6
tions. Glen Dimplex accepts no responsibility for the deterioration of surfaces of finish-
es. It is usually convenient to carry thesame material right up to the ceiling level. At
the lower edge, drill (4.5mm diameter) holes into the metal support angle through the holes in
the top flange of the shielding box and fasten with the self threading screws provided. The side
cladding of the enclosure may be Gib board or any other wall cladding material. You
must leave the cladding off at least one side until the flue system has been installed.
7. For heat sensitive floors, construct an insulating floor protector of the shape shown in the
Floor Plan (Fig.2). (see below for concrete floors). The standard insulating floor protector is
constructed of two layers of 16mm thick MICORE 160 or three layers of 12.5mm thick
MICORE 300 or one layer of WOODTEX 35mm thick, topped with a 6mm sheet of Hardies
TILE & SLATE UNDERLAY and a layer of tiles or slate. This will give a thickness of approxi-
mately 50mm, and the extension from the face of the front cladding must be at least 525mm.
The floor protector must be at least 1025mm wide. It is desirable to carry the floor protector all
the way inside the enclosure to ensure that the bottom of the shielding box does not rest below
the top surface of the floor protector.
8. Note: For elevated installations (bottom of the shielding box rails at least 300mm above floor
level), the floor protector (min. size: 305mm from cladding x 1025mm wide) may be installed
after the appliance is in position as it does not extend into the enclosure. However, its rear
edge must butt up against the face of the heat-proof front cladding below the appliance, and
the joint at that point must be sealed to prevent the possibility of ember penetration. In this
case an ash floor protector is sufficient. Construction requirements for an ash floor protector
are: one sheet of 6mm fibre cement board (e.g. Hardies TILE & SLATE UNDERLAY) covered
with ceramic tiles or slate.
9. Cement tiles or slate to the top of the floor protector. The part inside the enclosure will not be
visible and therefore does not need complete coverage. It is necessary to fix the finishing layer
only under the support rails in this area. The visible edges of the floor protector are best fin-
ished with wooden trim or tiles after the stove has been installed.
10. Penetrate the roofing material on the flue centerline. Working from the bottom, assemble sec-
tions of the flue pipe and the inner and outer casings and pass them up through the hole in the
roof. Remember the flue pipe sections must be fixed together at each joint with at least three
monel or stainless steel fasteners, and the crimped ends of the flue casings go to the top. The
joints of the flue pipes must be sealed with an appropriate fire proof sealant. When the flue
system is in its final position, the top of the outer casings must be above the ridge line or roof
as follows: If the flue centerline is within 3m from the ridge, the outer casing must end at least
600mm above the ridge. If it is further than 3m from the ridge, the outer casing must extend at
least 1000mm above the point of roof penetration. In some cases where there are trees or high
buildings in the vicinity, it may be necessary to increase the height to avoid down-draughts.
You need to temporary support the flue system so that you can install the appliance.
11. Assemble thebase, sides, back, top shield assembly and top panel of the shielding box.
The top shield rests on the top edges of the inner heat shields of the cabinet. Make sure the
back flange hooks over the shield on the rear panel (See Fig. 3).
12. Attach the two standoff brackets to the sides of the shielding box panels (if not already fitted).
Use four pop rivets for each bracket.
13. Slide the assembly into place in the enclosure. After centralizing, fix the flange of the
top panel of the shielding box through the cladding into the metal angle support. Use 2/ 12g x
25mm screws.
14. The special adapter spigot ring with holes to ventilate the space between the flue and
the inner casing as well as the space between the inner casing and the outer casing has to be
attached with 4 screws 8g x 13mm to the top of the shielding box. Both flue casings (inner &
outer) will engage with this special adapter spigot ring.
15. In New Zealand and some parts of Australia, Standards require that the appliance be seismic
restraint to prevent shifting in the event of an earthquake. To provide seismic restraint, fix the
shielding box to the floor (bearers in an elevated installation) with two 6mm masonry
anchors (DYNABOLTS) or two 12 gauge screws . Use the two holes in the bottom of the
shielding box spaced 760mm apart.
16. Now go to the firebox cabinet and remove the two retaining screws and slide out the top sec-