A safe access to the valve for installation and maintenance must be ensured by stairs, ramps or
platforms where necessary. Also arranging tools for valve lifting and movement shall be prevented.
Before installation employees must know the pipeline conditions in terms of knowledge of the eventual
hazards like high/low temperature, noise, toxicity, explosion or flammable medium.
Pipeline shall be cleaned by blow-off to avoid that impurities as welding particles can damage valve trim.
2.1 Recommended Installation details
All the above indications are strongly recommended to avoid injuries to people or damages to plant
during installation or maintenance.
Commissioning spares are suggested to avoid the risk that any unexpected damage or mistake during
operations could not permit the valve installation with a consequent huge loss of time and money.
Spare parts shall be requested by supplying the correct Serial Number (reported on valve plate located
on yoke) to Armstrong office for a precise quotation.
Armstrong valves will be supplied complete of a flow direction arrow on valve body casting. Where
process and piping design permit we suggest the installation of:
- Y filter to avoid impurities or suspensions that can damage valve trim parts (mesh to be defined
case by case)
- By-pass valves to permit an easier maintenance. Usually ball or butterfly to stop and a globe for
by-pass modulation
- Sensors or transmitters of Temperature, Pressure or Flow-rate depending on the specific
condition that the Armstrong valve is requested to control.
2.2 Installation sample scheme
The correct use of Armstrong control valve is conditional on the availability of a suitable installation
environment. Here below a Typical Scheme for correct valve installation.
As per standard construction the correct installation of Armstrong control valve shall be done with flow
direction that opens the plug (flow under the seat) and valve should be mounted on horizontal
pipeline with actuator oriented on top of piping as shown.
However, different installations are possible due to special process cases or skid design but
manufacturer shall be informed during quotation stage to include correct accessories and orientation
needed.