6
Installation
Before installing this device, turn off, tag/lock out power to the system, including console and submersible pumps.
Remove the dispenser’s lower sheet metal doors to access the vapor plumbing.
Prior to modifying any piping in the dispenser, consult the dispenser manufacturer to
determine if ISD ready retrofit kits are available. Any factory installed plumbing that must be
modified in order to install the VFM, must be removed to a non hazardous work area before
any cutting or threading takes place. After modifications to any plumbing, it must be
reinstalled in accordance with the dispenser manufacturers installation guidelines.
Above Shear Valve Installs
1. Loosen any factory installed mounts and/or brackets in order to provide room to disconnect any factory
installed vapor return plumbing from the shear valve.
2. Disconnect the factory installed vapor return plumbing from the vapor shear valve (see Figure 1).
3. Remove any unneeded field installed plumbing above the vapor shear valve. The Vapor Flow Meter with
flanges attached can be used for sizing the required head space of approximately 8 inches. Approximately 3
inches of clearance is required on both sides of the piping to accommodate the width of the meter body.
4. Thread one of the flanges (two provided in installation kit) onto the dispenser vapor return piping.
5. Install any necessary plumbing and the lower flange above the vapor shear valve. The use of 90° elbows
should be kept to a minimum to minimize pressure drop, maximize vapor collection efficiency and to prevent
liquid traps. All horizontal plumbing must pitch to drain.
IMPORTANT! Upper and lower flanges must align to within 1/16” center-to-center before
installing flow meter. If piping is improperly aligned, torque could damage the flow meter and
result in vapor leakage.
6. Clean all debris around the inlet and outlet plumbing prior to installing the VFM. DO NOT blow compressed air
through the VFM to prevent damaging the internal screens.
7. Install the o-ring into the lower mounting flange.
8. Taking care that foreign material (chips, debris, sealant, etc.) does not enter the open piping or VFM, carefully
insert the o-ring and then connect the VFM to the upper flange. Note that the flow arrow on the side of the
meter body must point down.
9. Connect the lower flange to the VFM.
10. Tighten any loose fittings and hardware.
11. Install a cord grip from the kit into the I.S. junction box. Route the VFM cable into the I.S. junction box and
tighten the cord grip. Observing polarity, connect the VFM wiring to the field wiring from the TLS console with
wire nuts (see Figure 4). Seal wire nuts in epoxy sealant following the instructions in Figure 5.
For Wireless installations skip Steps 11 - 13. The VFM connects to a TLS RF transmitter, not
to field wiring from the TLS Console (see manual 577013-964 for instructions).
12. Push the epoxy sealed bag into the junction box. Replace and tighten the junction box cover.
13. Connect VFM field wiring in the TLS Console to the USM Module (TLS-450PLUS - Figure 6), or to the Smart
Sensor Module (TLS-3XX - Figure 7), as appropriate.
14. Replace the lower sheet metal doors in the dispenser
15. After all Vapor Flow Meters are installed, pressurize the tank ullage space and vapor piping to at least 2
inches WC and test piping connections for leaks using leak detection solution.