actionair DWFX-F User manual

INSTALLATION GUIDE
DWFX-F Installation Method
Health and safety
• This process must be undertaken by competent per-
sons. More than one person may be required to ensure
the safe handling of large dampers and other materi-
als. Use must be made of access equipment to ensure
unsafe practices are not used to approach walls or dif-
cult access areas.
• Standard site PPE should be used (minimum steel toe
cap boots, hard hat); together with any protective
eyewear, gloves and masks, when drilling or cutting is
being undertaken. The latter should also be used when
handing the wall construction materials, as dened by
the material suppliers. If loud equipment is being used,
hearing protection should be used.
• All waste materials should be collected and disposed of
as dened by the relevant supplier.
• Actuators: All wiring should be carried out in accor-
dance with the wiring details provided by the IEE and
BS regulations and by a competent person. Care must
be taken when installing and inspecting dampers, as
they are likely to close without warning due to loss of
electrical power or a temperature rise in the ductwork.
This is their prime function. Do not insert any items,
ngers or limbs between the blades. Larger dampers
must be handled in accordance with current regula-
tions and good practice due to weight.
Drawings
Please visit our website to download the installation dra-
wings, which are located on the relevant product down-
load section.
Applies to...
• Actionair SmokeShield PTC
• Actionair FireShield
Contents
Drawings ............................................. 1
Applies to............................................. 1
Health and safety .................................. 1
CE Installation Method Overview ............... 2
Vertical Damper Installation in Plasterboard
Walls...................................................3
Vertical Damper, Alblative Batt in a
Plasterboard Wall...................................4
Vertical Damper Installation (Top Flange
removed) in a Plasterboard Wall under
Concrete Slab........................................5
Vertical Damper Installation in Masonry Walls
6
Vertical Damper, Ablative Batt in Masonry
Walls................................................... 7
Vertical Damper (with a Pattress) in a
Masonry Wall ........................................8
Vertical Damper in a Masonry Wall against
slab ....................................................9
Periodic maintenance.............................10
Actuators............................................ 11
Control Mode Installation Procedure .............................11
Wiring Diagrams .......................................................... 12
DWFX-F Damper Dimensional Data............13
Actionair SmokeShield PTC .......................................... 13
Actionair FireShield ...................................................... 15
Inspection and handover check sheet.........16

Actionair DWFX-F Installation Guide
2Swegon reserves the right to alter specications. 20210408 - LNNN00354 (3.0)
Application
Installation Method
Actionair SmokeShield Actionair FireShield
Vertical DWFX-F In A Plasterboard
Wall
Page 3, [AA/F13069]
Page 3, [AA/F10704]
Page 3, [AA/F10705]
Vertical DWFX-F, Ablative Batt In A
Plasterboard Wall
Page 4, [AA/F10710] Page 4, [AA/F10711]
Vertical DWFX-3F (Top Flange Remo-
ved) In A Plasterboard Wall Under
Concrete Slab
Page 5, [AA/F11945] Page 5, [AA/F11944]
Vertical DWFX-F In A Masonry Wall Page 6, [AA/F10706] Page 6, [AA/F10707]
Vertical DWFX-F, Ablative Batt In A
Masonry Wall
Page 7, [AA/F10712] Page 7, [AA/F10713]
Vertical DWFX-F, In A Masonry Wall
With Pattress
Page 8, [AA/F12493] N/A
Vertical DWFX-3F (Top Flange Remo-
ved) In A Masonry Wall Under Con-
crete Slab
Page 9, [AA/F12394] Page 9, [AA/F12827]
• The methods in this manual should be followed to
ensure a CE-marked installation. This CE installation
document covers single dampers only. If a multiple
damper assembly or, if a non-standard install is requi-
red, talk to us as early as possible in the project to get
important stakeholders engaged and ensure an instal-
lation solution can be found.
• The instructions are based on the tested method using
Actionair Smoke Shield PTC re/smoke dampers and
Firetherm products.
• Our SmokeShield dampers are designed to be used
with re separating elements to maintain re compart-
ments. The SmokeShield is an actuated failsafe close
damper with low smoke leakage, often referred to in
the industry as a Fire/Smoke damper.
• Under the Fire Damper Product standard BS EN 15650
our Fire Damper products are tested to BS EN 1366-2
and classied under BS EN 13501-3.
• Notied body - BRE Global
• Test report P112628-1006 (Vertical Test) P112628-1014
(Actuator in Horizontal test) P112628-1015 (Actuator
out Horizontal Test)
• For smoke control, the product you use should be
tested to BS EN 1366-10 and drive open, drive closed
without failsafe position, see our website for informa-
tion on the Actionair SmokeCommand smoke con-
trol damper documentation and suitable installation
methods.
CE Installation Method Overview

3
20210408 - LNNN00354 (3.0) Swegon reserves the right to alter specications.
Actionair DWFX-F Installation Guide
Vertical Damper Installation in a
Plasterboard Wall
Actionair SmokeShield PTC - [AA/F13069], [AA/F10704]
Actionair FireShield - [AA/F10705]
Installation Method
1. Measure the overall Fire damper casing size w x h, but
for Smoke Shield include the PTC Shroud (28mm) in
the width but do not include any of the peripheral
ange.
2. Calculate the hole size...
3. For Fire Shield calculate the nished hole size by adding
10-40mm to the case width and height.
4. For Smoke Shield calculate the nished hole size adding
10-52mm to the width and 10-40mm to the height.
5. Calculate the hole to cut size by adding two board
thicknesses to the nished hole width and height.
6. Mark out the hole on the partition and cut it out, cut-
ting the top and bottom edges rst to maintain stabi-
lity.
7. Frame out the hole with stud and track and cover this
with board. Finish edges with joint ller.
8. Drill clearance holes in the damper ange at 150mm
centres and such that they will allow screws to pull into
the stud and track around the hole.
9. Install the damper and fasten.
10. Back ll with mineral/stone wool and pattress over
this down to the spigot. Fasten with drywall screws at
Comments:
Rev:
Drawn By:
M.Bushell
Approved By:
A. Hill
1 of 1
Reference No:
S. Gore
Date:
Date:
By: Date:
10/02/2020
28/01/2020
10/02/2020
Date:
A
Checked By:
Sheet Rev
AAF13069
Description:
If your proposed installation details differ from
that shown here, please discuss this with the
Building Control Authority (BCA), referencing
this documentation, associated fire tests,
assessments, and other documentation shown
below. Deviation from this drawing requires
the approval of the relevant authority.
Installation Detail
Connecting ductwork omitted for clarity.
Ductwork must be independently supported.
There must be an appropriate break-away joint
between the damper and connecting ductwork
on both sides of assembly. Aluminium rivets or
plastic cleats, clips, clamps and bolts etc.
should be used for this, unless fire resisting
ductwork is being used where fire resisting
fixings should be used. A minimum of 200mm
between fire dampers installed in separate
ducts and 75mm between fire damper and a
construction element (wall/floor).
³
³
Applicable Test Report to
BS EN1366-2:
P112628-1011
BRE 256493
MINUTESES 120
Fire Resistance Integrity
and Leakage
AECN1975 MJB 10-02-20
Damper Size Range (mm)
VERTICAL APPLICATION
SMOKE SHIELD DWFX-F
IN PLASTERBOARD WALL,
OPTION 2
200 x 200 to 1000 x 1000
©Swegon Air Management Limited
South Street, Whitstable, Kent CT5 3DU
Tel: +44 (0)1227 276100
Fax: +44 (0)1227 264262
www.swegonair.co.uk
300mm centres such that they will allow screws to pull
into the stud and track around the hole.
11. Connecting ductwork omitted for clarity. Ductwork
must be independently supported. There must be an
appropriate break-away joint between the damper and
connecting ductwork on both sides of assembly. Alu-
minium rivets or plastic cleats, clips, clamps and bolts
etc. should be used for this, unless re resisting duct-
work is being used where re resisting xings should
be used. A minimum of 200 mm between re dam-
pers installed in separate ducts and 75 mm between
re damper and a construction element (wall/oor).
12. Alternative partition systems to those shown within
this installation manual can be used if they have been
shown by test to have at least the same re resistance
when tested to BS EN 1364-1:1999 as is required of
the damper. If the partition system has been success-
fully tested without stone mineral wool it does not
have to be used in practice when only considering the
re performance of the complete system. The mineral
wool may still be needed for other reasons e.g. acous-
tic performance.
13. For SmokeShield installations, please reference the
actuator installation information on page 11.

Actionair DWFX-F Installation Guide
4Swegon reserves the right to alter specications. 20210408 - LNNN00354 (3.0)
Vertical Damper, Alblative Batt in a
Plasterboard Wall
Actionair SmokeShield PTC - [AA/F10710]
Actionair FireShield - [AA/F10711]
Installation Method
1. Mark out the hole on the partition and cut it out, cut-
ting the top and bottom edges rst to maintain stabi-
lity.
2. Frame out the hole with stud and track and cover this
with 2 layers of board. Finish edges with joint ller.
3. Rivet steel duct (by others) to damper spigot on non-
access side, using steel rivets.
4. Suspend the damper from the ceiling, using 10mm
studding drop rods, and support the damper from
lateral movement.
5. Make sure the area within the aperture and the
damper casing is free from any debris and remove any
dust.
6. Where the coated BATT will contact the surrounding
aperture apply Rockwool Fire pro glue to the outer
edges of the BATT. Where two coated BATTS are in
contact use Rockwool re pro glue as the joint adhe-
sive. In both cases ensure that an even cover is achie-
ved over the entire thickness of the BATT.
7. Continue installation of Rockwool ablative coated
BATT, until aperture is completely lled.
8. Apply a bead of Rockwool acoustic intumescent sealant
Comments:
Rev:
Drawn By:
S.Wehrle
Approved By:
N.Harris
1 of 1
Reference No:
S.Gore
Date:
Date:
By: Date:
13/04/18
15/07/10
13/04/18
Date:
G
Checked By:
Sheet Rev
AAF10710
Description:
If your proposed installation details
differ from that shown here, please
discuss this with the Building Control Authority
(BCA), referencing this documentation,
associated fire tests, assessments, and other
documentation shown below. Deviation from
this drawing requires the approval of the
relevant authority.
Installation Detail
Connecting ductwork omitted for clarity.
Ductwork must be independently supported.
There must be an appropriate break-away
joint between the damper and connecting
ductwork on both sides of assembly.
Aluminium rivets or plastic cleats, clips,
clamps and bolts etc. should be used for this,
unless fire resisting ductwork is being used
where fire resisting fixings should be used. A
minimum of 200 mm between fire dampers
installed in separate ducts and 75 mm
between fire damper and a construction
element (wall/floor).
³
IF YOUR PROPOSED
INSTALLATION DETAIL DIFFERS
FROM THAT SHOWN, YOU MUST
DISCUSS THIS WITH THE
BUILDING CONTROL AUTHORITY
(BCA), REFERENCING THIS
DOCUMENT AND THE
ASSOCIATED FIRE TESTS,
ASSESSMENTS AND OTHER
DOCUMENTS SHOWN BELOW.
DEVIATION FROM THIS DRAWING
REQUIRES THE APPROVAL OF
THE RELEVANT AUTHORITY.
©Swegon Air Management Limited
South Street, Whitstable, Kent CT5 3DU
Tel: +44 (0)1227 276100
Fax: +44 (0)1227 264262
www.swegonair.co.uk
Applicable Test Report to
BS EN1366-2:
BRE 267924
MINUTESES 120
Fire Resistance
Integrity and Leakage
EEC1770 MJB 20-02-18
Damper Size Range (mm)
VERTICAL APPLICATION
SMOKE SHIELD + DWFX-F &
ABLATIVE BATT
200 x 200 to 1000 x 1000
VERTICAL BLADES;
DAMPER CAN BE INSTALLED WITH THE
BLADES IN THE VERTICAL ORIENTATION
WITH THE ACTUATOR MOUNTED AT
EITHER THE TOP OR BOTTOM.
FEC1830 RTC 20/03/18
G EC1839 RTC 13/04/18
to both sides of the wall, approximately 15mm wide,
around the perimeter of the aperture between dry wall
and BATT, ensuring that any gaps between the BATT
and surrounding edges are fully lled.
9. Allow 12 hours for BATT penetration seal to cure prior
to removing any lateral damper supports.
10. Alternative partition systems to those shown within
this installation manual can be used if they have been
shown by test to have at least the same re resistance
when tested to BS EN 1364-1:1999 as is required of
the damper. If the partition system has been success-
fully tested without stone mineral wool it does not
have to be used in practice when only considering the
re performance of the complete system. The mineral
wool may still be needed for other reasons e.g. acous-
tic performance.
11. Connecting ductwork omitted for clarity. Ductwork
must be independently supported. There must be an
appropriate break-away joint between the damper and
connecting ductwork on both sides of assembly. Alu-
minium rivets or plastic cleats, clips, clamps and bolts
etc. should be used for this, unless re resisting duct-
work is being used where re resisting xings should
be used. A minimum of 200 mm between re dampers
installed in separate ducts and 75 mm between re
damper and a construction element (wall/oor).
12. For SmokeShield installations, please reference the
actuator installation information on page 11.

5
20210408 - LNNN00354 (3.0) Swegon reserves the right to alter specications.
Actionair DWFX-F Installation Guide
Vertical Damper Installation (Top
Flange removed) in a Plasterboard
Wall under Concrete Slab
Actionair SmokeShield PTC - [AA/F11945]
Actionair FireShield - [AA/F 11944]
Installation Method
1. Measure the overall Fire damper casing size w x h, but
for Smoke Shield include the PTC Shroud (28mm) in
the width but do not include any of the peripheral
ange.
2. Calculate the hole size...
3. For Fire Shield calculate the nished hole size by adding
10-60mm to the case width and 5-30mm for the
height as the head of the damper will be against the
slab.
4. For Smoke Shield calculate the nished hole size adding
10-57mm to the width and 10-30mm to the height as
the head of the damper will be against the slab.
5. Calculate the hole to cut size by adding two board
thicknesses to the nished hole width and only one for
the height.
6. Mark out the hole on the partition and cut it out.
7. Frame out the hole sides and bottom with stud and
track and cover this with board. Finish edges with joint
ller.
8. Drill clearance holes in the three damper ange sides at
150mm centres and such that they will allow screws to
pull into the stud and track around the hole.
9. Apply a bead of low pressure intumescent mastic
along top edge of damper as a gap ller and Install the
damper and fasten.
10. Back ll with mineral/stone wool and pattress over
this down to the spigot. Fasten with drywall screws
at 300mm centres on the sides and bottom such that
they will allow screws to pull into the stud and track
around the hole. Fix the top pattress into the track at
the sides.
11. Connecting ductwork omitted for clarity. Ductwork
must be independently supported. There must be an
appropriate break-away joint between the damper and
connecting ductwork on both sides of assembly. Alu-
minium rivets or plastic cleats, clips, clamps and bolts
etc. should be used for this, unless re resisting duct-
work is being used where re resisting xings should
be used. A minimum separation of 200 mm between
re dampers installed in separate ducts and 75mm bet-
ween re damper and a construction element (ie wall/
oor) unless otherwise tested.
12. Alternative partition systems to those shown within
this installation manual can be used if they have been
shown by test to have at least the same re resistance
when tested to BS EN 1364-1:1999 as is required of
the damper. If the partition system has been success-
fully tested without stone mineral wool it does not
have to be used in practice when only considering the
re performance of the complete system. The mineral
wool may still be needed for other reasons e.g. acous-
tic performance.
13. For SmokeShield installations, please reference the
actuator installation information on page 11.
Comments:
Rev:
Drawn By:
S.Wehrle
Approved By:
A. Hill
1 of 2
Reference No:
S. Gore
Date:
Date:
By: Date:
01/07/2019
07/11/2016
01/07/2019
Date:
F
Checked By:
Sheet Rev
AAF11945
Description:
If your proposed installation details differ from
that shown here, please discuss this with the
Building Control Authority (BCA), referencing
this documentation, associated fire tests,
assessments, and other documentation shown
below. Deviation from this drawing requires
the approval of the relevant authority.
Installation Detail
Connecting ductwork omitted for clarity.
Ductwork must be independently supported.
There must be an appropriate break-away
joint between the damper and connecting
ductwork on both sides of assembly.
Aluminium rivets or plastic cleats, clips,
clamps and bolts etc. should be used for this,
unless fire resisting ductwork is being used
where fire resisting fixings should be used. A
minimum of 200 mm construction element
(wall) between fire dampers installed in
separate ducts and 75 mm between fire
damper and a construction element (wall).
³
IF YOUR PROPOSED
INSTALLATION DETAIL DIFFERS
FROM THAT SHOWN, YOU MUST
DISCUSS THIS WITH THE
BUILDING CONTROL AUTHORITY
(BCA), REFERENCING THIS
DOCUMENT AND THE
ASSOCIATED FIRE TESTS,
ASSESSMENTS AND OTHER
DOCUMENTS SHOWN BELOW.
DEVIATION FROM THIS DRAWING
REQUIRES THE APPROVAL OF
THE RELEVANT AUTHORITY.
©Swegon Air Management Limited
South Street, Whitstable, Kent CT5 3DU
Tel: +44 (0)1227 276100
Fax: +44 (0)1227 264262
www.swegonair.co.uk
Applicable Test Report to
BS EN1366-2:
WF388114
MINUTESES 120
Fire Resistance Integrity
and Leakage
AECN1770 MJB 20-02-18
Damper Size Range (mm)
VERTICAL APPLICATION
SMOKE SHIELD DWFX-F IN
PLASTERBOARD WALL
AGAINST SLAB
200 x 200 to 1000 x 1000
VERTICAL BLADES
Damper can be installed with the
blades in the vertical orientation
with the actuator mounted at the
bottom. For cleat locations of
motors mounted on the bottom
refer to drawing
³
BECN1820 MJB 06-03-18
C ECN1821 N.H 08/03/18
DECN1922 MJB 12-04-19
EECN1928 MJB 14-05-19
FECN1936 MJB 01-07-19

Actionair DWFX-F Installation Guide
6Swegon reserves the right to alter specications. 20210408 - LNNN00354 (3.0)
Vertical Damper Installation in
a Masonry Wall
Actionair SmokeShield PTC - [AA/F10706]
Actionair FireShield - [AA/F10707]
Installation Method
1. Drill clearance holes in the damper ange at 150mm
centres.
2. Install the damper and x through ange using re
rated fasteners, min ø4mm.
3. Back ll between damper casing and wall, with mine-
ral/stone wool and secure in place with angle retaining
anges, xed in corners, or with Z shaped retaining
anges, to give the option of face xing onto wall.
Note: either angle or Z retaining anges to be supplied
by others.
4. Note: dampers supplied with cleats welded to top
ange to assist with installation only.
5. Connecting ductwork omitted for clarity. Ductwork
must be independently supported. There must be an
appropriate break-away joint between the damper and
connecting ductwork on both sides of assembly. Alu-
minium rivets or plastic cleats, clips, clamps and bolts
etc. should be used for this, unless re resisting duct-
work is being used where re resisting xings should
be used. A minimum of 200 mm between re dam-
pers installed in separate ducts and 75 mm between
re damper and a construction element (wall/oor).
6. Alternative partition systems to those shown within
this installation manual can be used if they have been
Comments:
Rev:
Drawn By:
swehrle
Approved By:
N. Harris
1 of 1
Reference No:
S. Gore
Date:
Date:
By: Date:
20/03/18
31/05/11
20/03/18
Date:
F
Checked By:
Sheet Rev
AAF10706
Description:
If your proposed installation details
differ from that shown here, please
discuss this with the Building Control Authority
(BCA), referencing this documentation,
associated fire tests, assessments, and other
documentation shown below. Deviation from
this drawing requires the approval of the
relevant authority.
Installation Detail
Connecting ductwork omitted for clarity.
Ductwork must be independently supported.
There must be an appropriate break-away
joint between the damper and connecting
ductwork on both sides of assembly.
Aluminium rivets or plastic cleats, clips,
clamps and bolts etc. should be used for this,
unless fire resisting ductwork is being used
where fire resisting fixings should be used. A
minimum of 200 mm between fire dampers
installed in separate ducts and 75 mm
between fire damper and a construction
element (wall/floor).
³
IF YOUR PROPOSED
INSTALLATION DETAIL DIFFERS
FROM THAT SHOWN, YOU MUST
DISCUSS THIS WITH THE
BUILDING CONTROL AUTHORITY
(BCA), REFERENCING THIS
DOCUMENT AND THE
ASSOCIATED FIRE TESTS,
ASSESSMENTS AND OTHER
DOCUMENTS SHOWN BELOW.
DEVIATION FROM THIS DRAWING
REQUIRES THE APPROVAL OF
THE RELEVANT AUTHORITY.
EXPLANATION:
2 Hour fire, smoke rating, & 2 hour fire integrity.
The damper must be installed in accordance with the manufacturer's
recommendations and HEVAC/HVCA publication HVC6/5/83 rev 1
APRIL 2002.
This solution has been assessed by BRE to BS476 PT 20 for 2 hours
and tested by BRE to BS-EN1366-2.
Acceptance of this solution must be sought by the system designer
(In writing) from the appropriate LA prior to installation.
Requirements for access openings for inspection and cleaning
purposes are provided in HVCA DW/144 specification for sheet metal
ductwork.
Access provision must be allowed to permit jointing of ducts to fire
damper. It may be necessary to install access doors on both sides of
the partition so that the ducts can be fitted from inside the damper.
©Swegon Air Management Limited
South Street, Whitstable, Kent CT5 3DU
Tel: +44 (0)1227 276100
Fax: +44 (0)1227 264262
www.swegonair.co.uk
Applicable Test Report to
BS EN1366-2:
BRE 256493
MINUTESES 120
Fire Resistance
Integrity and Leakage
EEC1770 MJB 20-02-18
Damper Size Range (mm)
VERTICAL APPLICATION
SMOKE SHIELD + DWFX-F
200 X 200 to 1000 x 1000
VERTICAL BLADES;
DAMPER CAN BE INSTALLED WITH
THE BLADES IN THE VERTICAL
ORIENTATION WITH THE ACTUATOR
MOUNTED AT EITHER THE TOP OR
BOTTOM.
FEC1830 RTC 20/03/18
shown by test to have at least the same re resistance
when tested to BS EN 1364-1:1999 as is required of
the damper. If the partition system has been success-
fully tested without stone mineral wool it does not
have to be used in practice when only considering the
re performance of the complete system. The mineral
wool may still be needed for other reasons e.g. acous-
tic performance.
7. For SmokeShield installations, please reference the
actuator installation information on page 11.

7
20210408 - LNNN00354 (3.0) Swegon reserves the right to alter specications.
Actionair DWFX-F Installation Guide
Vertical Damper, Ablative Batt in a
Masonry Wall
Actionair SmokeShield PTC - [AA/F10712]
Actionair FireShield - [AA/F10713]
Installation Method
1. Rivet steel duct (by others) to damper spigot on non-
access side, using steel rivets.
2. Suspend the damper from the ceiling, using 10mm
studding drop rods, and support the damper from
lateral movement.
3. Make sure the area within the aperture and the
damper casing is free from any debris and remove any
dust.
4. Where the coated BATT will contact the surrounding
aperture apply Rockwool Fire pro glue to the outer
edges of the BATT. Where two coated BATTS are in
contact, use Rockwool re pro glue as the joint adhe-
sive. In both cases ensure that an even cover is achie-
ved over the entire thickness of the BATT.
5. Continue installation of Rockwool ablative coated
BATT, until aperture is completely lled.
6. Apply a bead of Rockwool acoustic intumescent sealant
to both sides of the wall, approximately 15mm wide
around perimeter of the aperture between wall and
BATT, ensuring that any gaps between the BATT and
surrounding edges are fully lled.
7. Allow 12 hours for BATT penetration seal to cure prior
Comments:
Rev:
Drawn By:
S.Wehrle
Approved By:
A. Hill
1 of 1
Reference No:
S. Gore
Date:
Date:
By: Date:
25/11/2019
15/07/2010
25/11/2019
Date:
H
Checked By:
Sheet Rev
AAF10712
Description:
If your proposed installation details differ from
that shown here, please discuss this with the
Building Control Authority (BCA), referencing
this documentation, associated fire tests,
assessments, and other documentation shown
below. Deviation from this drawing requires
the approval of the relevant authority.
Installation Detail
Connecting ductwork omitted for clarity.
Ductwork must be independently supported.
There must be an appropriate break-away joint
between the damper and connecting ductwork
on both sides of assembly. Aluminium rivets or
plastic cleats, clips, clamps and bolts etc.
should be used for this, unless fire resisting
ductwork is being used where fire resisting
fixings should be used. A minimum of 200 mm
between fire dampers installed in separate
ducts and 75 mm between fire damper and a
construction element (wall/floor).
IF YOUR PROPOSED
INSTALLATION DETAIL DIFFERS
FROM THAT SHOWN, YOU MUST
DISCUSS THIS WITH THE
BUILDING CONTROL AUTHORITY
(BCA), REFERENCING THIS
DOCUMENT AND THE
ASSOCIATED FIRE TESTS,
ASSESSMENTS AND OTHER
DOCUMENTS SHOWN BELOW.
DEVIATION FROM THIS DRAWING
REQUIRES THE APPROVAL OF
THE RELEVANT AUTHORITY.
©Swegon Air Management Limited
South Street, Whitstable, Kent CT5 3DU
Tel: +44 (0)1227 276100
Fax: +44 (0)1227 264262
www.swegonair.co.uk
Applicable Test Report to
BS EN1366-2:
APPLUS 19/20747-1925
MINUTESES120
Fire Resistance
Integrity and Leakage
EEC1770 MJB 20-02-18
Damper Size Range (mm)
VERTICAL APPLICATION
SMOKE SHIELD + DWFX-F &
ABLATIVE BATT
200 x 200 to 1000 x 1000
VERTICAL BLADES;
Damper can be installed with the blades in the
vertical orientation with actuator mounted at
either the top or bottom. For cleat locations of
motors mounted on top refer to drawing
FEC1830 RTC 20/03/18
G EC1839 RTC 13/04/18
CHANGE IN PROGRESS
See Mark Bushell
HECN1959 MJB 26-11-19
to removing any lateral damper supports.
8. Connecting ductwork omitted for clarity. Ductwork
must be independently supported. There must be an
appropriate break-away joint between the damper and
connecting ductwork on both sides of assembly. Alu-
minium rivets or plastic cleats, clips, clamps and bolts
etc. should be used for this, unless re resisting duct-
work is being used where re resisting xings should
be used. A minimum of 200 mm between re dampers
installed in separate ducts and 75 mm between re
damper and a construction element (wall/oor).
9. For SmokeShield installations, please reference the
actuator installation information on page 11.

Actionair DWFX-F Installation Guide
8Swegon reserves the right to alter specications. 20210408 - LNNN00354 (3.0)
Vertical Damper in a Masonry Wall
with Pattress
Actionair SmokeShield PTC - [AA/F12493]
Installation Method
1. Drill clearance holes in the damper ange at 150mm
centres.
2. Install the damper and x through ange using re
rated fasteners, min ø4mm.
3. Back ll between damper casing and wall, with mine-
ral/stone wool and pattress over this down to the
spigot. Fasten pattress with re rated fasteners, min
ø4mm. at 300mm centres.
4. Note: Dampers supplied with cleats welded to top
ange to assist with installation only.
5. Connecting ductwork omitted for clarity. Ductwork
must be independently supported. There must be an
appropriate break-away joint between the damper and
connecting ductwork on both sides of assembly. Alu-
minium rivets or plastic cleats, clips, clamps and bolts
etc. should be used for this, unless re resisting duct-
work is being used where re resisting xings should
be used. A minimum of 200 mm between re dampers
installed in separate ducts and 75 mm between re
damper and a construction element (wall/oor).
6. For SmokeShield installations, please reference the
actuator installation information on page 11.
Comments:
Rev:
Drawn By:
M. Bushell
Approved By:
S. Wehrle
1 of 1
Reference No:
S. Gore
Date:
Date:
By: Date:
23/08/18
21/08/18
23/08/18
Date:
.
Checked By:
Sheet Rev
AAF12493
Description:
If your proposed installation details differ from
that shown here, please discuss this with the
Building Control Authority (BCA), referencing
this documentation, associated fire tests,
assessments, and other documentation shown
below. Deviation from this drawing requires
the approval of the relevant authority.
Installation Detail
Connecting ductwork omitted for clarity.
Ductwork must be independently supported.
There must be an appropriate break-away
joint between the damper and connecting
ductwork on both sides of assembly.
Aluminium rivets or plastic cleats, clips,
clamps and bolts etc. should be used for this,
unless fire resisting ductwork is being used
where fire resisting fixings should be used. A
minimum of 200 mm between fire dampers
installed in separate ducts and 75 mm
between fire damper and a construction
element (wall/floor).
³stone wool
©Swegon Air Management Limited
South Street, Whitstable, Kent CT5 3DU
Tel: +44 (0)1227 276100
Fax: +44 (0)1227 264262
www.swegonair.co.uk
Applicable Test Report to
BS EN1366-2:
BRE 256493
MINUTESES 120
Fire Resistance
Integrity and Leakage
.EC1879 MJB 23-08-18
Damper Size Range (mm)
VERTICAL APPLICATION
SMOKE SHIELD + DWFX-F WITH
PATTRESS IN MASONRY WALL
200 X 200 to 1000 x 1000
VERTICAL BLADES;
Damper can be installed with the blades
in the vertical orientation with the
actuator mounted at either the top or
bottom. For cleat

9
20210408 - LNNN00354 (3.0) Swegon reserves the right to alter specications.
Actionair DWFX-F Installation Guide
Vertical Damper Installation (Top
Flange Removed) In A Masonry Wall
Under Concrete Slab
Actionair SmokeShield - [AA/F12394]
Actionair FireShield - [AA/F12827]
Installation Method
1. Measure the overall Fire damper casing size width x
height, but for Smoke Shield include the PTC Shroud
(28mm) in the width but do not include any of the
peripheral ange.
2. Calculate hole size...
3. For Fire Shield calculate the nished hole size by adding
10-80mm to the case width and 5-40mm for the
height as the head of the damper will be against the
slab.
4. For Smoke Shield calculate the nished hole size adding
10-57mm to the width and 5-30mm to the height as
the head of the damper will be against the slab.
5. Drill clearance holes in the three damper ange's side
and bottom at 150mm centres.
6. Apply a bead of low pressure intumescent mastic
along top edge of damper as a gap ller and install
the damper and fasten through ange using re rated
fasteners, min ø4mm.
7. Dampers are supplied with cleats and only need to be
used to help/assist with the installation before faste-
ning the ange to the wall.
8. Back ll with mineral/stone wool and to retain this use
Section A-A
Section B-B
- DRIVE SIDE DETAIL
Section C-C
Section D-D
A
A
BB
C C
D
D
1
1
2
2
3
3
4
4
5
5
6
6
A A
B B
C C
D D
Comments:
Rev:
Drawn By:
M. Bushell
Approved By:
A. Hill
1 of 2
Reference No:
S. Gore
Date:
Date:
By: Date:
01/07/2019
01/05/2018
01/07/2019
Date:
B
Checked By:
Sheet Rev
AAF12394
Description:
If your proposed installation details differ from
that shown here, please discuss this with the
Building Control Authority (BCA), referencing
this documentation, associated fire tests,
assessments, and other documentation shown
below. Deviation from this drawing requires
the approval of the relevant authority.
Installation Detail
Connecting ductwork omitted for clarity.
Ductwork must be independently supported.
There must be an appropriate break-away
joint between the damper and connecting
ductwork on both sides of assembly.
Aluminium rivets or plastic cleats, clips,
clamps and bolts etc. should be used for this,
unless fire resisting ductwork is being used
where fire resisting fixings should be used. A
minimum of 200 mm construction element
(wall) between fire dampers installed in
separate ducts and 75 mm between fire
damper and a construction element (wall).
A
A
B
B
C
C
D
D
©Swegon Air Management Limited
South Street, Whitstable, Kent CT5 3DU
Tel: +44 (0)1227 276100
Fax: +44 (0)1227 264262
www.swegonair.co.uk
Applicable Test Report to
BS EN1366-2:
WF388114
MINUTESES120
Fire Resistance Integrity
and Leakage
VERTICAL BLADES;
The damper can be installed with the
blades in the vertical orientation with the
actuator mounted at the bottom. For
cleat locations of motors mounted on the
bottom refer to drawing AA-SS-2011.
Slab
Actuator
Interface
Interface
shroud
Damper
Dampers supplied with cleats
welded to side flanges to assist
with installation only
Min. 100kg/m³stone mineral wool
insulation filing gaps on three sides.
5-30mm.infillon
nondriveside
andbottom.
Block/masonry wall
Damper Size Range (mm)
VERTICAL APPLICATION
SMOKE SHIELD DWFX-F, IN
MASONRY WALL AGAINST SLAB
200 x 200 to 1000 x 1000
EC1843 MJB 08-05-18
12.5mm. thick 150mm. gypsum fire
boards type F (EN520) on sides and
bottom, fixed with min. M5 fire rated
fasteners to suit supporting construction.
Up to 55mm.
infil on actuator
side only.
AECN1922 MJB 12-04-19
DWFX-F angle flange
(welded to damper casing)
on sides and bottom fixed with
drywall screws (@150mm. ctrs)
into stud channel.
Cleat
BECN1940 MJB 01-07-19
a 150mm pattress down to the damper spigot/duct
line. Fasten with re rated fasteners, min ø4mm at
300mm centres on the sides and bottom. Measure the
gap for the top pattress and x this pattress to the wall
either side of the damper, (do not x at 300ctr to the
damper case).
9. Connecting ductwork omitted for clarity. Ductwork
must be independently supported. There must be an
appropriate break-away joint between the damper and
connecting ductwork on both sides of assembly. Alu-
minium rivets or plastic cleats, clips, clamps and bolts
etc. should be used for this, unless re resisting duct-
work is being used where re resisting xings should
be used. A minimum of 200 mm between re dampers
installed in separate ducts and 75 mm between re
damper and a construction element (wall/oor).
10. For SmokeShield installations, please reference the
actuator installation information on page 11.

Actionair DWFX-F Installation Guide
10 Swegon reserves the right to alter specications. 20210408 - LNNN00354 (3.0)
Periodic Maintenance
Manufacturer Recommended Service Inter-
vals
• After commissioning and handover (see DW145 check
sheet), in order to remain compliant with 15650:2010,
we recommend that you follow a regular service and
inspection programme to ensure correct operation
of dampers in the event the damper is required to
actuate.
• In addition to regular physical inspections (in accor-
dance with 15650:2010) we recommend using a
dedicated damper control panel with a digital reporting
mechanism (such as an Actionpac LNS system) to fre-
quently monitor and report on regular remote damper
testing.
• Ensure maintenance is performed in line with the latest
best practice and relevant local or specialist guidance.
• Our recommended service intervals for life safety pro-
ducts are as follows:
Interval Action Competence
6 Months Check Actuator Wiring (if appli-
cable) for Damage
Specialist
Persons
6 Months Check Limit Switch Wiring (if
applicable) for Damage
Specialist
Persons
6 Months Check Damper Cleanliness, Clean
and Lubricate if necessary.
Specialist
Persons
6 Months Check Condition of Blades and
Seals, report and rectify if neces-
sary.
Specialist
Persons
6 Months Check for blade obstructions Specialist
Persons
6 Months Check Damper Release Me-
chanism (through activation or
release of the ETR or Thermal
Fuse Device)
Specialist
Persons
6 Months Check damper is left in normal
operational position after inspec-
tion.
Specialist
Persons
Monthly Complete actuation of damper
from control panel (if installed)
and check all faults. Consult spe-
cialist persons to investigate any
reported faults.
Facility Ma-
nager
• *Specialist Persons: A recognised and experienced
person with prior experience in the inspection and
assessment of the functional safety of smoke and re
damper products. If in doubt, please consult with our
technical support team for advice. To talk about our
OEM maintenance inspections, contact our nationwide
service team.
BS EN 15650:2010 - Ventilation for Buildings
- Fire Dampers
• Section 8.3 states regular testing/ inspection should
be undertaken to meet regulatory requirements, or at
intervals not exceeding six months.
• A comprehensive example of the maintenance pro-
cedure is given in Annex D of the standard. Some
automatic systems may allow more frequent testing
(48hr or less) and this may be required by a national
standard.
Approved Document B, Volume 2
• Clause 10.12 states adequate means of access must be
provided to allow inspection, testing and maintenance
of both re damper and its actuating mechanism.
BS 9999:2017 - Code of Practice for the Fire
Safety in the Design, Management and Use
of Buildings - Annex I
Smoke Control Systems
• For means of escape states actuation of the system
should be simulated once a week. It should be ensured
that any fans and powered exhaust ventilators ope-
rate correctly, smoke dampers close (or open in some
systems), natural exhaust ventilators open, automatic
smoke curtains move into position, etc.
Three Monthly
• In addition to the checks recommended in V.2, V.3 and
V.4, the actuation of all smoke control systems should
be simulated once every three months. All zones should
be separately tested and it should be ensured that any
fans and powered exhaust ventilators operate correctly,
smoke dampers close (or open in some systems) etc.
Yearly
• In addition to the following checks should be made for
annual inspections and tests of the following to be car-
ried out by competent persons, for any defects to be
logged and the necessary action taken, and for certi-
cates of testing to be obtained.
– Fire detection and re alarm systems;
– Self-contained luminaires with sealed batteries, if more
than 3 years old;
– Sprinkler, drencher and watermist systems;
– Smoke ventilators and smoke control systems;
– Fire dampers
BS 9999:2017 - Code of Practice for the Fire
Safety in the Design, Management and Use
of Buildings - Annex W
• Maintenance of air conditioning and ventilation equip-
ment including air lters, motors, re dampers and
their controls, smoke detectors and alarms is of para-
mount importance both in preventing re and in ensur-
ing that measures taken to mitigate its consequences
are effective when needed. Arrangements should be
made for all re dampers to be tested by a competent
person on completion of the installation and at regular
intervals not exceeding 2 years. They are to be repaired
or replaced immediately if found to be faulty. Spring
operated re dampers should be tested annually and
re dampers in dust laden and similar atmospheres
should be tested much more frequently, at periods
suited to the degree of pollution.

11
20210408 - LNNN00354 (3.0) Swegon reserves the right to alter specications.
Actionair DWFX-F Installation Guide
Actuators
Control Mode Installation Procedure
1. Remove transit plate and recycle.
2. Slide the interface and mode assembly into the shroud.
Ensure the slots in the interface casing and the drive
coupling located on the rear of the interface are in line.
3. Push the assembly fully home until the interface sprung
retaining pin engages through the locating hole in the
damper shroud (snaplock™).
4. The control mode can be tted in any of three orienta-
tions i.e. vertically down, horizontally and vertically up
(For height restrictions). This can easily be carried out
by the following:
5. Remove and retain screw (8mm A/F) and washer,
through the position indicator on the control mode.
6. Remove the control mode and interface adapter plate.
7. Taking care not to disturb the drive hexagon. Replace
the interface adapter plate and control mode in the
new orientation.
8. Replace the washer and screw tight (Max 5Nm) Select
a suitable position for the Electrical Thermal Release
(ETR) to be mounted through the ductwork.
9. Ideally this should be in the top half of the duct and/ or
above the level of the interface.
10. Apply the self-adhesive template (located on the rear
of the ETR) and drill the necessary holes (Ø3mm &
Ø9.5 & Ø11mm). Push the ETR through the duct and
ensure both screws are used to hold it in position.
Both screws should be tightened fully to ensure that
both sections of the ETR are closed together. It is a
safety feature, if both sections are not closed the unit
will not operate. For ductless installations the ETR
should be tted onto the damper spigot (not casing)
above the damper interface shroud and in accordance
with the tting instructions. If the ETR is not tted in
the exact manner described above, the unit will not
operate.
11. The damper should be manually reset and released
using the winder provided to ensure that correct
mechanical operation is achievable. It is possible to
mechanically lock open the SmokeShield PTC damper
to allow air to pass through it using the winder pro-
vided, this may be necessary if electrical power isn’t
available yet. The ETR is not operable in this instance,
the damper will not release automatically if the tempe-
rature rises or a re occurs.
12. The unit must be wired as detailed. When power is
available, the unit must be checked for correct electri-
cal operation. Power on to reset, power off to release.
13. The unit must also be checked by pushing and holding
the test switch on the ETR to conrm that the damper
releases. When pressure is removed from the switch
the damper resets. This may also be done after the
initial installation test, to provide periodic operation of
the damper to simulate actual fail-safe release under
smoke/re conditions.
14. The ETR cable must not cut to shorten or lengthen,
and care must be taken not to damage it. Either will
render the unit inoperable and void any warranties.
This is due to a built in safety feature.

Actionair DWFX-F Installation Guide
12 Swegon reserves the right to alter specications. 20210408 - LNNN00354 (3.0)
DWFX-F Wiring Diagrams
Close Time ≈ 22 secs.
Open Time ≈ 60 secs.
(Connect 24V via a safety isolating
transformer.)
IP54 Rated.
Supply On – Damper motors open.
Electrical Thermal Release.
External mechanical position indicator
with pointer.
WHITE (2)
BLACK (1)
1
2
3
4
5
6
_
+
COMMON
SUPPLY 24V AC or DC
TYPICALLY 10W (MOTORING
2W (RESET)
CONTINUITY WITH 'COMMON'
WHEN DAMPER CLOSED
COMMON
VOLT FREE CONTACT
MADE BETWEEN 1 & 2
WHEN DAMPER
FULLY CLOSED
M
AC/DC 24V
50 / 60 Hz
12.5 VA
VOLT FREE CONTACT
MADE BETWEEN 4 & 6
WHEN DAMPER
FULLY OPEN
10 / 2 W
Imax
8.3A @ 5ms
-30°C...+50°C
CONTINUOUS TF 72°C
AC
250V
6(3)
A
ELECTRICAL THERMAL RELEASE (ETR)
(MUST BE FITTED TO DUCTING FOR
DAMPER OPERATION).
(SPRING BIASED TEST SWITCH)
CONTINUITY WITH 'COMMON'
WHEN DAMPER OPEN
CONTINUITY WITH 'COMMON'
WHEN DAMPER CLOSED
CONTINUITY WITH 'COMMON'
WHEN DAMPER OPEN
Supply O – Damper spring closes.
Mode 6 PTC 230V
Supply On – Damper motors open.
Electrical Thermal Release.
External mechanical position indicator
with pointer.
Close Time ≈ 22 secs.
Open Time ≈ 60 secs.
(To isolate from main power supply, the
system must incorporate a device which
disconnects the phase conductors, with at
least 3mm contact gap.)
Note: 120V A.C. version also available.
IP54 Rated.
BLUE
BROWN
1
2
3
4
5
6
L1
COMMON
COMMON
SUPPLY 230V AC 50/60Hz
TYPICALLY 12W (MOTORING
4W (RESET)
VOLT FREE CONTACT
MADE BETWEEN 1 & 2
WHEN DAMPER
FULLY CLOSED
VOLT FREE CONTACT
WHEN DAMPER
MADE BETWEEN 4 & 6
M
FULLY OPEN
AC/DC 230V
50 / 60 Hz
14 VA
12 / 4 W
-30°C...+50°C
CONTINUOUS TF 72°C
AC
250V
6(3)A
N
CONTINUITY WITH 'COMMON'
ELECTRICAL THERMAL RELEASE (ETR)
(MUST BE FITTED TO DUCTING FOR
DAMPER OPERATION).
(SPRING BIASED TEST SWITCH)
WHEN DAMPER CLOSED
CONTINUITY WITH 'COMMON'
WHEN DAMPER OPEN
CONTINUITY WITH 'COMMON'
WHEN DAMPER CLOSED
CONTINUITY WITH 'COMMON'
WHEN DAMPER OPEN
Supply O - Damper spring closes.
Mode 5-3P
Supply On – Damper motors open.
Spring close time ≈ 18 seconds
Motor open time ≈ 120 seconds
(Connect 24V via a safety isolating transformer.)
IP54 Rated.
The M5-3P is controlled by standard 0...10V
control signal. The actuator motors to the position
activated, power supply lost or removed the device
springs the damper to the fail-safe position.
Electrical thermal release (ETR)
_
+
~
T
1
2
3
4
5
6
COMMON
COMMON
VOLT FREE CONTACT
WHEN DAMPER
MADE BETWEEN 1 & 2
FULLY RELEASED
VOLT FREE CONTACT
MADE BETWEEN 4 & 6
WHEN DAMPER
FULLY RESET
TF 72°C
AC
250V
6(3)A
CONTINUITY WITH 'COMMON'
ELECTRICAL THERMAL RELEASE (ETR)
(MUST BE FITTED TO DUCTING FOR
DAMPER OPERATION).
(SPRING BIASED TEST SWITCH)
WHEN DAMPER CLOSED
CONTINUITY WITH 'COMMON'
WHEN DAMPER OPEN
CONTINUITY WITH 'COMMON'
WHEN DAMPER CLOSED
CONTINUITY WITH 'COMMON'
WHEN DAMPER OPEN
WHITE (5)
WHITE (3) Y DC 0...10V
U DC 2...10V
AC/DC 24V
50 / 60 Hz
9.5 VA
7 / 2.5 W
Imax
8.3A @ 5ms
M
-30°C...+50°C
CONTINUOUS
RED (2)
BLACK (1) SUPPLY 24V A.C. or D.C.
TYPICALLY 6W (MOTORIN G
2W (HOLDING)
DIAGRAMS SHOWS ACTUATOR IN FULLY CLOSED STATE
NOTE THAT THE FOR INTERMEDIATE
POSITIONS, NEITHER OF THE
CONDITIONS BELOW WILL BE TRUE.
Supply O - Damper spring closes.
specied by the control signal. If the ETR is
(Must be tted to ducting for damper operation).
Mode 5 PTC 24V

13
20210408 - LNNN00354 (3.0) Swegon reserves the right to alter specications.
Actionair DWFX-F Installation Guide
DWFX-F Damper Dimensional Data
O 398mmVERALL FLANGE WIDTH =
OVERALL FLANGE HEIGHT = 395mm
OVERALL FLANGE WIDTH = 448mm
OVERALL FLANGE HEIGHT = 445mm
OVERALL FLANGE WIDTH = DUCT DIA + 248mm
G
W
OVERALL FLANGE HEIGHT = DUCT DIA + 245mm
FOR DUCT DIAMETERS BET EEN 970mm - 1000
mm
OVERALL WIDTH OF FLAN E WIDTH IS 1198mm
OVERALL HEIGHT OF INSTALLATION FRAME IS 11
95mm
OVERALL FLANGE WIDTH = DUCT DIA + 248mm
OVERALL FLANGE HEIGHT = DUCT DIA + 245mm
FOR DUCT WIDTHS BETWEEN 970mm - 1000m
m
OVERALL WIDTH OF INSTALLATION FRAME IS 11
98mm
Flat Oval Dampers Series 701
C
Circular Dampers Series 601 FOR DAMPERS 100-150MM
2
FOR IRCULAR DAMPERS SERIES 601, DIAMETERS 151-199MM
FOR CIRCULAR DAMPERS SERIES 601, DIAMETERS 00-1000MM
Actionair SmokeShield PTC

Actionair DWFX-F Installation Guide
14 Swegon reserves the right to alter specications. 20210408 - LNNN00354 (3.0)
Rectangular Dampers Series 501
For Rectangular Dampers spigots are 5mm under duct size.
Widths and heights available in 1mm increments.
OVERALL FLANGE WIDTH DUCT WIDTH + 198mm
OVERALL FLANGE HEIGHT DUCT HEIGHT + 195mm
For Ducts with widths and heights of 200 - 1000mm
FOR DUCT WIDTHS 200MM - 1000MM WITH HEIGHTS OF 100-199MM
OVERALL FLANGE WIDTH IS 398mm
UCT WIDTHS A
OVERALL FLANGE HEIGHT IS 395mm
FOR D ND HEIGHTS OF 100-150MM
FOR DUCT WIDTHS AND HEIGHTS OF 151-199MM
OVERALL FLANGE WIDTH IS 448mm
OVERALL FLANGE HEIGHT IS 445mm
FOR OVERALL HEIGHTS SEE 100 - 150mm
OR 151 - 199mm AS ABOVE

15
20210408 - LNNN00354 (3.0) Swegon reserves the right to alter specications.
Actionair DWFX-F Installation Guide
FireShield and DWFX-F Installation Dimensional Data
Base Dampers Dampers with DWFX-F
Series 101
FireShield Dampers with blades partly in airstream (Damper spigots
-
stream
Series 201
spigots 5mm under duct size) 100 – 249 high, use Series 101 Damper as
Series 301
spigots 3mm under duct size)
Series 401
spigots 3mm under duct size)
Actionair FireShield

Actionair DWFX-F Installation Guide
16 Swegon reserves the right to alter specications. 20210408 - LNNN00354 (3.0)
Inspection and handover check sheet
This certicate applies only to Swegon Fire Dampers. The installer must complete this installation certicate when instal-
ling re and smoke dampers. A separate certicate must be completed for each individual re and smoke damper.
Damper Unique System I.D: ...............................................................................................................................................................................
Name of installation location:.............................................................................................................................................................................
Address:....................................................................................................................................................................................................................
Installation location identication section/oor/room: ..............................................................................................................................
Damper product type: .........................................................................................................................................................................................
Release fuse temperature: ..................................................................................................................................................................................
Notes/Considerations: ...........................................................................................................................................................................................
Installed by: .............................................................................................................................................................................................................
Company Name: ....................................................................................................................................................................................................
Address: ....................................................................................................................................................................................................................
Company Telephone No: .....................................................................................................................................................................................
Installers Name: ......................................................................................................................................................................................................
Installers Telephone No: .......................................................................................................................................................................................
Date of installation: ...............................................................................................................................................................................................
It is hereby veried that the damper detailed above has been installed and tested according to the manufactures recom-
mendations:
Installers signature: ................................................................................................ Date: ................................................
Question Action
1 Are the dampers the correct type? Conrm damper is correct type for the application
2 Are the dampers located correctly? The damper location is to be checked against the installation
drawings/details
3Are the dampers correctly identied? Unique system ID to be clearly indicated on the damper or
other agreed location.
4 Have supports for both the damper and the adjacent
ductwork been installed in accordance with the appro-
ved manner?
5Are the dampers tted in the correct orientation? Conrm the damper is installed with any actuators (if app-
licable) on the left or right hand side. Not on the top or the
bottom (i.e. blade pivot running vertically).
6 Is access through the ductwork, to the damper unob-
structed?
Unobstructed space should be provided for safe access to the
damper. This must include access through ceiling voids and ad-
jacent services. Damper installer to advise the system designer
if problems are foreseen.
7Has the space around the damper and within the
opening been left clear and not been used for other
services?
Other services within the installation opening will invalidate
the installation method. Damper installer to advise the lead
contractor if problems are foreseen.
8 Using the access opening provided, check that blades
open and close.
Check position of damper blades.
9Has the damper been checked for internal cleanliness,
free from damage and that vertical casings in particular
are free from debris?
With the damper in the closed position, inspect for damage.
10 Has the damper been released to simulate operation of
the thermal release? (Damper drop test)
Ensure damper operation is free from interference.
11 Have the damper blades been re-set following drop
test and the access panel replaced?
After re-setting the damper, check the position shown on the
blade position indicator is correct.
12 At the time of damper handover, is the re barrier and
penetration seal complete?
Damper installer to record on the handover register if
any following trades are still to complete their activities.
13 Is the damper installation complete and available for
handover prior to system commissioning?
Obtain the relevant acceptance of the damper installation from
the CDM coordinator.
14 Is the completed handover register cross-referenced
back to the identication codes listed in the system
designers damper schedule?
This manual suits for next models
1
Table of contents
Other actionair Fire And Smoke Damper manuals
Popular Fire And Smoke Damper manuals by other brands

Trox Technik
Trox Technik FKRS-EU Supplementary installation manual

mercor
mercor mcr WIP LD Operation and maintenance manual

Greenheck
Greenheck VCD Series Installation, operation and maintenance manual

Tecnosystemi
Tecnosystemi SIRIO 2.0 MASTER user manual

mercor
mercor mcr FID S Operation and maintenance manual

Ace
Ace FYN-P1 Operating and mounting instructions