropriate fluids and air-bleed the entire system. Check all connections for
leaks and verify the system pressure.
The quality of top-up and heating water is set by ČSN 07 7401:1992. Hot water quality must meet the
conditions shown in the Table of limit values for total dissolved solids in hot water, page 7 of this
Manual.
Fill the heating circuits with the appropriate fluids and air-bleed the entire system. Check all connections for
leaks and verify the system pressure. Set the heating controller in compliance with the documentation and
manufacturer’s recommendations. Check regularly a proper function of all control and adjusting elements.