SecondStageCarrierDisassembly
1. Drive dowel pin (2G) completely into
planet shaft (2E). If pin is not driven
commpletely into planet shaft,
damage to the carrier couls result
when the shaft is removed.
2. Drive planet shaft (2E) down out of
carrier housing (2A).
3. When shaft is driven out of carrier
housing, two thrust washers (2B),
one planet gear (2F), and two more
thrust washers (2B) will come off of
planet shaft (2E). Set these parts
aside.
4. Using an alignment punch, drive
dowel pins (2G) out of planet shaft
(2E).
5. Remove the 18 needle bearings
(2C0 from one side of planet gear
(2F).
6. Remove spacer (2D) from inside
planet gear (2F).
7. Remove the remaining needle
bearings (2C) from inside planet
gear (2F).
8. Repeat steps 1 to 7 to remove and
disassemble the two remaining
planet gears.
9. Atthispoint,thesecondstagecarrier
disassembly is complete.
First Stage Carrier Disassembly
1. Drive dowel pin (3D) completely into
planet shaft (3E). If pin is not driven
completely into planet shaft, damage
to the carrier could result when the
shaft is removed.
2. Drive planet shaft (3E) down out of
carrier housing (3A).
3. When shaft is driven out of carrier
housing, two thrust washers (3B),
one planet gear (3F), and two more
thrust washers (3B) will come off of
planet shaft (3E). Set these parts
aside.
4. Using an alignment punch, drive
dowel pin (3D) out of planet shaft
(3E).
5. Remove the 19 needle rollers (3C)
from planet gear (3F).
6. Repeat steps 1 to 5 to remove and
disassemble the two remaining
planet gears.
7. At this point, the first stage carrier
disassembly is complete.