2. Trim tubing to within 38 mm (1-1/2”) of the end
of the insulaon. If self regulang heat trace
proceed to step 3. For Zone-type heat trace
connue with idencaon of bus connecon
on step 2a.
1. Remove outer jacket and insulaon from tubing
bundle approximately 457 mm (18”) from end
of the tubing bundle.
457 mm
(18”)
Tubing
Bundle
TubeTrace
Heat Tracing
Heat Tracing
Trim Tubing
457 mm
(18”) Tubing
2a. Strip back bundle insulaon 38 mm (1 1/2”) to
76 mm (3”) beyond bus connecon indentaon
of each heat trace. If bus connecon indentaon
is less than 305 mm (12”)- 381 mm (15”) from
end of the heat tracing, proceed stripping the
bundle insulaon to the next indentaon.
38 mm
(1 1/2”)
Bus Connecon
Indentaons
Heat Tracing
305 mm-381 mm
(12”- 15”)
Heat Reecve
Tape
Tubing
Glass Fiber
Tape
4. Wrap tube and heat trace with 1 pass of
reecve tape (25% overlap), then wrap with 3
passes of glass ber tape (50% overlap), or unl
ber tape is equal to original bundle insulaon
thickness.
3. Make 90˚ elbow union connections (fitting
provided by others). Test ng for leaks before
proceeding.
90˚ Elbow Union Fing
(Provided by Others)
Terminator DP Cercaons/Approvals
The Terminator DP/FAK-2 and FAK-2L In-Line Splice Kit is designed
to make a waterproof seal over the end of TubeTrace at the splice
connecons. Review instrucons prior to installaon. Kit will make
one splice connecon (tube ngs not included). See separate
instrucons for details on splicing heat tracing.
IP66 NEMA/Type 4X -60°C ≤ Ta ≤ +55°C
Ordinary & Hazardous Locaons
Class I, Division 2, Groups A, B, C, & D, Zone 2 IIC
Class II, Division 2, Groups F & G, Class III
Listed Heat Tracing System 137M
Installaon Precauons
• To minimize the potenal for arcing and ground-fault protecon.
The Naonal Electrical Code (NEC) and Canadian Electrical Code
(CEC) require ground-fault protecon of equipment for each
branch circuit supplying electric heat tracing.
• Installaon must comply with Thermon requirements and
be installed in accordance with the NEC, CEC, or any other
applicable naonal and local codes.
• Component approvals and performance rangs are based on
the use of Thermon specied parts only. User supplied power
connecon ngs must be listed or cered for intended use.
• De-energize all power sources before opening enclosure.
• Keep ends of heang cable and kit components dry before and
during installaon.
• Individuals installing these products are responsible for
complying with all applicable safety and health guidelines.
Proper personal protecve equipment, or PPE, should be
ulized during installaon. Contact Thermon if you have any
addional quesons.
5. Complete with additional passes of heat
reecve tape.
Heat Reecve
Tape
CAUTION (Found on TubeTrace SE/ME bundles)
Do not cut or damage the heat