
IOM 108-B00: Page 10/12
MAINTENANCE
4. Inspect both sleeve bearings (24) for damage or wear. If
damaged, bearings MUST be replaced.
On SMVP50C/100C models: if the inside diameter of the
bearing measures 1.196" (30.38mm) or greater at any
point around the entire circumference, bearings MUST be
replaced.
On SMVP200C/300C models: if the inside diameter of the
bearing measures 1.765" (44.83mm) or greater at any
point around the entire circumference, bearings MUST be
replaced.
To replace bearings:
a. Using an appropriately sized arbor press, remove the
old bearing from the head.
b. To aid installation and prevent damage, heat the head
in an oven to 200°F (93°C).
c. Coat the new bearing with a quality grade of bearing
grease, and place it on the inside face of the head with
the notched end UP. Align the notch in the bearing
with the groove in the head.
d. Using an arbor press, CAREFULLY press the bearing
into the head until it is flush with the inside face of the
head. Ensure that the bearing does not become
misaligned during the pressing activity.
e. On SMVP200C/300C models, lightly grease the inner
head O-ring (72A) using a silicone base O-ring
lubricant. Install into the O-ring recess on the inside
face of the head. The grease will hold the O-ring in
place during head installation.
4. Install the outboard head and bearing assembly (23) on
the pump cylinder with the V-notch down, towards the
bottom of the cylinder. Use the head dowel pins for proper
alignment.
5. For SMVP Models lubricate the eight outboard head
capscrews (21A) with a quality grade of anti-seize
compound and install, torquing to 15 lbs-ft(20.3Nm).
7. Install a new bearing cover O-ring / seal ring (26) in the
groove in the outboard head / bearing cover. Place the
bearing cover (27) on the head.
For SMVP Models lubricate the bearing cover capscrews
(28) with a quality grade of anti-seize compound, and
install, torquing to 15 lbs-ft(20.3Nm).
8. Turn the pump cylinder / casing over so that it rests on the
just installed outboard head and bearing cover.
9. Remove the six vanes (14) and three push rods (77) from
the rotor assembly. Inspect for wear and damage, and
replace as follows:
a. The push rods MUST be installed before installing the
rotor and shaft (13) into the pump cylinder / casing. To
do so, hold the rotor and shaft vertical, with the non-
driven (shorter end) down. Slide the push rods into the
push rod holes of the rotor, then insert the rotor and
shaft into the open end of the pump cylinder / casing.
b. Insert new vanes into the rotor slots with the rounded
edges outward, and the vane relief grooves facing
TOWARDS the direction of rotation. Refer back to
Figure 3. If necessary, move the push rods with a
small screwdriver to install the vanes.
10. Install the inboard disc (71), head seal ring / O-ring (72),
and sleeve (24) bearing as instructed in steps 2 through 4
above.
11. Install the inboard head and bearing assembly (20) on the
pump cylinder / casing with the V-notch down, towards the
bottom of the cylinder / casing. Use the head dowel pins
for proper alignment.
12. For SMVP Models lubricate the eight inboard head
capscrews (21) with a quality grade of anti-seize
compound, and install, torquing to 15 lbs ft (20.3Nm).
RELIEF VALVE ASSEMBLY (If Equipped)
1. Insert the valve (9) into the relief valve bore of the casing
with the fluted end inward.
2. Install the relief valve spring (8) and spring guide (7)
against the valve.
3. Attach a new relief valve O-ring (10) and the valve cover
(4) on the cylinder.
4. Screw the relief valve adjusting screw (2) with locknut (3)
into the valve cover (4) until it makes contact with the
spring guide (7). NOTICE:
The relief valve setting MUST be tested and adjusted more
precisely before putting the pump into service. Refer to
"Relief Valve Setting and Adjustment"
5. After the relief valve has been adjusted, tighten the
Locknut (3) and install the relief valve cap (1) and O-ring
(88)
MAGNET HOUSING ASSEMBLY
INNER MAGNET & PUMP ASSEMBLY
1. Install the shaft key (35) on the inboard shaft end.
2. Align the inner magnet (52) with the key, and slide the
magnet over the shaft with the pump end of the magnet
towards the inboard head.
3. Fully and squarely install the snap ring (83) into the
groove in the end of the shaft.
4. Place the impeller (52A) against the inner magnet.
Lubricate the impeller capscrews (52B) with anti-seize
compound. Attach the impeller to the magnet with the
capscrews and lockwashers (52B, 52C).
5. Check to ensure the pump shaft rotates freely when
turned by hand.
Install a new containment can O-ring (51) into the groove
provided on the hub of the inboard head (20). Slide the
containment can (50) over the magnet and push it firmly
against the inboard head.