6 OM-HY-6CAV
Immediately inspect the unit for external and internal damage when it is delivered.
Report any damage to the carrier. After inspection, keep the unit in its shipping
container until it is ready to be installed. The unit must be installed level. Level the unit
front to rear and left to right, by adjusting its feet. Check for levelness by using a spirit
level on top of the cabinet, and checking in both directions.
The HY-6SG Gas Model is suitable for installation on combustible and noncombustible
floors. Minimum installation clearances for the HY-6SG are:
Right Side 2 inches
Left Side 4 inches
Rear 6 inches
HY-6SE and HY-6SM models have no minimum clearance requirements, but room
should be provided so that the units may be serviced. The use of approved flexible
tubing and quick disconnect attachments will be helpful in allowing the unit to be
moved. For example, 24 inches right side clearance is needed for proper servicing,
unless the unit can be easily moved.
1. Electrical Supply Connection
A. On models HY-6SG and HY6-SE, power is supplied to cavity controls
and blower from the boiler base, and no other electrical connections are
required.
B. On model HY-6SM, you must provide 115 Volt Alternating Current, 60 Hz,
single phase, 15 AMP service. Local codes and/or the National Electrical
Code should be observed in accordance with ANSI/NFPA-70-1987 (or latest
edition). AN ELECTRICAL GROUND IS REQUIRED.
C. The electrical schematic is located in the electrical enclosure and in
this manual. In Canada provide electrical service in accordance with the
Canadian Electrical Code, CSA C22.1, Part 1 and/or local codes.
2. Water Supply Connection
A. Models HY-6SG and HY-6SE feature two separate water inlets – one for the
steam boiler (treated water), the other for the spray condenser (untreated
water). The second intake will reduce treatment requirements resulting in
significant savings.
B. For the HY-6SM, provide a 3/8” NPT pipe connection for untreated water
at the rear of the unit. A back siphonage device (check valve) must be
installed, complying with local plumbing codes. The water pressure should
be between 30 and 60 PSI (210 to 410 kPa). A pressure regulator is
required above 60 PSI (410 kPa).
C. The condenser spray uses 0.70 to 0.95 gallons of water per minute (2.6 to
3.6 liters per minute) at 30 to 60 PSI (210 and 410 kPa). The spray will only
operate when a steamer cavity (cooking chamber) is in operation.
WARNING
THE UNIT MUST BE INSTALLED BY
PERSONNEL WHO ARE QUALIFIED TO
WORK WITH ELECTRICITY AND PLUMBING.
IMPROPER INSTALLATION CAN CAUSE
INJURY TO PERSONNEL AND/OR DAMAGE TO
THE EQUIPMENT. THE UNIT MUST BE
INSTALLED IN ACCORDANCE WITH ALL
APPLICABLE CODES.
CAUTION
SHIPPING STRAPS ARE UNDER TENSION.
THEY CAN SNAP BACK VIOLENTLY AND
CAUSE INJURY WHEN CUT.
CAUTION
MAKING ELECTRICAL OR MECHANICAL
CHANGES TO THE UNIT WITHOUT APPROVAL
FROM THE GROEN FOOD SERVICE
ENGINEERING DEPARTMENT MAY VOID
WARRANTIES.
PLEASE REFER TO THE APPROPRIATE
OPERATOR MANUAL (OM-CNGB/3 OR OM-
CNEB/1) FOR MODELS HY-6SG AND HY-6SE
STEAM BOILER INSTALLATION.
Installation