5a Switching on external power supplies
Switch on external power supplies in the following sequence:
disk enclosures → controller enclosure → switches (for a SAN) → application server.
Checking cable connections
4a Checking device installation
4b
Check Item Normal Abnormal
Controller
enclosure The device sits stably on the guide rails
without displacement.
Screws are properly secured.
The device slants or cannot be detected.
Screws are loose or have fallen off.
Disk enclosure
Check Item Normal Abnormal
Ground cable, optical
fiber cable, mini SAS HD
electrical cable/optical
cable, network cable,
and serial cable
The cable is fully inserted and secured. The cable is loose or disconnected.
AC power cable
The AC power cables for each controller
enclosure or disk enclosure are connected to
two separate power supplies for redundancy.
The AC power cables are secured with
plastic buckles.
The AC power cables for each controller
enclosure or disk enclosure are
connected to the same power supply.
The AC power cables are not secured
with plastic buckles.
DC power cable
The OT terminal of the black cable
connects to the RTN (+) terminal and the
OT terminal of the blue cable connects to
the NEG (-) terminal.
The OT terminal of the blue cable
connects to the RTN (+) terminal and
the OT terminal of the black cable
connects to the NEG (-) terminal.
4 Checking Hardware Installation
5 Powering On the Storage System
To avoid electric shocks, do not wear an ESD wrist strap when the storage system is powering on.
Do not adjust mini SAS HD electrical cable/optical cable connections between enclosures after power-on.
Otherwise the storage system may become abnormal.
Follow the correct power-on sequence of the storage system: Turn on the external power supplies to each
device (disk enclosures first and then controller enclosures). → Press the power buttons on the controller
enclosures. → Switch on the switch. → Switch on the application servers.
Follow the correct power-off sequence of the storage system: Stop host services. → Press and hold down the
power buttons on the controller enclosures until the system is completely powered off (five seconds). →
Disconnect the controller enclosures and the disk enclosures from their power supplies.
The power-on process requires 5-15 minutes. Then the disk enclosures start power-on automatically.
Scenario 1 Turning on the switches of the power
distribution box Scenario 2 Turning on the switch of the PDU
Front
Rear Front
Rear
20
NOTICE