Quartz™ Installation Guide 15
This product must be installed by a competent person in accordance with
the relevant Water Supply Regulations.
In addition to the guide below, it is essential that the written instructions
overleaf are read and understood and that you have all the necessary
components (shown overleaf) before commencing installation.
The Quartz Digital shower system is supplied with universal fixings intended
to secure it to a suitable wall.
!
Quartz
Digital Exposed with adjustable height head
!
Flush out the hot and cold supply pipes.
5
The maximum hot water inlet temperature must be no more than 65°C.
!
Place the Digital processor on a solid mounting
surface, adjusting the fixing feet into suitable
positions. Mark then drill and prepare suitable
fixings before securing the processor to the
mounting surface using the screws provided.
4
Carefully slide the rail end covers onto the
fixing brackets flush with the finished wall
surface and click the sides firmly into position.
17
6
Drill a hole through the ceiling, a minimum of Ø30mm, maximum Ø40mm.
8
Feed the riser rail assembly containing the
supply pipe and data cable through the hole in
the ceiling, ensuring that the control is at the
desired height, the rail is vertical, and that
there is adequate working clearance above the
top of the rail in the roof space.
9
Temporarily slide the gel hook up the rail ensuring it is positioned higher than
the lower fixing bracket assembly.
10
Place the lower bracket support pillar into
position ensuring the locking lug is correctly
fitted into the location hole.
11
Carefully slide the fixing bracket over the rail
onto the support pillar.
12
Place the upper rail bracket support pillar into
the desired location ensuring that both the
hose restraint and the handset holder are
below the rail wall bracket.
15
Connect the power to the processor and press
the ‘Start/stop’ button on the controller to turn
the shower on. Ensuring the hose washers are
fitted at either end of the shower hose, attach
the hose and flush the system through for 15
seconds to clear any debris. Turn the shower off
and isolate from the electricity supply.
23
Attach the supply pipes to the Digital processor,
ensuring that the cold and hot feeds are fitted
into the appropriately marked inlets.
DO NOT SOLDER NEAR TO PLASTIC
COMPONENTS.
!
90mm
445mm
270mm
350mm
265mm
70mm
To ensure safe operation and installation of this product, the processor MUST be
installed in one of the orientations shown.
1
Isolation valves are supplied with the Digital
processor and must be fitted on both inlets and
the blended water outlet. All pipe work should
be run in 15mm pipe. All pipe work should be
supported. For externally pumped gravity fed
installations, 22mm pipe work should be run
as close to the processor as possible before
reducing down to 15mm.
2
The inlet supply centres are 48mm. The inlet supply centres deviate from
EN1111 and EN1287, but are deemed to be a special case. Please note arrow
on isolation valve to indicate direction of flow.
Compression fittings should not be used on the inlet and outlet spigots and
may affect the warranty if fitted.
!
Connect the outlet pipe to the mixed water outlet on the Digital processor,
using the push-fit elbow provided. Using pipe clips as appropriate, ensure that
all pipe work is perpendicular to the processor, i.e. not putting any strain on
the fittings.
19
Do not solder any additional pipe work to the 15mm copper pipe from the
Digital shower system as the low voltage data cable could be damaged.
Instead, use push-fit fittings where necessary, to connect additional copper
piping.
TO ENSURE OPTIMUM PERFORMANCE USE THE MINIMUM AMOUNT
OF ELBOWS.
TO MAXIMISE FLOW RATES WE RECOMMEND USING COPPER PIPE WITH
THE MINIMUM AMOUNT OF ELBOWS.
BEFORE ANY ELECTRICAL ADJUSTMENT IS ATTEMPTED, THE ELECTRICITY
SUPPLY MUST BE TURNED OFF AT THE MAINS SWITCH.
ELECTRICAL INSTALLATION MAY ONLY BE CARRIED OUT BY A QUALIFIED
PERSON.
!
Connect the processor power lead to a double
pole 3amp switched fused spur, incorporated
in the wiring circuit, in accordance with current
wiring rules. Ensure that this is located in an
accessible, dry location and not in the
bathroom.
20
Re-instate the electricity supply to the Digital processor. Press the ‘Start/stop’
button on the controller to turn the shower on.
27
Slide the ceiling plate up to the ceiling to cover
the entry hole.
18
Choose the position for your Digital processor
as close to the shower control as possible.
The processor may be sited in the roof space
above the proposed shower site, in the airing
cupboard or behind a screwed bath panel if
more convenient. If siting in the roof space,
ensure that freezing cannot occur and that no
insulation material is placed under or over the
processor. Please refer to the system layout diagrams.
3
!
THE PROCESSOR MUST BE SITED IN A POSITION THAT IS SAFELY
ACCESIBLE FOR SERVICING AND COMMISIONING PURPOSES. WHEN
FITTED IN THE LOFT SPACE, THE ROUTE TO AND THE AREA AROUND THE
PROCESSOR MUST BE BOARDED TO ENSURE A SAFE WORKING
ENVIRONMENT.
The optimum position for the Digital processor is in the roof space above the
shower site to take full advantage of the ease and speed of installation –
please refer to the note above.
The distance between the Digital processor and shower control must be
within range of the 10m data cable supplied.
Thread the shower hose through the hose
restraint.
24
Shower Control User Guide
1. Turn the temperature dial to the required setting.
2. Press the ‘Start/stop’ button on the control, to turn
the shower on.
3. The blue LED display will flash until the selected temperature has been reached.
4. When the LED display is constant, step into your shower and enjoy!
5. The temperature may be adjusted once in the shower.
6. Press the ‘Boost’ button on the control to increase
the strength of the shower when desired.
N.B. If installed on a combination boiler system,
the strength of the ‘Boost’ button will depend on
the performance capability of your combination
boiler.
7. Press the ‘Start/stop’ button on the control, to turn the shower off.
Adjustable Head User Guide
1. Rotate the spray plate lever clockwise or
anti-clockwise to select the desired spray pattern.
N.B. When the lever is in the 3 o’clock position
when viewed from below, the water saving mode
is selected. This provides the same spray pattern
as position 3, but, depending on which water
system the product is fitted to, offers up to 25%
water saving.
2. To select the preferred height for the shower head,
depress the levers fully to enable the holder to be
moved up or down the rail.
3. Angular adjustment is made by carefully but firmly
pulling forwards or pushing back the shower head
against the knuckle ratchet in the holder.
Cleaning and maintenance
Your Quartz Digital shower system should be cleaned using only a soft cloth and
washing up liquid.
DO NOT USE ABRASIVE CLEANERS
To reduce the need for chemical descaling in hard water areas, your shower head
incorporates a ‘clear flow’ system, whereby any scale build up can be broken down
by gently rubbing the flexible tips of the jets during use. This procedure should be
completed regularly, as often as once a week in some hard water areas, as scale
build up can affect the spray pattern and cause the shower to perform poorly.
Failure to descale the shower head can affect the internal seals and may affect the
warranty.
Cleaning and maintenance should not be undertaken by children without supervision
by a person responsible for their safety.
Should chemical descaling of the head become necessary, remove the shower head
fully and immerse in a mild proprietary descalent.
!IT IS IMPERATIVE THAT DESCALING IS CARRIED OUT STRICTLY IN ACCORDANCE
WITH THE MANUFACTURER’S INSTRUCTIONS. SUBSTANCES THAT ARE NOT
SUITABLE FOR PLASTICS AND ELECTROPLATED SURFACES MUST NOT BE USED.
Locate a suitable entry point into the ceiling for the riser rail, avoiding joists
and services.
7
The Digital processors are supplied factory set
with the flow rate at either ‘NORMAL HP’ or
‘NORMAL GRAVITY’ mode depending on which
shower system has been ordered.
HP/COMBI PROCESSORS ON BALANCED HP
SYSTEMS:
HP/Combi Digital processors fitted to balanced
high pressure systems may be set to ‘NORMAL HP’, or for water economy,
‘ECO’ modes.
HP/COMBI PROCESSORS ON COMBINATION BOILER SYSTEMS:
For HP/Combi Digital processors installed on combi boiler systems, for optimum
performance we recommend setting the flow rate to the ‘COMBI’ mode.
26
N.B. The ‘ECO’ flow rate mode should not be selected for shower systems fitted
to combination boilers.
GRAVITY PUMPED PROCESSORS:
Gravity Pumped Digital processors fitted to gravity systems may be set to
‘NORMAL GRAVITY’, or for water economy, ‘ECO’ flow rate modes.
WHEN MAKING ANY ADJUSTMENT TO THE PROCESSOR SETTINGS THE
POWER MUST BE ISOLATED.
!
!
THIS APPLIANCE MUST BE EARTHED.
We recommend protecting surface mounted cables in suitable, approved
conduit to avoid the risk of damage from vermin.
The data cable and power lead should also be clipped in place with ‘P’ clips
or similar, to avoid accidents.
!
Unscrew the single fixing on top of the
processor box and then carefully tilt the lid up
and off the location lugs and pull the lid clear.
21
Run the shower at maximum temperature
(factory pre set to 45°C). If required, maximum
temperature adjustment can be made with
a flat bladed screwdriver using the ‘MAX TEMP
ADJUSTMENT’ control as indicated. When the
temperature has been set to the desired
position, carefully replace the Digital processor
lid and secure the fixing hand tight only.
28
Site conditions can affect temperature settings, installer to adjust as required.
ALL COPPER PIPE WORK MUST BE CROSS-BONDED AND CONNECTED TO
A RELIABLE EARTHING POINT.
!
TM
The centre of the riser rail stands 45mm from the wall. If this is not suitable, the
spacers provided with the fixing brackets will increase the depth to 70mm from
the wall.
!
Ensuring the rail assembly has been passed through the hole in the ceiling
and is at the desired height, mark the screw holes and remove the fixing
bracket.
13
Prepare suitable fixings and slide the fixing bracket back over the rail onto
the support pillar. Secure to the wall using the screws provided.
14
Slide the fixing bracket over the rail onto the
support pillar and repeat the above fixing
procedure.
16
The ceiling plate cannot be sited against an
uneven surface. If there is coving or an
alternative obstruction, please ensure the entry
hole is neat and unobtrusive; otherwise the
inner tube could be visible within the showering area.
If the ceiling height is over 2.4m (8ft), a Digital riser rail extension kit will be
required. Contact our Customer Service Department to purchase a riser rail
extension kit (part no: 223217).
!
Connect the low voltage data cable into the
socket adjacent to the temperature adjuster
as indicated on the label. Feed the cable out of
the processor box ensuring it is correctly
routed within the data cable channel.
22
A further data cable socket has been provided
for use with the secondary Digital remote
control or Digital diverter. This can be accessed by carefully snapping and
removing the entry pillar and connecting the cable as described above.
!
Ensuring the hose washer is in the correct
position, depress the anti-swivel locking button
on the handset and secure the handset to the
hose, then place the handset into the handset
holder.
25
Supply
Vent and draw-off
pipe to hot water
Hot water cylinder
Connect
‘A’ or ‘B’
Cold feed
to cylinder
B
A
NB: THE BASE OF THE PROCESSOR
MUST BE SITED NO HIGHER THAN
THE BASE LEVEL OF THE CISTERN
10m
max
Digital
shower
control
Supply
Pressure
reducing valve
if required
10m
max
Digital
shower
control
Supply
Hot water
cylinder
10m
max
Digital
shower
control
10m
max
Digital
shower
control
Central
heating
boiler
Supply
Supply
Vent and draw-off
pipe to hot water
Underside of cistern
Hot water
cylinder NB: 1.5 bar MINIMUM pump rating
Cold feed
to cylinder
Connect
‘A’ or ‘B’
B
A
10m
max
Digital
shower
control
Typical combination boiler installation
(Compatible with HP/Combi processor)
Typical HP system installation
(Compatible with HP/Combi processor)
Typical thermal storage unit system installation
(Compatible with HP/Combi processor)
Typical gravity system installation
(Compatible with Gravity pumped processor)
Typical pumped system installation
(Compatible with HP/Combi processor)
Quartz exposed guide V3:Quartz Exposed Install 9/1/14 14:52 Page 2
17
Place the lower bracket support pillar into position ensuring the
locking lug is correctly fitted into the location hole in the rail.
This product must be installed by a competent person in accordance with
the relevant Water Supply Regulations.
In addition to the guide below, it is essential that the written instructions
overleaf are read and understood and that you have all the necessary
components (shown overleaf) before commencing installation.
The Quartz Digital shower system is supplied with universal fixings intended
to secure it to a suitable wall.
!
Quartz
Digital Exposed with adjustable height head
!
Flush out the hot and cold supply pipes.
5
The maximum hot water inlet temperature must be no more than 65°C.
!
Place the Digital processor on a solid mounting
surface, adjusting the fixing feet into suitable
positions. Mark then drill and prepare suitable
fixings before securing the processor to the
mounting surface using the screws provided.
4
Carefully slide the rail end covers onto the
fixing brackets flush with the finished wall
surface and click the sides firmly into position.
17
6
Drill a hole through the ceiling, a minimum of Ø30mm, maximum Ø40mm.
8
Feed the riser rail assembly containing the
supply pipe and data cable through the hole in
the ceiling, ensuring that the control is at the
desired height, the rail is vertical, and that
there is adequate working clearance above the
top of the rail in the roof space.
9
Temporarily slide the gel hook up the rail ensuring it is positioned higher than
the lower fixing bracket assembly.
10
Place the lower bracket support pillar into
position ensuring the locking lug is correctly
fitted into the location hole.
11
Carefully slide the fixing bracket over the rail
onto the support pillar.
12
Place the upper rail bracket support pillar into
the desired location ensuring that both the
hose restraint and the handset holder are
below the rail wall bracket.
15
Connect the power to the processor and press
the ‘Start/stop’ button on the controller to turn
the shower on. Ensuring the hose washers are
fitted at either end of the shower hose, attach
the hose and flush the system through for 15
seconds to clear any debris. Turn the shower off
and isolate from the electricity supply.
23
Attach the supply pipes to the Digital processor,
ensuring that the cold and hot feeds are fitted
into the appropriately marked inlets.
DO NOT SOLDER NEAR TO PLASTIC
COMPONENTS.
!
90mm
445mm
270mm
350mm
265mm
70mm
To ensure safe operation and installation of this product, the processor MUST be
installed in one of the orientations shown.
1
Isolation valves are supplied with the Digital
processor and must be fitted on both inlets and
the blended water outlet. All pipe work should
be run in 15mm pipe. All pipe work should be
supported. For externally pumped gravity fed
installations, 22mm pipe work should be run
as close to the processor as possible before
reducing down to 15mm.
2
The inlet supply centres are 48mm. The inlet supply centres deviate from
EN1111 and EN1287, but are deemed to be a special case. Please note arrow
on isolation valve to indicate direction of flow.
Compression fittings should not be used on the inlet and outlet spigots and
may affect the warranty if fitted.
!
Connect the outlet pipe to the mixed water outlet on the Digital processor,
using the push-fit elbow provided. Using pipe clips as appropriate, ensure that
all pipe work is perpendicular to the processor, i.e. not putting any strain on
the fittings.
19
Do not solder any additional pipe work to the 15mm copper pipe from the
Digital shower system as the low voltage data cable could be damaged.
Instead, use push-fit fittings where necessary, to connect additional copper
piping.
TO ENSURE OPTIMUM PERFORMANCE USE THE MINIMUM AMOUNT
OF ELBOWS.
TO MAXIMISE FLOW RATES WE RECOMMEND USING COPPER PIPE WITH
THE MINIMUM AMOUNT OF ELBOWS.
BEFORE ANY ELECTRICAL ADJUSTMENT IS ATTEMPTED, THE ELECTRICITY
SUPPLY MUST BE TURNED OFF AT THE MAINS SWITCH.
ELECTRICAL INSTALLATION MAY ONLY BE CARRIED OUT BY A QUALIFIED
PERSON.
!
Connect the processor power lead to a double
pole 3amp switched fused spur, incorporated
in the wiring circuit, in accordance with current
wiring rules. Ensure that this is located in an
accessible, dry location and not in the
bathroom.
20
Re-instate the electricity supply to the Digital processor. Press the ‘Start/stop’
button on the controller to turn the shower on.
27
Slide the ceiling plate up to the ceiling to cover
the entry hole.
18
Choose the position for your Digital processor
as close to the shower control as possible.
The processor may be sited in the roof space
above the proposed shower site, in the airing
cupboard or behind a screwed bath panel if
more convenient. If siting in the roof space,
ensure that freezing cannot occur and that no
insulation material is placed under or over the
processor. Please refer to the system layout diagrams.
3
!
THE PROCESSOR MUST BE SITED IN A POSITION THAT IS SAFELY
ACCESIBLE FOR SERVICING AND COMMISIONING PURPOSES. WHEN
FITTED IN THE LOFT SPACE, THE ROUTE TO AND THE AREA AROUND THE
PROCESSOR MUST BE BOARDED TO ENSURE A SAFE WORKING
ENVIRONMENT.
The optimum position for the Digital processor is in the roof space above the
shower site to take full advantage of the ease and speed of installation –
please refer to the note above.
The distance between the Digital processor and shower control must be
within range of the 10m data cable supplied.
Thread the shower hose through the hose
restraint.
24
Shower Control User Guide
1. Turn the temperature dial to the required setting.
2. Press the ‘Start/stop’ button on the control, to turn
the shower on.
3. The blue LED display will flash until the selected temperature has been reached.
4. When the LED display is constant, step into your shower and enjoy!
5. The temperature may be adjusted once in the shower.
6. Press the ‘Boost’ button on the control to increase
the strength of the shower when desired.
N.B. If installed on a combination boiler system,
the strength of the ‘Boost’ button will depend on
the performance capability of your combination
boiler.
7. Press the ‘Start/stop’ button on the control, to turn the shower off.
Adjustable Head User Guide
1. Rotate the spray plate lever clockwise or
anti-clockwise to select the desired spray pattern.
N.B. When the lever is in the 3 o’clock position
when viewed from below, the water saving mode
is selected. This provides the same spray pattern
as position 3, but, depending on which water
system the product is fitted to, offers up to 25%
water saving.
2. To select the preferred height for the shower head,
depress the levers fully to enable the holder to be
moved up or down the rail.
3. Angular adjustment is made by carefully but firmly
pulling forwards or pushing back the shower head
against the knuckle ratchet in the holder.
Cleaning and maintenance
Your Quartz Digital shower system should be cleaned using only a soft cloth and
washing up liquid.
DO NOT USE ABRASIVE CLEANERS
To reduce the need for chemical descaling in hard water areas, your shower head
incorporates a ‘clear flow’ system, whereby any scale build up can be broken down
by gently rubbing the flexible tips of the jets during use. This procedure should be
completed regularly, as often as once a week in some hard water areas, as scale
build up can affect the spray pattern and cause the shower to perform poorly.
Failure to descale the shower head can affect the internal seals and may affect the
warranty.
Cleaning and maintenance should not be undertaken by children without supervision
by a person responsible for their safety.
Should chemical descaling of the head become necessary, remove the shower head
fully and immerse in a mild proprietary descalent.
!IT IS IMPERATIVE THAT DESCALING IS CARRIED OUT STRICTLY IN ACCORDANCE
WITH THE MANUFACTURER’S INSTRUCTIONS. SUBSTANCES THAT ARE NOT
SUITABLE FOR PLASTICS AND ELECTROPLATED SURFACES MUST NOT BE USED.
Locate a suitable entry point into the ceiling for the riser rail, avoiding joists
and services.
7
The Digital processors are supplied factory set
with the flow rate at either ‘NORMAL HP’ or
‘NORMAL GRAVITY’ mode depending on which
shower system has been ordered.
HP/COMBI PROCESSORS ON BALANCED HP
SYSTEMS:
HP/Combi Digital processors fitted to balanced
high pressure systems may be set to ‘NORMAL HP’, or for water economy,
‘ECO’ modes.
HP/COMBI PROCESSORS ON COMBINATION BOILER SYSTEMS:
For HP/Combi Digital processors installed on combi boiler systems, for optimum
performance we recommend setting the flow rate to the ‘COMBI’ mode.
26
N.B. The ‘ECO’ flow rate mode should not be selected for shower systems fitted
to combination boilers.
GRAVITY PUMPED PROCESSORS:
Gravity Pumped Digital processors fitted to gravity systems may be set to
‘NORMAL GRAVITY’, or for water economy, ‘ECO’ flow rate modes.
WHEN MAKING ANY ADJUSTMENT TO THE PROCESSOR SETTINGS THE
POWER MUST BE ISOLATED.
!
!
THIS APPLIANCE MUST BE EARTHED.
We recommend protecting surface mounted cables in suitable, approved
conduit to avoid the risk of damage from vermin.
The data cable and power lead should also be clipped in place with ‘P’ clips
or similar, to avoid accidents.
!
Unscrew the single fixing on top of the
processor box and then carefully tilt the lid up
and off the location lugs and pull the lid clear.
21
Run the shower at maximum temperature
(factory pre set to 45°C). If required, maximum
temperature adjustment can be made with
a flat bladed screwdriver using the ‘MAX TEMP
ADJUSTMENT’ control as indicated. When the
temperature has been set to the desired
position, carefully replace the Digital processor
lid and secure the fixing hand tight only.
28
Site conditions can affect temperature settings, installer to adjust as required.
ALL COPPER PIPE WORK MUST BE CROSS-BONDED AND CONNECTED TO
A RELIABLE EARTHING POINT.
!
TM
The centre of the riser rail stands 45mm from the wall. If this is not suitable, the
spacers provided with the fixing brackets will increase the depth to 70mm from
the wall.
!
Ensuring the rail assembly has been passed through the hole in the ceiling
and is at the desired height, mark the screw holes and remove the fixing
bracket.
13
Prepare suitable fixings and slide the fixing bracket back over the rail onto
the support pillar. Secure to the wall using the screws provided.
14
Slide the fixing bracket over the rail onto the
support pillar and repeat the above fixing
procedure.
16
The ceiling plate cannot be sited against an
uneven surface. If there is coving or an
alternative obstruction, please ensure the entry
hole is neat and unobtrusive; otherwise the
inner tube could be visible within the showering area.
If the ceiling height is over 2.4m (8ft), a Digital riser rail extension kit will be
required. Contact our Customer Service Department to purchase a riser rail
extension kit (part no: 223217).
!
Connect the low voltage data cable into the
socket adjacent to the temperature adjuster
as indicated on the label. Feed the cable out of
the processor box ensuring it is correctly
routed within the data cable channel.
22
A further data cable socket has been provided
for use with the secondary Digital remote
control or Digital diverter. This can be accessed by carefully snapping and
removing the entry pillar and connecting the cable as described above.
!
Ensuring the hose washer is in the correct
position, depress the anti-swivel locking button
on the handset and secure the handset to the
hose, then place the handset into the handset
holder.
25
Supply
Vent and draw-off
pipe to hot water
Hot water cylinder
Connect
‘A’ or ‘B’
Cold feed
to cylinder
B
A
NB: THE BASE OF THE PROCESSOR
MUST BE SITED NO HIGHER THAN
THE BASE LEVEL OF THE CISTERN
10m
max
Digital
shower
control
Supply
Pressure
reducing valve
if required
10m
max
Digital
shower
control
Supply
Hot water
cylinder
10m
max
Digital
shower
control
10m
max
Digital
shower
control
Central
heating
boiler
Supply
Supply
Vent and draw-off
pipe to hot water
Underside of cistern
Hot water
cylinder NB: 1.5 bar MINIMUM pump rating
Cold feed
to cylinder
Connect
‘A’ or ‘B’
B
A
10m
max
Digital
shower
control
Typical combination boiler installation
(Compatible with HP/Combi processor)
Typical HP system installation
(Compatible with HP/Combi processor)
Typical thermal storage unit system installation
(Compatible with HP/Combi processor)
Typical gravity system installation
(Compatible with Gravity pumped processor)
Typical pumped system installation
(Compatible with HP/Combi processor)
Quartz exposed guide V3:Quartz Exposed Install 9/1/14 14:52 Page 2
18
Carefully slide the fixing bracket over the rail onto the support pillar.
19
Ensuring the rail assembly has been passed through the hole in the ceiling and is at the desired
height, mark the screw holes and remove the fixing bracket.
20
Prepare suitable fixings and slide the fixing bracket back over the rail onto the support pillar.
Secure to the wall using the screws provided.
Place the upper rail bracket support pillar into the desired location
ensuring that both the hose restraint and the Aqualisa Pinch Grip™
holder are below the rail wall bracket.
21
Slide the fixing bracket over the rail onto the support pillar and repeat
fixing procedures 18-20.
22