Connections
NOTE
The electrical wiring between the air treatment
and water heater sections must be carried out
in accordance with the stipulations in force.
NOTE
Drain F750 of water if it was previously installed.
There may be some hot water when draining,
risk of scalding.
Separating and installing
1. Install some form of bracket to position the air
treatment section on. The air treatment section must
be positioned a maximum of 80 cm from the heater
section.
Check that the brackets can take the air treatment
section weight. Also check that the protective panel
can be installed under the air treatment section when
it has been mounted on the brackets.
2. Shut off the heat pump and turn off the current on
the safety breaker.
3. Open the heat pump front covers.
4. Remove the insulation at the immersion heater.
5. Remove the actuator for the reversing valve for the
climate control system/hot water heater(QN10).
6. Remove the top insulation.
TIP
See the heat pump installer handbook
for more detailed instructions.
7. Disconnect the wiring between the air treatment
section and the water heater section.
8. Disconnect the condensation hose from the air
treatment section and from the overflow cup.
9. Disconnect the pipe connections to the flow and re-
turn lines.
TIP
Lift the air treatment section slightly at
the front edge so that it is easier to ac-
cess the pipe connections. The air
treatment section is secured at the front
edge of the heat pump with two
screws.
10. Install the air treatment section on the brackets.
Caution
Take care not to damage the condensa-
tion water pipe on the air treatment
section.
9