4
MODEL 383
5. Unscrew impeller screw (9) and remove washer (9A), gasket
(9B) and seal washer (9C).
6. Slide impeller (11) and impeller key (12) from the shaft.
Remove O-ring (10).
7. Wearing ring(s) (7 & 16) are pressed into their housings
with an interference fit and must be removed with a puller if
new rings are required.
8. Remove capscrews (65), gland clamps (22), and gland
halves (23).
9. Unscrew remaining capscrews (41) and remove cover
assembly (26).
10. Shaft sleeve (25) is slip fit on the shaft and should be easily
removed unless the pump has been in service for a long
time. In this case, it may be necessary to use a puller. Take
care to prevent damaging the surface of the sleeve. Replace
the sleeve if it is grooved from wear.
11. The packing (28) and lantern ring (29) (if used) must now be
removed from the packing box of cover (26), and the cavity
thoroughly cleaned to allow new packing to fit properly. The
throat of cover (26) should be checked for excessive wear.
12.If necessary, unscrew capscrews (32) and remove bracket
(35) from motor.
REASSEMBLY:
Reassembly will generally be in reverse order of disassembly. If
disassembly was not complete, use only those steps related to
your particular repair program.
1. Replace wear ring(s) (7 & 16) in casing (6) and cover (26).
Rings should not be hammered into place. Use a press or
clamp the parts in a bench vice using wooden blocks to
protect the rings. It may be necessary to pin or dowel the
rings after assembly if the cover or casings has had rings
replaced before, since each reassembly can stretch or tear
metal and thereby loosen fits. If the facilities are available, it
is good practice to take a very light finish cut or to ream the
inside diameter of the casing rings after pressing to restore
roundness. When rings are pressed, they may get squeezed
out of shape.
2. If bracket (35) was removed, position the motor and secure
with capscrews (32). Tighten screws evenly to assure proper
alignment.
3.Place one ring of packing (28) into cover (26). On
successive rings of packing, stagger the packing joints to
prevent excessive leakage though the packing box. If lantern
ring (29) is used, place a second ring of packing (28) into the
cover before installing lantern ring.
There must be two (2) rings of packing in front of lantern
ring (29) to assure proper alignment between the lantern
ring and the sealing tube connection (1) in the cover (26).
Install remaining packing rings (28). Each ring should be
tapped firmly in place with a wood or metal bushing.
4. Slide the sleeve (25) through the packing making sure the
pin end of the sleeve (25) is in the cover side opposite the
gland halves (23).
5. Replace gland halves (23) and place gland clamps (22) over
capscrews (65). Tighten capscrews (65) finger tight into
cover assembly (26).
NOTE:
The slots in gland halves (23) should be diagonal to pump
horizontal center line.
6. The cover assembly (26) as a unit may be replaced onto
the motor shaft. Align key groove to facilitate impeller
reassembly. The cover is held to motor bracket (35) by
capscrews (41). These should be installed and tightened at
this time.
7. Carefully place O-ring (10) on motor end of impeller (11).
Assemble key (12) and impeller (11) to motor shaft. Secure
impeller with gasket (9B), washer (9A), seal washer (9C),
and impeller screw (9).
8. Install the pipe plug (74) in the pump casing (6). Position
a new gasket (8) on casing (6). Lower bracket, cover, and
motor assembly onto casing and secure with capscrews (50).
9. If provided, replace compression fittings (1 & 2), ball valve
(75), and tubing (3).
10. Secure suction and discharge piping to the pump. Make sure
to install gaskets on flanged connections.
11. Connect electricity to the motor.
12.Read carefully the sections of the manual titled
INSTALLATION and OPERATION.
STARTING PUMP AFTER REASSEMBLY:
Do not start pump until all air and vapor have been bled and
until making sure that there is liquid in the pump to provide the
necessary lubrication for the packing.
When the pump is returned to service, additional care must
be given to packing box to ensure a proper packing life. It is
necessary to allow 60–120 drops leakage per minute through the
packing for lubrication purposes. If the flow rate is other than
this, the capscrews should be either loosened or tightened
one quarter turn at a time to acquire the correct leakage (both
capscrews must be turned equally to prevent cocking of the
gland). It will take approximately ten minutes at anyone gland
setting before the leakage rate will stabilize. When in doubt,
choose the greater leakage rate since overly tight packing will
ruin not only the packing, but the sleeve as well.
Warning: Lifting Hazard
The motor and pump assembly may be very heavy. Use
extreme caution and safe lifting equipment during the lifting
procedure. Failure to follow these instructions could result
in serious personal injury, death or property damage.
CAUTION