TS4-A-O/S/M with TAP and CCA
Quick Start Guide
Install a CCA Requires Ethernet or WiFi internet access. One CCA can communicate with up to 7 TAPs and up to 900 TS4s.
1. Mount the CCA within a NEMA 1 (indoors) or NEMA 4 (outdoors) enclosure.
2. Connect TAP wires to the CCA GATEWAY port.
3. Connect a Tigo or 3rd-party power supply with 24VDC output.
• The CCA must be on the same AC branch circuit as the inverter.
• Rapid shutdown occurs when an AC disconnect (inverter or switch) disconnects power to the CCA/TAP.
• Make all connections to TAPs before powering on the CCA.
DIN-rail
power supply
External
power supply
CCA LED Status Indicator
LED Activity State Description
Solid green System OK The system is operating normally.
Blinking green/gray EI app activity The CCA is connected to the Tigo mobile EI app.
Blinking green/yellow User PV-O The PV-O mode was manually activated.
Blinking yellow/gray Discovery The CCA is scanning for TAPs/TS4s.
Solid yellow Warning Scanning is incomplete or the CCA cannot connect to the Tigo server.
Blinking red/yellow Auto PV-O The PV-O mode was automatically activated.
Solid red Error The CCA cannot nd all TS4s or cannot connect to the Tigo server.
Locate the TAP centrally in an array.
10m (33ft) max 10m (33ft) max
35m (115ft) max
Connect the TAP and CCA using 4-wire or CAT5/6 cables.
– + B A
Install a TAP One TAP can communicate with up to 300 TS4s.
• Ensure the TAP is within 10m (33ft) of a TS4.
• Ensure the cable glands of the NEMA 4 TAP face down and
cannot collect moisture.
• Make all TAP connections to the CCA before powering on the CCA.
TAP
Top
Specications and Additional PVRSS UL 1741 Compliance Requirements
Model Max Power Max Input V Max Input A Max System Voltage1
TS4-A-O 700W 80V 15A 1000V/1500V
TS4-A-S 700W 80V 15A 1000V/1500V
TS4-A-M2500W 90V 15A 1000V/1500V
TS4 PV conductors are 12 AWG.
The combination of TS4-A-O/S with TAP and CCA is certied as a UL 1741 photovoltaic rapid shutdown system
(PVRSS) within a rapid shutdown time limit of 30s. The CCA data logger/gateway (P/N 346-00000-00) is powered
from the same AC circuit as the rapid shutdown initiator (RSI) circuit. It provides a keep-alive signal to TS4 MLPE
via a wired connection to a TAP and a wireless connection between the TAP and TS4s.
The installer must install signage complying with Section 690.56(C) of NEC NFPA 70 and indicating whether all
conductors are controlled, or only conductors leaving the footprint of the array are controlled.
IT IS THE RESPONSIBILITY OF THE INSTALLER TO ENSURE THAT THE COMPLETED PV SYSTEM MEETS RAPID
SHUT DOWN FUNCTIONAL REQUIREMENTS.
Modules must not be installed in readily accessible locations (Canada only).
Connectors from dierent manufacturers cannot be mated with each other.
1Depending on connection method.
2Not a rapid shutdown system (PVRSS) component.
Testing/Commissioning
Download the Tigo Energy Intelligence (EI) mobile app to test and commission all TS4/TAP/CCA components. To
remove a CCA post-commissioning, contact Tigo Support.
Resources
Tigo Energy, Inc.
655 Campbell Technology Pkwy.
Campbell, CA 95008
+1 408 402 0802
Help Center
www.tigoenergy.com
LED status
indicator
• All PVRSE components must be installed and
maintained by qualied personnel in accordance with
applicable electrical codes and instructions in the
TS4-A with CCA and TAP Installation Manual.
• Improper installation may cause damage not covered
by the warranty.
• Adhere to ANSI/NFPA 70 (North America) and local
electrical code requirements.
Wire schedule:
• Shielded if running
next to PV conductors
• 20 – 18 AWG or CAT5/6
twisted pairs
• Solid core
• Cable outside diameter (OD)
≤9mm (.35in)
Cable glands