YORK INTERNATIONAL
12
FORM 150.62-NM7 (103)
Hand stop valves should be installed in all lines to fa-
cilitate servicing.
Piping to the inlet and outlet connections of the chiller
should include high-pressure rubber hose or piping
loops to ensure against transmission of water pump
vibration.The necessarycomponents mustbeobtained
in the field.
Drain connections should be provided at all low points
to permit complete drainage of the cooler and system
water piping.
Asmallvalveor valvesshould beinstalled atthe highest
point or points in the chilled water piping to allow any
trapped air to be purged. Vent and drain connections
shouldbe extendedbeyondthe insulationto makethem
accessible.
The piping to and from the cooler must be designed
to suit the individual installation. It is important that the
following considerations be observed:
1. The chilled liquid piping system should be laid out
so that the circulating pump discharges directly
into the cooler. The suction for this pump should
be taken from the piping system return line and not
the cooler. This piping scheme is recommended,
but is not mandatory.
2. The inlet and outlet cooler connection sizes are
3" (YCAL0043 - 0073), 4" (YCAL0087 - 0107), 6"
(YCAL0117 - 0253), or 8" (YCAL0287 - 0377) .
3. A strainer, preferably 40 mesh, must be installed
in the cooler inlet line just ahead of the cooler. This
is important to protect the cooler from entrance of
large particles which could cause damage to the
evaporator.
4. Allchilledliquid pipingshould be thoroughlyflushed
to free it from foreign material before the system
is placed into operation. Use care not to flush any
foreign material into or through the cooler.
5. As an aid to servicing, thermometers and pressure
gauges should be installed in the inlet and outlet
water lines.
6. The chilled water lines that are exposed to outdoor
ambients should be wrapped with supplemental
heater cable and insulated to protect against
freeze-up during low ambient periods, and to pre-
vent formation of condensation on lines in warm
humid locations.
7. Achilled water flow switch, (either by YORK or oth-
ers)MUSTbeinstalledintheleavingwaterpipingof
thecooler.There shouldbe a straighthorizontal run
of at least 5 diameters on each side of the switch.
Adjust the flow switch paddle to the size of the pipe
in which it is to be installed. (See manufacturer’s
instructions furnished with the switch.) The switch
is to be wired to terminals 13 - 14 of CTB1 located
in the control panel, as shown on the unit wiring
diagram.
WIRING
Liquid Chillers are shipped with all factory-mounted
controls wired for operation.
Field Wiring – Power wiringmustbe providedthrough
a fused disconnect switch to the unit terminals (or op-
tional molded disconnect switch) in accordance with
N.E.C. or local code requirements. Minimum circuit
ampacity and maximum dual element fuse size are
given in the Tables 2 – 6.
A 120-1-60, 15 amp source must be supplied for the
controlpanel throughafused disconnectwhen acontrol
panel transformer (optional) is not provided. Refer to
Table 1 and Figures 2 - 6.
See Figures 2 - 6 and unit wiring diagrams for field and
power wiring connections, chilled water pump starter
contacts, alarm contacts, compressor run status con-
tacts,PWMinput, andloadlimitinput. Refertosectionon
UNITOPERATIONforadetaileddescription ofoperation
concerning aforementioned contacts and inputs.
Installation
The Flow Switch MUST NOT be used
to start and stop the chiller (i.e. start-
ing and stopping the chilled water
pump). It is intended only as a safety
switch.